Court No. - 21 Case :- WRIT - C No. - 38799 of 2023 Petitioner :- Ambey Enterprises Respondent :- State Of U.P. And 3 Others Counsel for Petitioner :- Sanjeev Kumar Sharma Counsel for Respondent :- C.S.C.,Awadhesh Kumar Malviya Hon'ble Manoj Kumar Gupta,Acting Chief Justice Hon'ble Kshitij Shailendra,J.
¶1The prayer of the petitioner is for a direction to the respondents to make payment against the bills raised by him for the work done under a contract relating to cleaning and lifting of garbage from the municipal limits.
¶2Learned counsel for the petitioner submits that on representation made by the petitioner, District Magistrate , Ghazipur vide order dated 30.3.2022 directed the Executive Officer, Nagar Maha Palika to enquire into the matter and make payment according to Rules. However, no payment has been made so far.
¶3Sri A.K. Malviya, learned counsel appearing on behalf of respondent no. 4, states that the claim of the petitioner would be considered by respondent no. 4.
¶4Accordingly, the petition is disposed of with direction to respondent no. 4 to pass a speaking order on the representation of the petitioner dated 1.3.2023 (annexure-6) within a period of six weeks from the date of communication of the instant order along with photocopy of the representation. (Kshitij Shailendra, J.) (Manoj Kumar Gupta, A.C.J.) Order Date :- 15.12.2023 Jaideep/- High Court of Judicature at Allahabad
Source: High Court of Judicature at Allahabad, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.