Court No. - 21 Case :- WRIT - C No. - 42374 of 2023 Petitioner :- M/S K.T. Constructions Respondent :- State Of U.P. And 4 Others Counsel for Petitioner :- A Kumar Srivastava,Anand Kumar Upadhyay Counsel for Respondent :- C.S.C.,Shyam Mani Shukla Hon'ble Manoj Kumar Gupta,Acting Chief Justice Hon'ble Donadi Ramesh,J.
¶1Heard Shri Anand Kumar Upadhyay, learned counsel for the petitioner and learned Additional Chief Standing Counsel for the State.
¶2The grievance of the petitioner is that its payments for the works executed between 2020 and 2022 in pursuance of various work orders is not being honoured by the respondent-Nagar Nigam. The representation of the petitioner dated 18.11.2022 is stated to be pending. It is submitted that work completion certificate has already been issued.
¶3Having regard to the facts of the case and submissions made, we dispose of the instant petition with a direction to the respondent no.3 to examine the claim of the petitioner and take appropriate decision in accordance with law within 8 weeks from the date of communication of the instant order alongwith photocopy of the representation dated 18.11.2022. (Donadi Ramesh, J.) (Manoj Kumar Gupta, A.C.J.) Order Date :- 8.12.2023 Ankit. High Court of Judicature at Allahabad
Source: High Court of Judicature at Allahabad, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.