- Court
- High Court of Judicature at Allahabad
- Decided
- 1 November 2023
- Case no.
- WRIC 33406/2023
Judgment
Court No. - 40 Case :- WRIT - C No. - 33406 of 2023 Petitioner :- Smt. Ekta Varsney And 2 Others Respondent :- State Of U.P. And 3 Others Counsel for Petitioner :- Prem Shankar Pandey Counsel for Respondent :- C.S.C.,Baleshwar Chaturvedi Hon'ble Mahesh Chandra Tripathi,J. Hon'ble Prashant Kumar,J.
¶1Heard learned Counsel for the petitioners, Sri S.C. Upadhyay, learned Standing Counsel for the State respondents and Sri Baleshwar Chaturvedi, learned counsel for electricity department.
¶2The instant writ petition under Article 226 of the Constitution of India has been filed for direction to the electricity department to provide new electricity connection to the petitioner within stipulated period.
¶3Learned counsel for the petitioners submits that the petitioners have purchased flats from the housing society, M/s Brijesh Extension Pvt. Ltd. and applied for electric connection. He further submits that even if entire formalities have been completed but the respondent authorities are not providing electricity connection to the petitioners. He also submits that the petitioners have also represented the matter before the respondent no.3 but nothing has been done till now.
¶4Sri Baleshwar Chaturvedi, learned counsel for electricity department submits that in case, have any grievance, they can approach the Chief Engineer, Agra Region, Dakshinanchal Vidyut Vitran Nigam Limited, who will definitely redress the grievance of the petitioners.
¶5Considering the facts and circumstances of the case, without going into its merit and with the consent of the parties, the writ petition is disposed of permitting the petitioners to move a fresh representation before the respondent no.3, Chief Engineer, Agra Region, Dakshinanchal Vidyut Vitran Nigam Limited ventilating their grievance within a period of two weeks from today. In case, any such representation is moved, we hope and trust that the grievance of the petitioners would be redressed expeditiously, as per law within a period of four weeks from the date of production of a certified copy of this order. Order Date :- 2.11.2023 S.P. High Court of Judicature at Allahabad
Source: High Court of Judicature at Allahabad, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.