A - , : ,; V IN THE HIGH COURT OF DELHI AT NEW DELHI Reserved on :

21.09.2011 Pronounced on:

24.10.2011 + w.p.rc^ 4347/2011. 4559/2011. 4593/2011. 4610/2011 4650/2011. 4651/2011. 4827/2011. 4923/2011. 5024/2011 5028/2011. 4775/2011, 5247/2011. 5254/2011. 5255/2011. 5257/2011. 5258/2011. 5261/2011. 5262/2011. 5263/2011-5264/2011. 5277/2011. 5292/2011. 5312/2011. 5317/2011. 5402/2011. 5403/2011. 5405/2011. 5408/2011. 5410/2011. 5411/2011. 5413/2011. 5418/2011. 5423/2011. 5444/2011. 5473/2011. 5484/2011. 5485/2011. 5497/2011. 5498/2011. 5503/2011. 5504/2011. 5505/2011. 5506/2011. 5507/2011. 5508/2011. 5595/2011. 5614/2011. 5615/2011. 5616/2011, 5618/2011. 5627/2011, 5630/2011. 5631/2011. 5643/2011. 5645/2011. 5654/2011. 5656/2011. 5711/2011. 5717/2011. 5718/2011. 5728/2011. 5729/2011. 5731/2011. 5732/2011. 5737/2011. 5738/2011. 5739/2011. 5743/2011. 5761/2011. 578472011. 5785/2011. 5791/2011. 5794/2011. 5797/2011. 5798/2011. 5822/2011. 5911/2011. 5918/2011. 5928/2011. 5931/2011. 5933/2011. 5934/2011. 5935/2011. 5957/2011. 59S5/2011. 5966/2011. 5967/2011. 5968/2011. 5969/2011, 5970/2011. 5974/2011. 6096/2011. 6100/2011. 6101/2011. 6102/2O11« 6107/2011. 6108/211. 6114/2011. 6115/2011. 6116/2011. 6117/2011. 6118/2011. 6119/2011. 6120/2011. 6121/2011. 6122/2011. 6123/2011. 6144/2011. 6250/2011. 6270/2011. 6271/2011. 6449/2011. 6527/2011. 6528/2011, 6529/2011. 6530/2011. 6531/2011. 6532/2011. 6533/2011. 6534/2011. 6538/2011. 6555/2011. 6667/2011. 6668/2011. 6669/2011. 6670/2011. 6684/2011. 6701/2011. 5173/2011. 5051/2011. 5157/2011. 4649/2011. 4722/2011. 2601/2011. 2602/2011. 3052/2011. 3181/2011. 3185/2011. 3189/2011. 3196/2011. 4340/2011. 4342/2011, 4343/2011. 4344/2011. 4345/2011. 4349/2011. 4350/2011. 4352/2011. 4354/2011. 4356/2011. 4358/2011. 4359/2011. 4360/2011. 4361/2011. 4362/2011. 4363/2011. 4364/2011. 4365/2011. 4366/2011. 4367/2011. 4368/2011. 4369/2011. 4370/2011. 4371/2011 4372/2011. 4373/2011. 4374/2011. 4375/2011. 4377/2011, 4387/2011. 4388/2011. 4389/2011. 4391/2011. 4392/2011. 4393/2011. 4395/2011. 4396/2011. -21398/2011. 4398/2011. 4399/2011. 4400/2011. 4402/2011, 4404/2011. 4405/2011. 4406/2011. 4407/2011. * • *•' m tSm f 4408/2011. 4409/2011. 4410/2011. 4412/2011. 4413/2011. 4414/2011. 5341/2011. 4847/2011. 4859/2011. 4887/2011. 4990/2011, W.P.(C)4347/2011andconnectedmatters Page1 of8 Certify that the digital file and physical file have been compared and the digital data is as per the physical file and no page is missing. A \ (/• 5063/203.1. 5089/2011. 5099/2011. 5114/2011. 5115/2011. 5117/2011. 5129/2011. 5139/2011. 5144/2011. 6708/2011. 6799/2011. 6824/2011. 6825/2011. 6826/2011. 6827/2011. 6896/2011. 6901/2011. 6902/2011. 6903/2011. 6904/2011. 6905/2011. 6906/2011. 6907/2011. 6908/2011. 6909/2011. 6910/2011. 6917/2011. 6919/2011. 6920/2011. 6921/2011. 6922/2011. 6932/2011 and 5420/2011. m THE MATTERS OF MOHD. AZAD Petitioner In W.P.(C) 4347/2011 MOHD. ALAM Petitioner in W.P.(C) 4559/2011 KIRPAL SINGH Petitioner in W.P.(C) 4593/2011 SHAILENDER KUMAR Petitioner in W.P.(C) 4610/2011 SANJAY Petitioner in W.P.(C) 4650/2011 BABLU Petitioner in W.P.(C) 4651/2011 AMAR NATH SINGH Petitioner in W.P.(C) 482.7/2011 GANESH PRASAD Petitioner in W.P.(C) 4923/2011 BHUPAL SINGH Petitioner in W.P.(C) 5024/2011 SURENDER SINGH AND ORS. Petitioners in W.P.(C) 5028/2011 USHA Petitioner in W.P.(C) 4775/2011 RAKESH KUIMAR AND ORS. Petitioners in W.P.(C) 5247/2011 RAM DASS Petitioner in W.P.(C) 5254/2011 VISHAMBAR JHA Petitioner in W.P.(C) 5255/2011 DINESH KUMAR Petitioner in W.P.(C) 5257/2011 ANJU Petitioner in W.P.(C) 5258/2011 RAJESH C GUPTA AND ORS Petitioners in W.P.(C) 5261/2011 LAKHPATI AND ORS. Petitioners in W.P.(C) 5262/2011 SOHAN LAL AND ORS. Petitioners in W.P.(C) 5263/2011 KEDARI Petitioner in W.P.(C) 5264/2011 ARUN KUMAR ALIAS LUCKY Petitioner in W.P.(C) 5277/2011 MITHU LAL Petitioner in W.P.(C) 5292/2011 MOHD. ZAHID Petitioner in W.P.(C) 5312/2011 SHAKEEL AHMED Petitioner in W.P.(C) 5317/2011 NAND KISHORE Petitioner in W.P.(C) 5402/2011 RINKU KUMAR GUPTA Petitioner in W.P.(C) 5403/2011 HARJEET KAUR Petitioner in W.P.(C) 5405/2011 NARESH KUMAR RAO AND ORS Petitioners in W.P.(C) 5408/2011 RAJU ..... Petitioner in W.P.(C) 5410/2011 NABI HASAN Petitioner in W.P.(C) 5411/2011 HARENDER PRASAD Petitioner in W.P.(C) 5413/2011 BHUPINDER SINGH Petitioner in W.P.(C) 5418/2011 GOVIND SINGH AND ANR. Petitioners in W.P.(C) 5423/2011 BAL CHAND GUPTA Petitioner in W.P.(C) 5444/2011 MUNNA THAKUR @ RAMESH THAKUR Petitioner in W.P.(C) 5173/2011 W.P.(C) 4347/2Q11 and connected matters ANIL KUMAR AND ORS. SUNDER SINGH DHARAM VEER SINGH MAHESH PAL SINGH RAJ RANI DULI CHAND SHANTA RAM MAHENDER PAL PAWA^J-KUMAPv SXiMGW TARUN KUMAR RAVINDER KUMAR DINESH YADAV RAM BAHADUR ANIL KUMAR GUPTA RAM AVTAR SHANKAR LAL PADAM SINGH MEENA MOHD.HASMAT VIPIN PRASAD SUSHIL KUMAR GUPTA BABU KHAN VIJAY KUMAR SHASHI KUMAR PANDEY PREMA SINGH. PURAN CHAND OMKAR GUPTA KUMER RAJENDER BHAGNARAYAN YADAV KARAN VIR MATA PRASAD YADAV BABU LAL RAMESH CHAND LAXMI BHAGWAN SAHAI RAM NPA/AS NAVIN SINGH DHARAM RAJ YADAV VINOD KESHRI ANIL SINGH lUIRANJAN DEV KULDEEP SHANKLA SURENDER KHURANA @ NEERU SURESH BABU W.P.(C) 4347/2011 and connected matters Petitioners in W.P.(C) 5484/2011 . Petitioner . Petitioner . Petitioner . Petitioner . Petitioner . Petitioner . Petitioner . Petltloner- , Petitioner , Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner n W.P.(C) 5485/2011 n W.P.(C) 5497/2011 n W.P.(C) 5498/2011 n W.P.(C) 5503/2011 n W.P.(C) 5504/2011 n W.P.(C) 5505/2011 n W.P.(C) 5506/2011 S50Z12011 n W.P.(C) 5508/2011 n W.P.(C) 5595/2011 n W.P.(C) 5614/2011 n W.P.(C) 5615/2011 n W.P.(C) 5616/2011 n W.P.(C) 5618/2011 n W.P.(C) 5627/2011 n W.P.CC) 5630/2011 n W.P.(C) 5631/2011 n W.P.(C) 5643/2011 n W.P.(C) 5645/2011 n W.P.(C) 5654/2011 n W.P.(C) 5656/2011 n W.P.(C) 5711/2011 n W.P.(C) 5717/2011 n W.P.(C) 5718/2011 n W.P.(C) 5728/2011 n W.P.{C) 5729/2011 n W.P.(C) 5731/2011 n W.P.(C) 5732/2011 n W.P.(C) 5737/2011 Petitioner in W.P.(C) 5738/2011 n W.P.(C) 5739/2011 n W.P.(C) 5743/2011 n W.P.(C) 5761/2011 n W.P.(C) 5784/2011 n W.P.(C) 5785/2011 n W.P.(C) 5791/2011 n W.P.(C) 5794/2011 n W.P.(C) 5797/2011 n W.P.(C) 5798/2011 n W.P.(C) 5822/2011 n W.P.(C) 5911/2011 n W.P.(C) 5918/2011 n W.P.(C) 5928/2011 n W.P.(C) 5931/2011 \ GULSHAN KUMAR PAWAN KUMAR SUBHASH SHRIVASTAV RAM RAJ AJAY KUMAR RAMESH CHANDER @ RAMESH VINOD KHANA KISHAN LAL MOHAN LAL SANJEEV KUMAR GUPTA PRADEEP GUPTA RAM KUMAR SUNEHRILAL BHAGIRATHI CHOURASIYA MOHD. SHARIQ KARUNA SHANKAR PANDEY VDAY KUMAR GUPTA MD.SHAMSHAD ALAM VIRENDER TRILOK CHAND VINOD SALIM KHAN SATYA PRAKASH . SANJAY KAUSHIK REHMAT ALI KHAN INDULESH ANIL KUMAR BISHT KAMLESH DEVI YADAV CHARAN SINGH ARUN SINGH SATISH KUMAR PUSHKARNA SHIV NARAIN SAHU CHAND KAPOOR jITENDER KUMAR RAJ KUMAR PAPPU BASANT LAL TIWARI NEPAL SINGH SURENDER SAINI BHAWANI SINGH MOHAN PRASAD GUPTA RAM KISHAN LALA RAM PRAKASH BALWANT SINGH Petitioner in W. PetitfoneiHnWr P.(C P.{C P.(C P.(C P.(C .P.(C P.(C P.(C P.(C P.(C P.(C P.(C P.(C P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C .P.(C Petitioner Petitioner Petitioner CHAND. Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner ..... Petitioner Petitioner Petitioner ..... Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner ..... Petitioner Petitioner Petitioner ..... Petitioner Petitioner Petitioner - Petitioner Petitioner n W. n W. n W. n W n W. n W. n W. n W. n W. n W. n W. n W. n W. n W. n W. n W. n W. n W. n W. n W. n W. n W. n W. n W. n W. n W. n W nW n W n W n W n W n W n W n W n W n W n W n W n W n W n W n W W.P.(C} 4347/2011 and connected matters 5933/2011 5934/2011 5935/2011 5957/2011 5965/2011 5966/2011 5967/2011 5968/2011 5969/2011 5970/2011 5974/2011 6096/2011 6100/2011 6101/2011 6102/2011 6107/2011 6108/2011 6114/2011 6115/2011 6116/2011 6117/2011 6118/2011 6119/2011 6120/2011 6121/2011 5122/2011 6123/2011 6144/2011 6250/2011 6270/2011 6271/2011 6449/2011 6527/2011 6528/2011 6529/2011 6530/2011 6531/2011 6532/2011 6533/2011 6534/2011 6538/2011 6555/2011 6667/2011 6668/2011 6669/2011 Page 4 ofS V DINESH KISHORI LAL BACHU SINGH ANIL KUMAR SURESH GUPTA RAJ BAHADUR MAHENDRA PRASAD AND ORS. RAMU SIMANT SHARMA RAM SINGH AND ORS. VINAY KUMAR SATYA NARAYAN SHARMA ROHAN SHARMA KULDEEP SINGH AND ORS. RAM PRAKASH SURAJ SINGH VEER SINGH SURENDRA SINGH USHA SUBHASH DASU RAM YADAV SURENDER LOKENDER SUNITA BHAGWAT SWAROOP GUPTA SHAKAL SINGH NARENDER KUMAR BRIJ PAL RAJU ASHOK JAI CHHABRA BINDU DEVI MOHD. MUZAHID AND ANR. KAMLESH UJJAINWAL KISHAN DEVI CHARAN ANJU SHOBHA JEET SEHGAL POONAM RANA YUSUF KHAN SHANTI BASANTI AND ORS. RAJ KUMARI GUDDI W.P.(C} 4347/2011 and connected matters A Petitioner in W.P.(C) 6670/2011 Petitioner in W.P.(C) 6684/2011 Petitioner in W.P.(C) 6701/2011 Petitioner in W.P.(C) 5173/2011 Petitioner in W.P.(C) 4739/2011 Petitioner in W.P.(C) 5046/2011 Petitioners in W.P.(C) 5051/2011 Petitioner in W.P.(C) 5157/2011 Petitioner in W.P.(C) 4649/2011 Petitioners in W.P.(C) 4722/2011 Petitioner in W.P.(C) 2601/2011 Petitioner in W.P.(C) 2602/2011 Petitioner in W.P.(C) 3052/2011 Petitioners in W.P.(0)3181/2011 Petitioner in W.P.(C) 3185/2011 Petitioner in W.P.(C) 3189/2011 , Petitioner in W.P.(C) 3196/2011 , Petitioner in W.P.(C) 4340/2011 , Petitioner in W.P.(C) 4342/2011 , Petitioner in W,P.(C) 4343/2011 , Petitioner in W.P.(C) 4344/2011 . Petitioner in W.P.(C) 4345/2011 . Petitioner in W.P.(C) 4349/2011 . Petitioner in W.P.(C) 4350/2011 . Petitioner in W.P.(C) 4352/2011 . Petitioner in W.P.(C) 4354/2011 . Petitioner in W.P.(C) 4356/2011 . Petitioner in W.P.(C) 4358/2011 . Petitioner in W.P.(C) 4359/2011 . Petitioner in W.P.(C) 4360/2011 . Petitioner in W.P.(C) 4361/2011 . Petitioner in W.P.(C) 4362/2011 . Petitioners in W.P.(C) 4363/2011 . Petitioner in W.P.(C) 4364/2011 . Petitioner in W.P.(C) 4365/2011 . Petitioner in W.P.(C) 4366/2011 . Petitioner in W.P.(C) 4367/2011 . Petitioner in W.P.(C) 4368/2011 . Petitioner in W.P.(C) 4369/2011 . Petitioner in W.P.(C) 4370/2011 . Petitioner in W.P.(C) 4371/2011 . Petitioner in W.P.(C) 4372/2011 . Petitioners in W.P.(C) 4373/2011 . Petitioner in W.P.(C) 4374/2011 Petitioner in W.P.(C) 4375/2011 V V-cjTv: . Petitioner in W.P.(C) 4377/2011 HARISH KUMAR-- PeWttonerIn W.P.(Q4387/2011 OM PRAKASH PATHAK ®'' u/ dS l^SQ/2011 GOVIND PRASAD GUPTA Petitionerin W.P. C) 4389/2011 amtq ahmfd Petitionerin W.P.(C) 4391/2Uii MOHD. KHURSHID Petitionerin W.P.(C)^392/201 SAMARTH PRASADYADAV PeWloner 43930011 MADAN SINGH RAWAT AND ANR Petitionersin W.P.(C)439S/M^^^ MOMH TMtrSKT ..... PetitionertnW.P.(C)4396/2011 panpatrT Petitionerin W.P.(C)4397/2011 BHUR^Y^AV - petitionerin W.P.{C)4398/2011 ARUN KUMAR BANSAL Petitionerin W.P.(C)4399/2011 ZlNDEr®^ Petitionerin W.P.(C)4400/2011 SAN3AY KUMAR GUPTA Petitionerin W.P.(q4402/2011 HARISHCHAND w'p S 44^5/2^1 nnflMon Petitionerin W.P.(C) 4405/2011 VIJAY KUMARSINGH Petitionerin W.P.(g4406/2011 JAIVIRSINGH I" ^/p r 44^8/2011 AQMnk-lAjqWAL Petitionerin W.P.(C) 4408/2Uii DAUP KUIMAR GUPTA PetitionerIn W.P.CQ 4409/2011 AMTDi inTM Petitioner in W.P.(C) 4410/2011 IAXMAj\! Petitionerin W.P.CC) 4412/2011 lAT qiNCH PAL Petitionerin W.P.(C) 4413/2011 fsHOK KUMARYADAV Petitionerin W.P.(Q4414/2011 Mnwn AIT Petitioner in W.P.(C) 5341/ZUli rm^E^L Petitionerin W.P.(C)4847/2011 SYED 'rIZWANALI Petitionerin W.P.(g4859/2011 MANOJ KUMAR S IqQO/M PAWAN KUMAR GUPTA AND ORS Petitioners 5063/20U MFFNA DFVI Petitionerin W.P.(C) 5089/2011 SaTgUDDI ~"'":i;-pS5??4/2Si RAJU SINGH PetitionermWP. C 5114/2011 SURA] DEV PASWAN Petitionerin W-P-(C) 5115/201 PANKWPANDEY wDS BRU MOHAN ALIAS SASHI •" w'p'fnli?9/2oii PRFM MASSEY Petitionerin W.P.(C) 5139/201 CHANDEI?PAL SINGH PetitionerIn W.P.(Q|144/2W1 NARENDERKUMAR ••••• SVM/MU SHIV NANDAN PRASAD Pe Itionerin WP. C 6799/2011 PAWAN KUMAR PetitionermW.P. C 6824/2011 SANJEEVAGGARWAL u,'p S fiS^S/Mll SANTOSHAGGARWAL PetitionermW.P. C 6826/2011 NARENDERKUMAR u/p S 689^^^^ RAJ KUIVIAR Petitionerin W.P.(C)6896/2011 W.P.(C}4347/2011andconnectedmatters 6of8 \ ASHA RANI MD. TAIYAB MEENA DEVI MOHAMMAD IKRAMUL HAK SURAJ KUMAR PRAKASH CHAND MEENA RAVINDER KUMAR BIJENDER ASHWNI KAPOOR JAMIRUDDIN DIRENDER Sm&4 SHYAM SUNDER R.AJIV KUMAR MAHESH RAM KUMAR NAND LAL GUPTA SUSHIL KUMAR versus NDMC &ORS. Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner Petitioner n W.P.(C) n W.P.(C) n W.P.(C) n W.P.(C) n W.P.(C) n W.P.(C) n W.P.(C) n W.P.(C) n W.P.(C) n W.P.(C) n w.p.ra n W.P.(C) n W.P.(C) n W.P.(C) n W.P.(C) n W.P.(C) n W.P.(C) U'' 6901/2011 6902/2011 6903/2011 6904/2011 6905/2011 6906/2011 6907/2011 6908/2011 6909/2011 6910/2011 ^917/2011 6919/2011 6920/2011 6921/2011 6922/2011 6932/2011 5420/2011 Respondents Present: Mr. B. B. Sawiiney, Sr. Advocate with Mr. Ankan Suri, Mr. Lakshay Sawhney, Mr. Ankur Suri and Mr. Sunil Kumar, Advocates for the petitioners. Mr. Sumit Kumar Singh, Mr. Anand Shailani, Mr. Satish Kumar Tripathi, Mr. N.K. Sahoo, Mr. R.N.Singh, Mr. l^i.R. Singh, Mr. Ramesh K. Mishra, Mr. Surender Pandit, Mr. Navjot Kumar, Mr. Mahendra Singh, Mr.Sunder Lai Juneja, Mr. Pranesh, Mr. B.B. Bhatia, Mr. Navjot Kumar and Mr. Satish Chand Gupta, Mr. Pranesh, Mr. Sahil Kapoor, Ms. S, Fatima, Mr. Jagdeep Kr. Sharma, Ms. Rani Chhabra, Ms. Rupinder Kaur, Ms. Ferida Satarawala, Mr. R.N. Singh, Mr. Vikas Batra, Mr. V.P. Rana and Mr. Navjot Kumar, Advocates for the petitioners. Ms. Madhu Tewatia, Ms. Sidhi Arora, Mr. Vinod Kumar, Mr.Arjun Pant, Mr. Ashutosh Lohia and Mr. Vinod Wadhwa, Advocates for the respondent/NDMC., Mr, Najmi Waziri, Standing Counsel, Mr. Bhupesh Narula, Mr. SanjaySahay, Ms. Farida SatarwalaChopra, Mr. Sachin Datta, Mr. Abhimanyu Kumar and Ms. Rachna Saxena,Advocatesfor the respondent/GNCTD, W.P.(C) 4347/2G11 stid mnnsctad matters Ms, NavraWn Chaudhary, Mr, H,S. Sachdeva, Mr a Rajeshwar Rao, Mr. Vikram Aggarwal and Mr. Shariq Mohammad,Advocatesfor the respondent/DelhiPolice. .CORAI^ HOB^'BLE NS.JUSTICE HIMA KOHLI

¶1Whether Reporters of Local papers may be allowed to see the Judgment?

¶2To be referred to the Reporter or not? /

¶3Whetherthe judgmentshould be reported in the Digest? iC0|-ILI/3. • • ' For detailedjudgment,see WP(C) No.4743/2011. The Registryis directedto place acopy of the judgmentpassed in " WP(C) Wo.4743/2irrrTnthTs^e- " -4 OCTOER 24^^ ,2011 rkb W.P.(C)4347/2011 and connected matters (HIMA KOHLI) JUDGE IN THE HIGH COURT OF DELHI AT NEW DELHI ! Reserved on :

21.09.2011 Pronounced on: .10.2011 + W. IN THF MATTERS OF SHIV NAFH CHOUDHARY RAM DASS versus NDMC & ORS. 4743/2011 and 5254/2011 Petitioner in W.P.(C) 4743/2011 Petitioner in W;P.(C) 5254/2011 Respondents /Alonr^wiit-h W.PJC) 2601/2011, 2602/2011, 3052/2011, ' 4347/2.011-4FiS;g/2011, 4593/2011. 4610/2011. 4650/2011, 1/701.1, 4649/2011, 4722/2011, 4739/2011. 5046/2011, .^157/2011, 4775/^011 r 4S27/2011. 4923/2011, 5024 / ^yoil-502S/2011. 5247/2011, 5255/2011, 5257/2011;. 525872011- -^261/2011. 5262/2011. 5263/2011, 5264/2011. •R777/:>.QiJ-" 5292/2011, 5312/2011, 5317/2011^—5402/2011, 5^03/2011. '^470/2011. 5405/2011, 5408/2011. 5410/2011, .S411/2011. 5413/2011. 5418/2011. 5423/2011, 5444i2Ml^ ••S473/2Qli, -^404/2011, 5485/2011, 5497/2011, 5498/2011, S.^.03/2011, .>i504/2011, 5505/2011. 5506/2011/ 5507/201.1^ 5508/2011. 5595/2011, 5614/2011, 5615/2011, 5616/2011, 5618/2013-5627/2011. 5630/2011. 5631/2011, 5643/2011^ 5654/2011. 5656/2011. 5711/2011, 5717/^011^ S728/2011. 5729/2011. 5731/.2011, 5732Z2Mlr ^r-r4.7/7011. 5738/2011. 5739/2011. 5743/2011, 5761/201.1^' 5784/2011. 5785/2011, 5791/2011, 5794/2011. 5797/2M1jl 57911/2011. 5822/2011, 5911/2011, 5918/2011,—^28/2011, 5931/2011. 5933/2011, 5934/2011. 5935/2011, 5957/2011, 5966/2011, 5967/2011. 5968/2011, 5969/2011, S97i0/2011, 5974/2011, 6096/2011, 6100/2011,—6101/2011,. 6m2J2011, 6107/2011. 6108/2011, 6114/2011, 6115/2011x 6j'i6/2011, 6117/2011. 6118/2011, 6119/2011, 6120Z2M-L. 6122/2011. 6123/2011. 6144/2011, 6250/2011, 6271/2011. 644Q/2011. 6527/2011, 6528/2011, 6529/201i, 6530/2011. 6531/2011, 6532/2011,—6533/2011, 65^4/2011. 6538/2011, 6555/2011, 5173/2011, 3181/2011^ 3185/ 2011." 3189/2011, 3196/2011. 4340/2011, 4342/2011^. '.P.(C) 4743/2011, S2S4/2011 &connected matters w. f /b 4352/2011, 4354/2011, "Tf if ' / ^wJLJLf 4356/2011, V* -A-r 4358/2011, 4359/2011, 4360/2011, 4361/2011, 4362/2011, 4363/2011, 4364/2011, 4365/2011, 4366/2011, 4367/2011, 4368/2011, 4369/2011, 4370/2011, 4371/2011. 4372/2011, 4373/2011, 4374/2011, 4375/2011, 4377/2011, 4387/2011, 4388/2011, 4389/2011, 4391/2011, 4392/2011, 4393/2011, 4395/2011, 4396/2011, 4397/2011, 4398/2011, 4399/2011, 4400/2011, 4402/2011. 4404/2011, 4405/2011, 4406/2011, 4407/2011, 4408/2011, 4409/2011, 4410/2011, 4412/2011, 4413/2011, 4414/2011, 5341/2011, 4847/2011, 4859/2011, 4887/2011, 4990/2011. 5063/2011, 5089/2011, 5099/2011, 5114/2011, 5115/2011. 5117V(2011, 5129/2011, 5139/2011, 5144/2011, 6667/2011, 6668/2011, 6669/2011, 6670/2011, 6684/2011, 6701/2011. 6708/2011, 6799/2011, 6824/2011, 6825/2011, 6826/2011. 6827/2011, 6896/2011, 6901/2011, 6902/2011, 6903/2011. 6904/2011, 6905/2011, 6906/2011, 6907/2011, 6908/2011, (SQ09/2011. 6910/2011, 6917/2011, 6919/2011, 6920/2011, 6921/2011,6922/2011 and 6932/2011. Present; Mr. B. B. Sawhney, Sr. Advocate with Mr. Ankan Suri, Mr. Lakshay Sawhney, Mr. Ankur Suri and Mr. Sunil Kumar, Advocates for the petitioners. Mr. Sumit Kumar Singh, Mr. Anand Shailani, Mr. Satish Kumar Tripathi, Mr. N.K. Sahoo, Mr. R.N.Singh, Mr. M.R. Singh, Mr. Ramesh K. Mishra, Mr. Surender Pandit, Mr. Navjot Kumar, Mr. Mahendra Singh, Mr.Sunder Lai Juneja, Mr. Pranesh, Mr. B.B. Bhatia, Mr. Navjot Kumar and Mr. Satish Chand Gupta, Mr. Pranesh, Mr. Sahil Kapoor, Ms. S. Fatima, Mr. Jagdeep Kr. Sharma, Ms. Rani Chhabra, Ms. Rupinder Kaur, Ms. Ferida Satarawala, Mr. R.N. Singh, Mr. Vikas Batra, Mr. V.P. Rana and Mr. Navjot Kumar, Advocates for the petitioners. Ms. Madhu Tewatia, Ms. Sidhi Arora, Mr. Vinod Kumar, i^ir.Arjun Pant, Mr. Ashutosh Lohia and Mr. Vinod Wadhwa, Advocates for the respondent/NDMC. Mr. Najmi Waziri, Standing Counsel, Mr. Bhupesh Narula, Mr. Sanjay Sahay, Ms. Farida Satarwala Chopra, Mr. Sachin Datta, Mr. Abhimanyu Kumar and Ms. Rachna Saxena, Advocates for the respondent/GNCTD. Ms. Navratan Chaudhary, Mr. H.S. Sachdeva, Mr. D. W.P.fC) 4743/2011, 5254/2011 & connected matters Rajeshwar Rao, Mr. Vikram Aggarwal and Mr. Shariq Mohammad, Advocates for the respondent/Delhi Police. CORAM HOSM'BLE MSJUSTICE HIMA KOHLI

¶1Whether Reporters of Local papers may be allowed to see the Judgment?

¶2To be referred to the Reporter or not?

¶3Whether the judgment should be reported in the Digest? HIMA KOHLI, J.,

¶1This common judgment shall dispose of the petitions filed by the petitioners/vendors as the issues raised in these writ petitions are common. For the sake of convenience, facts of W.P.(C) 4743/2011 are taken note of.

¶2The focus of the lengthy arguments addressed by both sides revolves around an order dated 15.07.2011 passed by the Supreme Court "t' on some miscellaneous applications presented in W.P.(C) 1699/1987 entitled nainda Ram & Ors. vs. NDMC & Qrs., which matter was decided on 08.10.2010 by issuing exhaustive directions. Before proceeding to deal with the respective arguments addressed by the learned counsels for petitioners/vendors and respondent/NDMC, it would be appropriate to set out the aforesaid order dated 15.07.2011, which is the bone of contention and is reproduced hereinbelow:- "Heard learned counsel for the applicants and perused the record. W.l^.(C)4743/2011, S2S4/2011 8i connectedmatters Page3 of 28 Since judgnnent of this Court has so far not been implemented, inasmuch as appropriate legislation has not been enacted by' the competent legislature, we direct parties to maintain the status quo as it is obtaining today."

¶3It was submission of learned counsel for respondent/NDI^C that the aforesaid order issued by the Supreme Court, calling upon parties to maintain status quo as obtaining on

15.07.2011, can only be interpreted to mean that the extensive directions issued earlier, on 08.10.2010, in the case of Gainda Ram fsupral reported as (2010) 10 see 715 shall continue to remain in operation, including the adjudicatory mechanism provided for by the NDIMC in the scheme presented by it before the Supreme Court and approved in the said judgment, till the appropriate government enacts a law for regulating urban street hawkers and street vendors. It was stated that simply because the legislature has not enacted a law in this regard on or before

30.06.2011, as directed in the aforesaid judgment, it cannot be contended by the petitioners/vendors that there exists a vacuum and the said vacuum can no longer be filled up by continuing to regulate vending activities in the NDMC jurisdiction in the manner as set out in the aforesaid judgment.

¶4To give a brief background of the dispute, learned counsel for the respondent/NDMCwalked this Court through some prominent decisions of the Supreme Court rendered from time to time, which relate to pavement VV.P.CC)4743/2011, 5254/2011 &connected matters "0 squatters/hawkers, starting from the decision in the case of Sodan Singh vs. NDMC &• Ors. reported as (1998) 2 SCC 727, the interim order dated

03.03.2006 passed by Supreme Court in W.P,(C) 1699/1987 entitled Sudhir Madan & Ors. vs. MCD. the final judgment in the case of Sudhir Madan fsupral reported as (2009) 17 SCC 597 and lastly, judgment dated 08.10.2010 passed in the case of Gainda Ram fsupra).

¶5Learned counsel for the respondent/NDMC vehemently opposed the prayer of the petitioners/vendors for grant of interim orders restraining the respondent/NDMC from removing them from the sites occupied by them till the enactment of an appropriate legislation, in terms of the . directions issued by the Supreme Court in the, case of Gainda Ram fsupraV She particularly referred to the observations made by the Supreme Court in paras 40 and 41 of the judgment in the case of Sodan Singh..(supra), which dealt with the immediate eviction of unauthorized squatters/hawkers and laid emphasis on the fact that in the said case, the Supreme Court had directed removal of unauthorized squatters/hawkers without awaiting final allotment of sites to be allotted to eligible claimants at the places recommended by the Thareja Committee or suggested by the NDMC.

¶6Again, in the interim order dated 03.03.2006 passed in Sudhir Madan's case fsupral, the following observation made by the Supreme Court was highlighted by the counsel for the respondent/NDMC:- W.P.(C)4743/2011, 5254/2011 &connected matters k "While we undertake this exercise, we direct Authorities to see to it that those persons, who are carrying on hawking activities or who are squatting on public land without any authority, even in accordance with present day schenne in force, are removed forthwith. This includes unauthorized hawking, squatting on public streets, footpaths and public parks, including playground. We direct the Delhi Administration to take steps immediately in collaboration with MCD and NDMC with necessary assistance from Delhi Police to clear, the roads, streets, footpaths, parks etc. by unauthorized occupants/squatters/hawkers." '^4

¶7As to the judgment dated

17.05.2007 rendered in the case of Sudhir Madan fsupral, much emphasis was laid by the counsel for th respondent/NDMC on paras 28 to 30 and 35, which are reproduced hereinbelow for ready reference:- "28. The New Delhi Municipal Committee has also submitted its Scheme. We have considered the Scheme submitted before us. The area which falls under NDMC does not create problems such as those in the areas under MCD. However, in the said Scheme reference has been made to persons who do not have permission under Section 225 or licence under Section 330 of the NDMC Act, 1994 but who are unauthorisedly continuing to carry on business as hawkers/street vendors. They have been described as those who are "tolerated" in the NDMC area. We fail to understand why any person who • violates the law should be tolerated. Either they should be compelled to obey the law or the law may be suitably amended, if it is found to create undue hardship. The problems need to be addressed by the legislature or the rulemaking authority. We, therefore, observe that if it is felt that the persons who fall in this category require special protection, the Act may be suitably amended to cover their cases or else number of such illegal squatters may increase from time to time. W.P.(C)4743/2011, 5254/2011 &connected matters e

¶29There has been no serious objection to the Scheme submitted by NDMC which is a comprehensive scheme. Certain directions have, however, been sought for from this Court. We approve Scheme submitted by NDMC.

¶30It is submitted before us that Schemes which have been approved by this Court must be subject to any Act or rules that may be framed in consonance with National Policy on Urban-Street Vendors. It goes without saying that we have approved the Schemes as framed by MCD and NDMC. If the legislature intervenes and frames another scheme or regulations governing such Schemes, that will certainly supersede Schemes prepared by MCD and NDMC. It is well settled that any administrative action is always subject to law that may be framed by the competent legislature.

¶35^Subject to the aforesaid modifications/changes in the Schemes submitted by MCD and NDMC, the same are approved. The said authorities shall now take appropriate steps to implement the Scheme forthwith. In case of any difficulty faced by them in implementing the schemes, they shall have the liberty to apply to this Court."

¶8Lastly, in the recent judgment in the case of Gainda Ram (supral, learned counsel for the respondent/NDMC specifically relied upon paras 30, 32, 50 to 66 to state that the Supreme Court was conscious of the fact that a structured regulation and legislation is urgently required to control and regulate the fundamental right of hawking. She also pointed out that three tier disputes redressal mechanism •set out in the affidavit filed by the then Chairperson of the NDMC was taken note of by the Supreme Court in para 72 of the aforesaid judgment and in para 73, it was then observed as below:- W.P.(C) 4743/2011, 5254/2011 & connected matters 'r "73. In paragraph 12 of the affidavit it has been stated that there shall be an Appellate Authority which shall attend to redressai of grievances of squatters, hawkers, traders, residents or any other person by hearing appeals against decision of the Vending Committee (l^ain). Paragraph 12 of that affidavit is set out below:- There shall be an Appellate Authority. On the forwarding of petitions received by Chairperson, this Authority shall attend to redressai of grievances of squatters, hawkers, traders, residents or any other person. The Authority shall also hear appeals against decision of Vending Committee

(Main). Decisions of this Authority unless challenged before a Higher Forum or in any Competent Court, shall be final. This Authority shall be initially headed by a person appointed by the Chairperson having at least 10 years legal or judicial background. There can be more than one member in this Authority."

¶9After making the aforesaid observations, in paras 74 to 76 of the judgment, the Supreme Court went on to observe as below:- "74. In the said affidavit, which was affirmed before this Court on 24'^'' August, 2010 it has been stated that NDMC shall comply with the orders which would be passed by the adjudicatory mechanism contemplated in the scheme and which has been approved by this Court for the NDMC area, unless such orders are made subject matter of challenge before a higher forum or.in any other competent Court.

¶75In view of such schemes, hawkers, squatters and vendors must abide by Dispute Redressai scheme mentioned above. There should not be any direct approach to this Court by way of fresh petition or lAs, bypassing Dispute Redressai Mechanism provided in the scheme. . W.P.(C) 4743/2011, 5254/2011 &connected matters V

¶76However, before 30"^ June, 2011, the appropriate Government is to enact a law on the basis of the Bill mentioned above or on the basis of any amendment thereof so that hawkers may precisely know contours of their rights." ••>>

¶10It was thus sought to be contended on behalf of respondent/NDMC that there can be no vacuum as far as regulation of trade of street hawkers/vendors in the NDMC jurisdiction is concerned and the failure on the part of the legislature to abide by the timeline set out by the Supreme Court in the case of Gainda Ram fsupra), by putting in place a statute on or before 30.06.2011, cannot be interpreted by the petitioners/vendors to mean that they can continue their trade unhindered at any place of their choice in the NDMC jurisdiction, in an unregulated manner and without any obstruction or objection from the NDMC. .y

¶11Learned counsel for the respohdent/NDMCparticulariyreferred to paras 74 and 75 of the aforesaid judgment to state that the dispute redressal scheme, noticed by the Supreme Court in para 75 was the one that was legally functioning in NDMC jurisdiction and which was taken note of by the Court in the preceding para 74. In other words, she stated that the scheme as set out in the affidavit dated 24.08.2010, filed by the then Chairperson of NDMC before the Supreme Court in Gainda Ram's, case (supra), was the one which was finally approved by the Supreme Court. She further submitted that assuming, without admitting, that the W.P.(C)4743/2011, S2S4/2011 &connectedmatters -V dispute redressal scheme set out by the NDI^iC had lapsed on 30.6.2011, as claimed by the petitioners, then the NDMC Act provides an adequate fallback to ensure orderly management of vendors in the area. Specific reference was made in this regard to the provisions contained in Sections 221, 224, 225 and 226 of the said Act.

12.. It was further argued by the counsel for the respondent/NDMC that the application filed by the NDMC before the Supreme Court in July 2011 praying inter alia for extension of time to regulate hawkers/squatters in the NDMC area, as per the scheme mentioned in the judgment in Gainda Ram's case fsupra), till the enactment of a law by the legislature in that regard, had not yet been finally disposed of by the Supreme Court at the time of passing of the status quo order dated

15.07.2011 and similarly, the other application filed by one of the hawkers/vendors praying inter alia for restraining the respondent/NDMC from granting Tehbazan rights to the winners of the lucky draw of lots for allotment, which was to be held on

12.05.2011 or any date thereafter, was also pending consideration before the Supreme Court. Hence, no finality could be attached to the order dated

15.7.2011 which can only be considered an interim measure till the final disposal of the aforesaid applications or the enactment of a legislation.

¶13On merits, learned counsel for the respondent/NDMC referred to the affidavit dated

01.08.2011 filed by the Director (Enforcement), NDMC, W.P.(C) 4743/2011, S2S4/2011 & connected matters v<, 'X-7 wherein it was stated that pursuant to the public notice issued by the NDMC inviting applications under NDMC Urban Street Vending Scheme in year 2007, respondent/NDMC had received 4367 applications. The documents required by the applicants for registration under the Scheme included a proof of age, documentary proof/affidavit for the purpose of annual income, proof of residence, proof in support of special categories like handicapped, Kashmiri migrants etc. and proof of squatting in the NDMC area, if any. In para 4 of the aforesaid affidavit, following criteria approved/adopted by the Vending Committee to shortlist the eligible applicants is set out:-"4. That the criteria approved/adopted by the Vending Committee to shortlist the eligitjle applicants is as under:-

(i) The applicants should be resident of Delhi with his name registered in electoral rolls as per abstract of photo E-Roll or ERO certificate.

(ii) The applicant should be a major, viz. with over 18 years of age as per valid birth certificate or age certificate or school certificate etc.

(iii) The applicant should be a needy as per income records of DC (Revenue) or as vulnerability records of Government of NCT of Delhi (Samajik Suvidha Sangam: vulnerable and most vulnerable category).

(iv) The applicant should be registered as per NDMC Street Vendors Scheme. The policy verification of the applicant should be available.

(v) The applicant or his dependent family member should not be employed or should not have any other tehbazari/vending or any other business premises in Delhi as per record verification of NDMC/MCD. W.P.{C)4743/2011, 5254/2011 &connected matters

(vi) Preference will be given to applicants who are physically handicapped or widows or senior citizens above years or Kashmiri migrants or SC/ST (necessary certificate to be submitted and relaxation may be given in the above criteria)."

¶14As per respondent/NDMC, category-wise list of eligible shortlisted applicants in terms of the aforesaid criteria totalled to 3878 W applicants. The affidavit dated

01.08.2011 states that respondent/NDMC has identified

¶183new spaces, in addition to the 203 remaining spaces identified by the Thareja Committee in the NDMC area, which were available for allotment, thus taking total number of available spaces to 386. It was further stated that due to factors like de-listing of the Parliament Street on security grounds, construction of flyovers and Metro Stations at various locations in the NDMC jurisdiction, the number of authorized tehbazari squatters has changed from 348 to 404 in number. The number of applicants, who the respondent/NDMC claims, are vending unauthorisedly at Connaught Place, Sarojini Nagar, Parliament Street and Janpath areas and in whose favour, status quo orders are operating, is stated to be 323 in number. The affidavit asserts that simply because the names of the petitioners, who are registered with the NDMC, figure in the eligibility list drawn by the respondent/NDMC, cannot be treated as proof of their regularly vending in the NDMC area \ and nor does it confer on them any enforceable vested right to ensure a vending space for them in the NDMC.area,which is directly dependent on W.P.(C)4743/2011, 5254/2011 &connected matters the number of spaces available. Thus, it was contended that neither the possession of any number of challans, nor the absence thereof can make a difference, for the reason that challans cannot form the basis for the petitioners to claim any vested legal right to squat at a given space.

¶15Counsel for respondent/NDMC asserted that present y petitions are not maintainable inasmuch as the petitioners have an ^ equally efficacious alternate remedy of approaching the appellate authority constituted by the Chairperson, NDMC, for redressai of their grievances and failure on their part to have approached Vending Committee is not on account of the fact that the said Committee including the appellate authority is not functioning, but because they have found it more convenient to bypass the aforesaid forum and approach this. Court directly, which is not permissible. She stated that extensive measures have been taken by the respondent/NDMC to constitute the adjudicatory ^ mechanism by way of a three tier system in the following manner:-

¶1Vending Sub-Committee (Site of Spaces),

¶2Vending Sub-Committee (Heath and Hygiene) and

¶3Vending Sub-Committee (Enforcement).

¶16She stated that the creation of the aforesaid three Vending Sub-Committees, Vending Committee (Main), as also of the appellate authority which was constituted to redress grievances of squatters, hawkers, traders, residents or any other person against the decision of W.P.(C}4743/2011, 5254/2011 &connected matters the Vending Committee

(Main), was placed before the Supreme Court for consideration and the said three tier adjudicatory mechanism was duly approved in the judgment of Gainda Ram fsupra).

¶17Per contra, learned counsels for petitioners/vendors, who appeared on different dates, vehemently opposed aforesaid stand ,K, taken by the respondent/NDMC and asserted that the scheme floated by \ the respondent/NDIMC for regulating vending activities in its jurisdiction had lapsed on 30.06.2011 in the absence of the enactment of a legislation as per directions of the Supreme Court in the case of Gainda Ram (supra) and as on date, there is no scheme in existence. It was canvassed that implication of the aforesaid order of status quo passed by the Supreme Court on 15.07.2011 can only mean that irrespective of the fact whether squatting is legal or illegal, the same be permitted to. continue on an 'as is where is' basis, and such status quo is to be •••> maintained by all the parties till a law is framed by.the legislature.

¶18Mr. B.B. Sawhney, Sr. Advocate appearing for petitioners/vendorssubmitted that in the case of Gainda Ram (supra), the Supreme Court had directed that the appropriate government must enact a law on or before 30.06.2011 so that the hawkers may precisely know contours of their rights, hence dispute redressal mechanism provided for in the scheme mentioned in the aforesaid judgment could operate only upto 30.05.2011 and thereafter, the said scheme would W.P.(C) 4743/2011, 5254/2011 &connectedmatters y' automatically stand lapsed. He stated that no other interpretation can be given to the order dated 15.07.2011, directing maintenance of status quo, in view of the qualifying words, "as it is obtaining today". He argued that if the scheme was continuing to operate, as claimed by the learned counsel for the respondent/NDMC, then there was no good reason for the respondent/NDMC to have refrained from holding a draw of lots, which was slated for the same day, i.e., 15.07.2011, and that fact of the matter is that even the respondent/NDMC had understood the status quo order to mean that there is no scheme in place after 30.6.2011, for the reason that in para 68 of the aforesaid judgment in the case of Gainda Ram fsupra), all the writ petitions and the interim applications filed before the Supreme Court were disposedof with clear and specificdirectionsthat the problem of hawking and street vending could be regulated by the schemes framed by the NDMC and MCD only upto 30.06.2011 and not thereafter. It was asserted on behalf of the petitioners/vendors that as on date, the directions of the Supreme Court that status quo is to be maintained by the parties can only be given one interpretation, which is that till a law is ultimately enacted by the Parliament, irrespective of their legal status, all the petitioners/vendors would be permitted to continue squatting/hawkingat the sites that have been occupiedby them.

¶19Insofar as the composition of the dispute redressal mechanism is concerned, learned Senior Advocate for the petitioners submitted that contrary to the understanding of the respondent/NDMC,the scheme W.P.(C}4743/2011,5254/2011&connectedmatters Page15of28 \j\® reproduced at paras 72 and 73 in the judgment in the case of Gainda Ram (^ypra}, was not the one which was actually recognized by the Supreme Court, and rather it is the dispute redressal scheme mentioned in para 75 of the aforesaid judgment i.e., a scheme for urban street vendors for NDMC area as formulated in year 2006, which was ultimately ^ approved by the Supreme Court on 17.05.2007, in the case of Sudhir Madan_ (supra), which is the scheme which finds mention specifically in the following para 74 and is the one approved by the Supreme Court. It was contended that even otherwise, the National Capital Territory of Delhi Laws (Special Provisions) Act, 2011 (hereinafter referred to as 'Special Provisions Act') comes to the rescue of the petitioners for the reason that sub-clause

(2) of Section 3 of the Special Provisions Act mandates maintenance of status quo as on

01.01.2006, notwithstanding any judgment, decree or order of any court, in respect of encroachment or I unauthorized development. Thus, it was submitted on behalf of the petitioners/vendors that they were entitled to grant of interim protection till the enactment of a legislation to regulate hawking/vending activities in urban streets in Delhi on the basis of the National Policy on Urban Street Vendors, 2009 framed on 17.06.2009 and the Special Provisions Act.

¶20With reference to Special Provisions Act, learned Senior Advocate for petitioners stated that phrase, "unauthorized development" used in the definition clause has to be seen in the same contextas the'one in which the phrase "encroachment"has been defined, W.P.(C) 4743/2011, 5254/2011 & connected matters \\ wherein it is mentioned that putting up of temporary, semi-temporary or permanent structure for residential use or commercial use or any other use, and the placement of goods on the pavements by the petitioners is liable to be termed as unauthorized use for maintaining status quo under the Special Provisions Act. Much emphasis was laid on the averments made by the respondent/NDMC in its interim application filed before the /' Supreme Court in Gainda Ram's case fsupra) in July 2011, to submit that the respondent/NDMC itself had stated in the said application that the scheme had lapsed and therefore, the only interpretation that can be given to the status quo order passed by the Supreme Court on

15.07'.2011 can be that no scheme would exist after

30.06.2011 and thus, the benefit of the Special Provisions Act ought to be extended to the petitioners. He submitted that the phrase 'street vendors' has been clearly defined under the National Policy on Urban Street Vendors, 2009. Reliance was placed in the case of Patri Vvapar Mandal Delhi fReqd.) vs. MCD Town Hall &. Ors. reported as (2009) 12 SCC 475 and the provisionsof the Special ProvisionsAct to submit that even the Supreme Court had recognized the fact that the Special ProvisionsAct is the only Central law governing the field and it would have primacy over other Statutes and administrative orders. It is thus stated that the provisions of the NDMC Act cannot be invoked by the respondent/NDMC as the said Act is not in consonance with Article 96 of the Constitution of India and furthermore, the Special Provisions Act being valid till the end of W.P.(C)4743/2011,5254/2011&connectedmatters Page17of28 December 2011, no orders in derogation of the provisions of the said Act can be passed.

¶21Mr. S.K. Tripathi, Advocate appearing for some of petitioners/vendors sought to embellish the submissions of Mr.Sawhney, Sr.Advocate and relied on the orders passed in W.P.(C) 1449/2011 entitled Mohd. Ismail vs. NDMC & Ors. to urge that "Appellate Authority" constituted under dispute redressal mechanism for the NDMC area, has not been functioning, which fact he stated is borne out from a perusal of the order dated

08.03.2011 passed in the aforesaid case, wherein the Court took notice of the claim of the petitioner/vendor therein to effect that inspite of orders passed by the Appellate Authority allowing squatting at a particular site, till a final determination by the Vending Committee as to his eligibility, the respondent/NDMC and the police were disturbing his activities. In the aforesaid order, the statement of the counsel for the respondent/NDMC was recorded to the effect that the appellate authority, whose order was being relied upon by the petitioner therein, was constituted initially for the MCD areas and later started functioning for the NDMC areas as well for the reason that at that time, there was no separate appellate authority for the NDMC areas, but subsequently, in accordance with the scheme approved by the Supreme Court, Chairperson, NDMC had constituted a separate appellate authority for •the NDMC areas. Therefore, appellate authority appointed earlier had ceased to have jurisdiction qua the NDMC areas. It W.P.{CJ4743/2011, S2S4/2011 & connected matters was thus contended on behalf of petitioners/vendors that aforesaid order clearly indicates that the appellate authority in the NDMC areas is not functioning.

¶22Reliance was also placed on the minutes of the meeting of the Vending Committee dated 11.03.2010, to claim that if the fact of whether there was actual squatting/vending was verified by the Committee and if the names of the petitioners/vendors figured in the eligibility list prepared by the respondent/NDIMC for holding the draw of lots, then it did not lie in the mouth of the respondent/NDMC to claim that the petitioners, who had been verified and found to be eligible, were not entitled to squat at various sites in the NDMC area after 30.06.2011.

¶23In rebuttal, counsel for respondent/NDMC disputed contentions of the petitioners/vendors and while reiterating her earlier submissions, asserted that petitioners did not have any legally enforceable right, created on the basis of the eligibility list drawn by NDMC, for claiming, grant of interim orders in their favour. She again referred to paras 68, 69, 75, 76 and 78 of the judgment in the case of Gainda Ram fsupra), to emphasize that when aforesaid paras are read collectively, it is clear that petitioners cannot claim an entitlement to any interim orders as sought by them in the present proceedings. She further stated that even otherwise, Special Provisions Act relied upon by the petitioners has duly recognized W.P. (C) 4743/2011, 5254/2011 & connected matters n schemes prepared by the local authorities in the National Capital Territory of Delhi for regulation of urban street vendors. To substantiate the said submission, she drew the attention of this Court to the preamble of the aforesaid Act, which mentions the fact that all the schemes prepared by local authorities in National Capital Territory of Delhi, for '^regulation of urban street vendors in accordance with the National Policy on Urban Street Vendors, 2009 and the Master Plan for Delhi 2021, have been implemented and further that more time is required for proper implementation of the schemes regarding hawkers and urban street vendors.

24.. A specific reference was made by the learned counsel for the respondent/NDMC to Section 2(l)(c) of the Special Provisions Act, which defines the phrase "encroachment" to claim that it does not. cover the petitioners herein, who are squatters. Further reference was made to the provision of Section 3 of the Special Provisions Act, which contains a non obstante clause, to state that status quo with regard to the encroachment or unauthorized development as on 01.01.2006, mentioned in the said provision, was in context of definition of phrases / "encroachment" and "unauthorized development" set out in the definition clause at Sections 2(l)(c) and 2(l)(i) respectively of Special Provisions Act and thus, the petitioners/vendors did not qualify under the aforesaid enactment for claiming protection as none of the ingredients set out in.the provisions of the aforesaid enactment are found to exist in their W.P.CC)4743/2011, 5254/2011 & connected matters i case. It was submitted that the Special Provisions Act, which came into effect in the year 2007 and has been extended from time to time and lastly, till December 2011, does not give permission to persons to re-start any activity once they have been removed by the civic authority and similarly, the Scheme of 2009 does not entitle the registrants to squat unless they have been allotted a specific site. In support of the aforesaid submission, reliance was place on the judgment in the case of MCD vs. Gurnam Kaur reported as (1989) 1 SCC 101. For the purpose of interpreting the meaning of the phrase, "structure", reference was made to judgment of the Supreme Court in the case of Municipal Corporation of Greater Bombay & Ors. vs. Indian Oil Corporation Ltd. reported as AIR 1991 SC 686. For the purpose of understanding the expression, 'status quo', reference was made to the judgment in the case of Messrs Bharat Coking Coal Limited vs. State of Bihar & Ors. reported as 1987 (Supp) SCC 394 to submit that in ordinary legal connotation, the term "status quo' implies the existing state of things at any given point of time.

¶25As for the National Policy on Urban Street Vendors, counsel for the respondent/NDMCstated that both, the 2004 policy and the 2009 policy, find mention in the decision of the Supreme Court in the case of Gainda Ram fsupra) and it was only after taking into consideration the said policies, did the Court directed the institutionalization of urban street vending through legislation. It was further stated that at the time of W.P.(C)4743/2011, 5254/2011 &connected matters delivering the judgment dated 8.10.2010, the Supreme Court took notice of the NCT of Delhi Laws (Special Provisions) Act, 2009, which was valid upto

30.12.2010, apart from noticing Model Street Vendors (Protection of Livelihood and Regulation of Street Vending) Bill, 2009 introduced by the Government of India, Ministry of Housing &. Urban Poverty Alleviation. She stated that nothing new is now being submitted K by the petitioners/vendors herein, for present petitions to be entertained for any purpose whatsoever and all the grievances raised by petitioners can easily be addressed before Vending Committee/appellate authority under the scheme relating to urban street vending in the NDMC area, which fora continue to remain functional, even after 30.6.2011.

¶26This Court has heard these matters at length since

17.8.2011, on different dates. Various counsels for the petitioners/vendors and Standing Counsel for the respondent/NDMC had addressed the Court. Their respective arguments have been taken note of. Both sides have made strenuous efforts to explain what status quo order dated

15.7.2011 passed by the Supreme Court in the case of Gainda Ramfsupra) implies. The leitmotif of the arguments addressed on behalf of the petitioners/vendors is that the status quo order read with the qualifyingwords, "as it is obtaining today", suffixedto the order, can only be read to imply that as on date, i.e., 15.7.2011, there was no scheme operationalin the NDMC areas to regulatevending activitiesand till a law W.P.(C)4743/2011, S2S4/2011 &connected matters Ov is ultimately enacted by the legislature, all the petitioners, irrespective of their legal status, can continue squatting/hawking at different sites that have been occupied by them. It is also asserted that in the teeth of the status quo orders passed by the Supreme Court, the respondent/NDMC in collusion with the police authorities, is threatening to illegally remove the , petitioners/vendors from different sites, which is detrimental, adverse, harassing and belligerent to those, who have been found eligible by the respondent/NDMC for being allotted specific tehbazari spaces within the NDMC jurisdiction, but are being threatened due to lack of further action in this regard which is pending at the end of the respondent/NDMC. The second limb of submissions made by learned counsels for petitioners/vendors was that the Special Provisions Act would additionally come to rescue of the petitioners/vendors, which also requires maintenance of status quo as existing on 01.10.2006, till the end of December, 2011.

¶27On the other hand, the main thrust of the arguments addressed by counsel for the respondent/NDMC was that as the legislature has failed to enact an appropriate legislation in terms of the decision of the Supreme Court in the case of Gainda RamfsupraV the subsequent order dated

15.7.2011 directing parties to maintain status quo as it is obtaining on the said date can only imply that the state of affairs as existing on date are not to be disturbed, until the rights of the parties can be finally determined through legislation. It was submitted that while W.P.(C) 4743/2011, 5254/2011 & connected matters passing the status quo order on

15.07.2011, the Supreme Court was conscious of fact that Parliament had yet to enact a comprehensive legislation to regulate urban street vending and in such circumstances, it goes without saying that it was the intent of the Court that the entire dispute redressal mechanism as recognized in the case of y^^Gainda Ramfsupra) would continue to remain in operation, so as to regulate the urban street vending in.the NDMC area, till the legislation in that regard is enacted. Further, it was stressed that Special Provisions Act did not provide any protective umbrella to the petitioners, whose squatting activities neither fell under definition of "encroachment", nor under "unauthorized development". It was further asserted that even otherwise pending an appropriate legislation, NDMC Act was availableas afall back option and the rellvantprovisions in the said enactment would continue to regulate street vending activity in the NDMC area and the petitioners/vendors could not claim a vested right to squat at any site of their own.

¶28From above, it is apparent that arguments and counter •arguments have been raised by both sides on their respective versions of meaning and the effect of the status quo order dated

15.7.2011 passed by the Supreme Court. It is also very apparent, that the meaning sought to be attributed by both sides as to the implication of the said status quo order, is diametrically opposed to each other. Not only this, both sides are at a tangent on the factum of the pendency or otherwise of W.P.(C)4743/2011, 5254/2011 &connected matters \-J' interim applications filed before Supreme Court by both, applicants/vendors and the respondent/NDMC, for clarifications, on which aforesaid order came to be passed as it is stand of the respondent/NDMC that the aforesaid applications were not disposed of while passing the order dated 15.7.2011. The parties are poles apart on ^\the question of import of the status quo order, and the effect of the observations made by Supreme Court in case of Gainda Ramfsupral as regards the approval of NDMC scheme. They, are'also at loggerheads on the composition of the adjudicatory mechanism in the NDMC jurisdiction and the manner of its functioning, as also the identity of the scheme which is validly operating in the NDMC areas for regulating urban street vending, which had all been subject matter of consideration before Supreme Court in the aforesaid case. The other issues agitated by the parties, starting from the interpretation of the various observations made by the Supreme Court in the aforesaid judgment, the formulation of the scheme as approved by the Supreme Court in the case of Sudhir Madan ("supra), to composition of the disputes redressal mechanism and its validity as also the meaning of the status quo order, are all in a turmoil as both the parties have stoutly defended their respective stands which are completely at variance with each other. The only common ground shared by the parties is the factum of passing of the recent judgment dated

08.10.2010 in case of Gainda RamCsujDraOand the subsequent status quo order dated 15.7.2011 passed V\!.P.(C)4743/2011, S2S4/2Q11 &connected matters by the Supreme Court.

¶29The fountainhead of the dispute in the present cases therefore remains the status quo order dated

15.7.2011 passed by the Supreme Court. The issue which is sought to be agitated before this Court is that having regard to the status quo order, whether a stay order ought to be A, granted by this Court in favour of the petitioners/vendors as prayed for by them, irrespective of their legal status, thus forbidding respondent/NDl^lC from threatening and/or removing them from the different sites occupied by them in the NDMC areas. In other words, this Court is being called upon to examine the meaning, scope and effect of the status quo-order dated 15.07.2011. On the question of how to ascertain the implication of a status quo order passed by a court, in the case of |viessrs Bharat Coking Coal Limited fsupra), it was observed by the Supreme Court that the expression, 'status quo' is undoubtedlya term of ambiguity and at times, gives rise to doubt and difficultyand in case any party has any doubt on the meaning and the effect of the status quo order, the proper course for such a party would be to approach the Court that had passed the status quo order, to s6^.,clarifications.

¶30In the case at hand, while seeking to ride the wave of the aforesaid status quo order, the parties have chosen to overlook one important factor, which is that a status quo order operates on both sides. The Supreme Court has passed orders requiring both sides to maintain status W.P.{C)4743/2011, S254/2011 &connectedmatters Page26 of28 Ni quo. Once such an order of the Supreme Court is on record, the same not only binds all the parties to the adjudication, and all the parties, civil or judicial who are required to act in accordance with the said orders, but it equally binds the High Court from interfering with such an order, as the said order has been passed in litigations before the highest Court of the land.

¶31The orders of the Supreme Court are on record. The status quo \ order is a clear signal to the High Court as well, to avoid granting any order, including an interim order, when the Supreme Court has directed for status quo to be maintained. In such circumstances, if this Court was to grant a stay order in favour of the petitioners/vendors arrayed before it, it would be tantamount to negating the orders of the Supreme Court, which require the parties to maintain status quo pending enactment of appropriate legislation. If either of the parties were unclear about the interpretation-of the status quo order, it was for them to have applied to the Supreme Court for clarifications thereof. Additionally, the reliance placed by the petitioners/vendors on the Special Provisions Act seeking interim legal sanctity to the placement of goods by them on the pavements, by terming it as encroachment/unauthorized use, as recognized under the said Act and their contention that the Supreme Court had recognized the fact that the Special Provisions Act is the only Central law having primacy over other Statutes, are also matters that the W.P.(C)4743/2011, S254/2011 &connected matters petitioners/vendors ought to have placed before the Supreme Court while seeking clarifications of the status quo order. It would therefore be advisable for the petitioners/vendors as also respondent/NDI^C to approach Supreme Court and make their submissions there as regards their grievances. However, as both parties insisted that their arguments be taken note of and their submissions be placed on record, some pains have been taken to do the needful.

¶32In view of the aforesaid facts and circumstances, this Court is of the opinion that it will not be appropriate for it to grant stay orders in the face of the status quo order dated 15.07.2011 passed by the Supreme Court. It is reiterated that any such order shall be an anti-thesis to the orders of the Supreme Court, which must be respected both, in letter and spirit. In such circumstances, the present petitions are disposed of by declining grant of any interim orders to the petitioners. However, liberty is granted to both the parties to apply to the Supreme Court for a clarificationof the status quo order dated 15.07.2011 passed in the case of Gainda Ram fsupra). The parties are left to bear their own costs. OCTOEI^;^^, 2011 rkb W.P.(C) 4743/2011, 5254/2011 & connected matters JUDGE