Court No. - 3 Case :- WRIT - C No. - 11376 of 2023 Petitioner :- Smt. Sanju Maurya Respondent :- State Of U.P. Thru. Prin. Secy. Deptt. Of Energy , Civil Secrt. Lko. And 5 Others Counsel for Petitioner :- Om Shankar Tiwari,Bijendra Kumar Mishra Counsel for Respondent :- C.S.C.,Amit Kumar Dwivedi Hon'ble Vivek Chaudhary,J. Hon'ble Manish Kumar,J.
¶1Heard learned counsel for parties.
¶2Petitioner has approached this Court for a mandamus directing respondent-Power Corporation to provide a new electricity connection to the petitioner.
¶3Learned counsel for respondent-Power Corporation states that in case petitioner provides an indemnity bond/security as per the provisions of the Act, electricity connection shall be provided to her.
¶4Learned counsel for petitioner states that the required indemnity bond/security would be submitted by petitioner within a period of two weeks from today. In case such indemnity bond/security is submitted by petitioner, the respondent-Corporation shall provide the electricity connection to the petitioner within a period of two weeks from the date, such documents are provided by petitioner.
¶5With the aforesaid direction, present writ petition stands disposed of. [Manish Kumar,J.] [Vivek Chaudhary,J.] Order Date :- 22.12.2023 Sachin High Court of Judicature at Allahabad, Lucknow Bench