- Court
- High Court of Judicature at Allahabad
- Decided
- 18 December 2024
- Bench
- Rajan Roy, Brij Raj Singh
- Case no.
- WRIC 10621/2024
Follow Allahabad High CourtFollow Rajan RoyFollow Brij Raj Singh
Judgment
Court No. - 2 Case :- WRIT - C No. - 10621 of 2024 Petitioner :- M/S R.K. Engineering Thru. Sole Proprietor Rakesh Kumar Sainik Respondent :- State Of U.P. Thru. Prin. Secy. P.W.D Lko. And 3 Others Counsel for Petitioner :- Pradeep Kumar Verma,Devendra Bahadur Yadav Counsel for Respondent :- C.S.C. Hon'ble Rajan Roy,J. Hon'ble Brij Raj Singh,J. Heard. We have perused the orders dated 26.07.2024 and 23.07.2024 passed in pursuance to the order dated 19.03.2024 passed in Writ-C No.2643 of 2024. Certain formalities are mentioned therein as having been not completed by the petitioner. However, learned counsel for the petitioner says that said formalities have been completed subsequently. If it is so then opposite party no.2 shall get the facts verified and if he finds that all the formalities are complete and there are any dues to which the petitioner is entitled, he shall do the needful as per law but with expedition say within one month. Accordingly, the petition is disposed of. (Brij Raj Singh,J.) (Rajan Roy,J.) Order Date :- 18.12.2024 Shanu/- High Court of Judicature at Allahabad, Lucknow Bench
Source: High Court of Judicature at Allahabad, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.