Judgment
Court No. - 3 Case :- WRIT - C No. - 9871 of 2023 Petitioner :- Manoj Singh Respondent :- State Of U.P. Thru. Prin. Secy. Energy Civil Secrt. Lko. And Others Counsel for Petitioner :- Alok Kumar Srivastava Counsel for Respondent :- C.S.C.,Aprajita Bansal Hon'ble Vivek Chaudhary,J. Hon'ble Manish Kumar,J.
¶1Heard Sri Alok Kumar Srivastava, learned counsel for the petitioner, learned Standing Counsel for the State and Sri Aprajita Bansal Manish Jauhari, learned counsel for the respondent nos. 2 to 3.
¶2Learned counsel for the petitioner submits that as per recovery notice / final assessment order, Rs.6,35,939/- was demanded, against which the petitioner has already deposited Rs.3,00,000/- and he is ready to pay Rs.2,00,000/- within a period of one week, so the electricity connection may be restored to him, which was earlier disconnected by the Department. It is further submitted that for the rest of the amount, the reply of the petitioner may be considered and decided by the Executive Engineer.
¶3Learned counsel for the Vidyut Parichan Khand, has no objection to the prayer made by the learned counsel for the petitioner.
¶4A perusal of assessment order shows that the reply of petitioner is nowhere considered in the same. In reply petitioner had submitted that he was having valid electricity connection and no checking was conducted in presence of petitioner nor anything was recovered. There is absolutely no consideration of reply of petitioner in the final assessment order. Hence, respondents may be restrained from making any recovery on the basis of final assessment order.
¶5In case, the petitioner deposits Rs.2,00,000/- and submits his objection to the Executive Engineer, Vidyut Parichan Khand, District Raebareli-Respondent No.3 within a week from today, the Respondent No.3 shall consider and decide the same within two weeks thereafter and restore the electricity connect to the petitioner forthwith. The final demand raised against the petitioner shall be subject to the final order passed by the Executive Engineer.
¶6With the aforesaid, the writ petition is disposed of. . [Manish Kumar,J.] [Vivek Chaudhary,J.] Order Date :- 8.11.2023 S. Kumar High Court of Judicature at Allahabad, Lucknow Bench High Court of Judicature at Allahabad, Lucknow Bench
Source: High Court of Judicature at Allahabad, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.