- Court
- High Court of Bombay
- Decided
- 14 December 2023
- Bench
- G.S. Patel, Kamal Khata
- Case no.
- CAW 13/2023
Judgment
ORDER DT. 12.12.2023 OF HON'BLE BOMBAY HIGH COURT OBSERVATIONS MADEBY THE ADTP
(NMMC) during site visit at 3:00 PM on dt.
13.12.2023
(a) Whether any part of the building F-4 redevelopment is beyond 1269.848 sq.mtrs. As per the notional plot boundary shown in as built drawings submitted by architect part area of Otla measuring around 34.7 mtr. X 2.673 mtr =
92.649 Sq.mtr. is beyond the area of 1269.848 sq.mtrs.
(b) Whether in the construction of Building F-4 the necessary marginal open spaces have been maintained at the ground level, and, if not, the extent of the shortfall. Yes, necessary marginal open spaces at ground level have been maintained as per the sanctioned plans. Table showing required marginal open space as per erstwhile regulations and existing available marginal open spaces on site are attached here with.
(c) Correspondingly, whether at the ground floor level there is an expansion of the construction beyond 1269.848 sq.mts. Yes as mentioned in point no 1 above part area of Otla measuring around 34.7 mtr. X
2.673 mtr = 92.649 Sq.mtr. Is beyond the area of 1269.848 sq. mtrs.
(d) For completeness, whether there are any As per the notional plot boundary shown
Sr. No. ISSUES TO BE INSPECTED BY THENMMC VIDE ORDER DT. 12.12.2023 OF HON'BLE BOMBAY HIGH COURT OBSERVATIONS MADEBY THE ADTP
(NMMC) during site visit at 3:00 PM on dt.
13.12.2023 projections at any higher floors that project beyond 1269.848 Sq. mtrs. of the notional plot boundary. in as built drawings submitted by the architect it is observed that there are projections beyond the dimensions forming area of 1269.848 Sq. mtrs.
¶10To avoid all ambiguity a scan of this document NMMC-1 is appended to this order.
¶11Now the report shows two things: (1) at the ground floor level the otla or elevated portion above ground has been extended by Building F-4 to occupy an area of 92.649 sq mts, i.e., 34.7 mts in length and 2.673 mts in depth. To leave no ambiguity about this, Mr Dande tenders a photograph of the frontage. On this, his officers have in court marked in red the distances and shown the alignment that is required to be removed to bring the otla into compliance. The scan of the photograph is taken on record and marked as "NMMC-2". It is part of the annexures to this order.
¶12The otla is elevated. We asked Mr Dande whether in maintaining the distance it was the elevated portion that would meet the outermost boundary or whether the lowest level of the second step would have to meet that boundary. He clarified on instructions
that it was the top level of the otla that had to meet the boundary. There are then two steps down to the road or ground level. We accept this.
¶13On the previous occasion, we were variously told also that Building F-4 had at the podium parking level and at some other levels projected outwards so that the outward projections at the upper level were beyond the notional plot boundary, thus rendering the space beneath it unusable and not as a common area.
¶14It is for this reason that we framed question (d) in paragraph 18 of our 12th December 2023 order. We noted the submissions specifically in paragraph 13 of that order. This was repeated before us at least four times.
¶15The present report of the NMMC shows this to be entirely untrue. The report is signed by one Somnath Kekan, the ADTP. He is personally present in court. He was present on site when the inspection was taken.
¶16We wholly deprecate the attempt by Mr Datar on behalf of the Rainbow Association to now question this report. The very suggestion seems to us to be an argument of desperation. After all, we began on 12th December 2023 by taking the figures from the CIDCO report and which we were invited to do by Mr Bapat on behalf of the Rainbow Association itself. We then took that to the next logical step by acting on the submissions that were made before us and, instead of demanding further Affidavits ordered a site
inspection to ascertain the correct factual position on ground. This was done. It is now yet being argued that all of this is either inconsequential or somehow incorrect and the writ court must yet engage in some ferreting of some abstract numbers that even the Rainbow Association's Petition cannot possibly justify or maintain.
¶17To be perfectly clear, the Association's Writ Petition does not tell us specifically or deal with the notional plot boundary as we find them in the CIDCO report. It does not deal with the footprint of the actually reconstructed/redeveloped Building F-4. It does not even attempt to show how there is the slightest transgression. It only says that there is something wrong and something amiss and therefore permission should not be granted. On this basis, in Writ Petition No 12714 of 2015 the following reliefs are sought: "a) Rule be issued and record and proceedings be called for; b) That this Hon'ble Court be pleased to issue a writ of certiorari or a writ in the nature of certiorari or any other appropriate writ, order or direction under Article 226 of the Constitution of India, calling for all the records and materials in respect of the Impugned Notification dated 4/2/2015 (Exhibit "M" hereto) and related thereto, issued by the Respondent No.1 and after going through the legality and propriety thereof, quashing and setting aside the same as being illegal and without authority of law; c) That this Hon'ble Court be pleased to issue a writ of certiorari or any appropriate writ, order or direction in the like nature of Article 226 of the Constitution of India:
i) Calling for the records and proceedings from the Respondent No.3 and after going through the
same be please to quash and set aside the order dated 29/10/2015 being Exhibit "K" to the Petition.
ii) To quash and set aside the order dated 30/10/2015 passed by the Commissioner Navi Mumbai Municipal Corporation being Exhibit "L" to the Petition. d) That this Hon'ble Court be pleased to issue a writ of Mandamus or any appropriate writ, order or direction in the like nature of Article 226 of the Constitution of India: i. To direct the Respondent No.3 to cancel the Commencement Certificate dated 8/9/2010 granted to the Respondent Nos.4 to 23 and to cancel the amended Commencement Certificate dated 17/11/2015 granted to the Respondent Nos.4 to 23 being Exhibit "C" and Exhibit "N". ii. To direct the Respondent No.2 to take immediate and necessary action against the Respondent Nos.4 to 23; iii. To direct the Respondent Nos.2 and 3 to demolish the unauthorized construction carried out by the Respondent Nos.4 to 23;
¶18Having regard to what has transpired now in court, not one of these reliefs can be granted in view of the Affidavits that are now before us and particularly in view of the reports and the photograph that have been tendered to us pursuant to our own direction.
¶19Finally, we have today an affirmed undertaking by the Petitioner No 1 on behalf of all the Petitioners in Writ Petition No 631 of 2023 saying that the portion that has been found by the NMMC to be in excess will be demolished within one week from
today. We accept that statement as an undertaking to the court. A copy of this undertaking, though affirmed, is to be filed in the Registry as an annexure to an Affidavit. In the meantime, a copy of the two-page undertaking is also annexed to this order.
¶20Mr Datar on behalf of the Rainbow Association expresses two concerns. The first, as we understand it, is that this order should not be seen as a permission or as a license to other societies to occupy, use or encroach upon common areas of the condominium/Association because the lease is in favour of the Association. That submission, though correctly placed, is of little assistance because saying something like this in the abstract can yield no meaningful order. It is for the Association to ensure that no constituent building or member occupies or uses a common area. The concept of notional plot boundaries and what each of the six buildings may or may not use comes from a CIDCO report relied on before us by the Rainbow Association itself. There is no turning back on that now. But nothing we have said in this order in regard to Mr Kapadi or the other Petitioners in Building F-4 can possibly be seen as a permission to anyone to exclusively use common areas.
¶21We also do not know what is to be made about the apprehension expressed in regard to further redevelopment of other buildings. It seems to us extremely strange that the Association claims some rights independent of its constituent buildings. It cannot. It exists for and only because of the constituent buildings. It has no separate or severable rights in regard to any open areas. Common areas mean commons areas shared by the buildings and
has nothing to do with the condominium as a separate legal entity except in ensuring enjoyment in common of all common areas. That is all there is to it.
¶22In light of this, Writ Petition No 12714 of 2015 is dismissed.
¶23Writ Petition No 11380 of 2015 filed by the occupant of Building F-4 is infructuous in view of the filing of the subsequent Writ Petition No 631 of 2023.
¶24In Writ Petition No 631 of 2023, there are the following reliefs: "(a) This Hon'ble Court be pleased to issue a Writ of Certiorari or any other Writ or order in the nature of Writ of Certiorari or any other Writ or order calling upon the records, papers and proceedings in relation to the application for regularisation filed by the Petitioners and the order dated 17th March, 2022 passed by Respondent No.2;
(b) This Hon'ble Court be pleased to issue a Writ of Mandamus or any other Writ or order in the nature of Writ of Mandamus or any other Writ or order directing Respondent No. 2 to pass an appropriate order regularising the construction carried out by the Petitioners;
(c) Without prejudice to the above, this Hon'ble Court be pleased to direct Respondent No. 1 to state on oath its response/issue clarification or otherwise appropriately reply to the condition required by Respondent No. 2 to be met for regularisation of Petitioners' construction viz. determining the share of the residents of building F-4 on the subject plot i.e. determining Petitioners' share out of
the leased plot and thereafter, this Hon'ble Court be pleased to direct Respondent No. 2 to decide the regularisation application of the Petitioners on the basis of such response of Respondent No. 1;
¶25In this case, it is sufficient to make an order in terms of prayer clause (b). We clarify that this means that the NMMC will proceed to issue all necessary permissions and sanctions including Occupancy Certificates ("OC") for redeveloped Building F-4. It is not to insist upon a separate "lease" or title document in regard to Building F-4, its footprint or its notional boundaries because obviously there can be no such thing. As Mr Datar has never failed to remind us, it is the Association that is the lessee of the entire unsubdivided plot.
¶26Therefore, any orders by the authorities demanding a copy of the lease deed, in view of this litigation, are quashed and set aside.
¶27Building F-4 does not yet have a water supply connection. Mr Kamdar states that the necessary application for a water connection will be made within three weeks from today. It is to be processed as expeditiously as possible and in accordance with law and subject to payment of all necessary charges and fees and, in any event, within three weeks of the application being made.
¶28In parallel, and subject to the water connection being granted (for we have held that occupancy requires a municipal water connection) it is open to the Petitioners, AI Kapadi and others to submit an application for an OC.
¶29Mr Kamdar confirms that a fire NOC is obtained. If necessary, this may require to be re-validated or a copy may be submitted to the NMMC.
¶30In parting we deal with Interim Application No 2669 of 2023. This is filed by an outsider who was joined as a party to this Writ Petition, in our view wrongly. This is not a Public Interest Litigation. He has admittedly no interest in the larger plot or in the individual plot. He may have gained orders in other Public Interest Litigations, but we believe it is an extraordinarily dangerous precedent to allow outsiders to intervene in privately held property matters that do not concern them in this fashion. We are saying nothing about the Applicants bona fides or credentials but we are extremely uneasy about the kind of precedent this sets. This branch of the law has received at least one order from the Supreme Court in Ramesh Hirachand Kundanmal v Municipal Corporation of Greater Bombay & Ors.1 Merely because a party believes that he has something of value to add or contribute is no reason to insist upon his joinder or to allow his participation in proceedings that do not concern him directly. To put it differently, had these been suits before a civil court, there was not the slightest possibility of this Applicant being able to be impleaded. If it could not be done in a suit, we do not see why it should be permitted in a Writ Petition that is not a PIL. The Application is rejected.
¶31Mr Kamdar's other submission which we have not thought it necessary to deal with is on the question of equities because he
(1992) 2 SCC 524.
argues that there are at least five NOC's from the Rainbow Association as also a demand from the Association that the occupants of Building F-4 form their own society. The submission was that it is not open to the Association now to question the formation of a society or to question the notional separation boundaries of Building F-4.
¶32In light of what we have held, it is not necessary to enter into this aspect of the matter.
¶33The Petitions are disposed in these terms. No costs.
¶34All other Interlocutory Applications stand disposed of.
(Kamal Khata, J) (G. S. Patel, J)
_________________ _________________ _________________ _________________ _________________ _________________
Case details
Parties and counsel
Arun IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION WRIT PETITION NO. 11380 OF 2015 WITH INTERIM APPLICATION NO. 2669 OF 2023 IN WRIT PETITION NO. 11380 OF 2015 WITH CIVIL APPLICATION NO. 13 OF 2023 IN WRIT PETITION NO. 11380 OF 2015 WITH INTERIM APPLICATION NO. 3265 OF 2019 IN WRIT PETITION NO. 11380 OF 2015 AI Kapadi & Ors …Petitioners ~ versus ~ City And Industrial Development Corporation of Maharashtra Ltd & Ors …Respondents ARUN RAMCHANDRA SANKPAL by ARUN RAMCHANDRA SANKPAL Date: 2024.01.29 10:02:30 +0530 WITH WRIT PETITION NO. 631 OF 2023 AI Kapadi & Ors …Petitioners ~ versus ~ City And Industrial Development Corporation of Maharashtra Ltd & Ors …Respondents WITH WRIT PETITION NO. 12714 OF 2015 WITH CIVIL APPLICATION NO. 935 OF 2016 IN WRIT PETITION NO. 12714 OF 2015 Rainbow Flat and Shop Owners Association & Ors …Petitioners ~ versus ~ State of Maharashtra, through the Principal Secretary & Ors …Respondents APPEARANCES for the petitioner in WP/12714/2015 and for the respondent WP/11380/2015 & WP/631/2023 Mr Rajesh Datar, with Pralhad Paranjape, Gaurav Gawande, Druti Datar & Rutuja Bapat, i/b Manish Kelkar. for the petitioner in WP/631/2023 Mr SU Kamdar, Senior Advocate, with Mr Chetan Kapadia, Senior Advocate, with Jagdish G Aradwad (Reddy). for respondent- NMMC. Mr Tejesh Dande. for respondent- CIDCO in all matters Mr GS Hegde, Senior Advocate, i/b PM Bhansali. for respondent- State in all matters Mrs MP Thakur, AGP. for respondent no. 4 in WP/11380/2015 7 for the applicant in IA/2669/2023 in WP/11380/2015 Mr Sandeep S Thakur. present in court Mr Somnath Kekan, ADTP and Mr Umesh Patil, Deputy Engineer, NMMC. CORAM : G.S.Patel & Kamal Khata, JJ. DATED : 14th December 2023 PC:- (Per GS Patel J):- 1. On 12th December 2023 we passed the following order: "1. After several rounds of hearings and filing of Affidavits it seems to us that the entire controversy in this matter can be resolved if we direct a site inspection and have the results of that site inspection before us. 2. In Writ Petition No 631 of 2023 there are 18 Petitioners. They purchased tenements in a building called F-4 on Plot No 6 in Vashi, Navi Mumbai. The City and Industrial Development Corporation of Maharashtra ("CIDCO") is the lessor/owner of the plot in question. The 4th Respondent is the Rainbow Flat & Shop Owners Association Condominium and is said to be an association of several such buildings. 3. The entirety of the plot is not formally sub-divided. This necessarily means that there are common open area spaces and that the aggregate plot area is pro-rata apportioned between the various buildings. 4. Building No F-4 on Plot No 6 was said to be in a dilapidated condition. Redevelopment permission was sought and was granted and a building of ground plus 16 floors has today come up. 5. The owners of tenements in the old building are not yet in occupation inter alia on account of these litigations that are pending since 2015/2019. 6. The Association maintains through Mr Bapat, Learned Senior Advocate, that the redeveloped building F- 4 has consumed or transgressed upon what Mr Bapat calls "common areas", i.e., the construction by the Petitioners extends beyond the proportionate area of that building. In particular, he maintains on the strength of a report from CIDCO at pages 200 and 201 that there is an impermissible lateral projection at the second floor level and that an elevated portion of the car parking podium has projected outwards. 7. Stated in these generalities, the submissions are of very little assistance and will not travel the necessary distance to an effective disposal of the matter. Above all, we are mindful that we should not be even inadvertently drawn into what are essentially disputed questions of fact no matter how long these Petitions have been pending before us. 8. In a matter of building construction, indeed, there should be very little scope for dispute about what actually exists on site. Whether what is bui
Source: High Court of Bombay, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.