- Court
- High Court of Delhi
- Decided
- 21 November 2024
- Bench
- Vikas Mahajan
- Case no.
- O.M.P.(MISC.)(COMM.) 913/2024
Judgment
O R D E R %
21.11.2024 I.A. 45723/2024 (under Section 151 CPC seeking exemption from filing originals/certified copies and true typed copies of the documents)
¶1Allowed, subject to all just exceptions.
¶2The petitioner shall file legible and clear copies of exempted documents, compliant with practice rules before the next date of hearing. O.M.P.(MISC.)(COMM.) 913/2024
¶3This is a petition filed under Section 29A of the Arbitration and Conciliation Act, 1996 seeking extension of the learned sole Arbitrator for a period of three months to make and publish the award.
¶4The learned counsel appearing on behalf of the petitioner submits that the arguments have already been concluded.
¶5In view of the above, issue notice. The learned counsel appearing on behalf of the respondent accepts notice. This is a digitally signed order. 6. He also affirms the aforesaid position and submits that he has no objection in case the present petition is allowed.
¶7I am satisfied that the sufficient cause has been shown.
¶8The mandate of the learned Arbitrator is further extended for a period of three months from 01.12.2024.
¶9The petition is disposed of. VIKAS MAHAJAN, J NOVEMBER 21, 2024 N.S. ASWAL This is a digitally signed order.
Case details
Parties and counsel
* IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 913/2024 M/S SHRI RAM ELECTRICAL WORKS .....Petitioner Through: Mr. Atul Kumar, Adv. versus POWER GRID CORPORATION OF INDIA LTD......Respondent Through: Mr. Pranay Kishore Mishra, Adv. CORAM: HON'BLE MR. JUSTICE VIKAS MAHAJAN
Source: High Court of Delhi, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.