VoxJuris
Home › High Courts › Delhi High Court 2012 › High Court of Delhi

Shri Hans Enterprises v. Airports Authority of India

Court
High Court of Delhi
Decided
20 November 2012
Bench
S. Muralidharauthor
Case no.
O.M.P. 370/2008

Judgment

ORDER

20.11.2012

¶1These are four petitions under Section 34 of the Arbitration & Concihation Act, 1996 ('Act') arising out of a common set of facts in the Award.

¶2The background to these petitions is that the Airports Authority of India ('AAF)issued a NoticeInvitingTender('NIT')on 15^"^ November1998 for removal and disposal of garbage from various designatedpoints inside the OMPNos.295of2008,370of2008,345of2009&364of2009 Page2ofIS o IT operational area and outside the terminal building of the Indira Gandhi International Airport ('IGI Airport'), New Delhi. The Minimum Reserve Price ('MRP') was indicated as Rs. 1,90,000 and the period of licence was five years.

¶3M/s. Shri Hans Enterprises ('Hans'), the proprietory concern of Mr. Sunil Kumar Yadav, bid for the tender. It offered Rs. 3,13,000 per month as licence fee if the garbage was held over to it and Rs. 5,35,000 per month "if entire wet garbage is handed over to us by M/s Taj, Oberoi and Ambassador Flight Kitchens at their premises." A meeting was held between the parties, followingwhichthe AAI issueda letterdated 15^*^ March 1999, awardingthe contract to Hans, inter alia, stating that Hans would pay AAI a sum of Rs. 5,3.5,000 per month as licence fee during the first year of the contract, with a further condition that the licence fee for the subsequent years would be subject to 10% of the compound escalation. The licence fee, so worked out for the 5 years, was set out in the letter. Clause (ix) of the said letter stated that Hans "shall not claim any reduction in licence fee on any account of •whatsoever including non availability of garbage from various agencies as well as due to decrease in the flight movement etc. or due to closure of operation of any airline(s) or closure of airport." Further, it was stated that "All the tenns and conditions mentioned in the tender document will be part and parcel of the agreement."

¶4Although the contractwas awarded to Hans by letter dated 15^*^ March 1999, a foiTTial agreementwas executedonly on 8^'' July 1999, althoughthe periodof5years was to countfrom 25^"^ June 1999. On 25^^ June 1999, AAI issued a letter to Hans where it set out the practice to be adopted by Hans for OMP Nos.295of2008,370of2008,345of2009&364of2009 Page3of15 removal of garbage from IGI Airport. It was stated that a token system would I be introduced, as was being adoptedby the previous Contractor.Clauses 1(c),

(d) and Clause 2 of the said letter read as under:- "(c) You will be required to collect wet garbage comprising of left over fiand in the tray from the flight kitchen units on daily basis and you will collect and carry dray/galley garbage in polythene bags.

(d) Any cutlery items, i.e. knife, fork, spoons etc. if found in the dray garbage will be required to be deposited by you to the respective/airlines/flight kitchen operators once in a month. In case any flight kitchen operators wishes to sort out its garbage, same will be allowed to be done at the sorting point itself

¶2You will also collect and remove the garbage from the designated points as well as flight kitchen units and dispose the same in the prescribed manner and there will be no separate contract for removal of the garbage by any other agency."'

¶5This was followed by the executionof the agreementon S'*" July 1999. Clause 19 of the agreement reads as under:- "19. The licensee shall not claim any reductions in licence fee on any account whatsoever including non-availability of garbage from various agencies as well as due to decrease in the flight movement etc. or due O to closureof operationsof airlinesat the Airport."

¶6Under Clause 21, the licensee, i.e., Hans could not terminate the licence before the expiry period of licence, except by giving 90 days' notice in writing. Under Clause 22, AAI also reservedto itself the right to terminatethe agreement by giving the 90 days' notice in writing without assigning any reasons. Under Clause 23, in the event of any default, failure, negligence and breach etc. by the licensee in complyingwith the licence agreement,AAI was at liberty to determinethe licence and resume possessionof the premises withoutpaymentofany compensationor damagesand also invoke,in full or OMRNos.295of2008,370of2008,345 of2009&364of2009 Page4of15 part, the Bank Guarantee ('BG') furnished by Hans. Under Clause 26, the Award letterdated 15^"^ March 1999 was also to be read as formingpartofthe agreement.

¶7There was also a schedule of garbage bins locations appended to the agreement from where Hans was required to lift the garbage. There were 13 locations within the domestic apron, 15 locations in the International apron. There were 4 garbage collection points within the airport premises and 3 Cj outsidethe airportand 6othernewpoints.

¶8There were General Terms and Conditions ('GTC') appended to the licence agreement. There were also Operating Terms and Conditions ('OTC') appended to the licence agreement. Clauses 16 and 19 of the OTC read as under: "16. The licensee will be required to collect wet garbage comprising of V leftover food in the tray from the Flight Kitchen units on daily basis. To ensure that tarmac is not spoiled when dry garbage is collected at tarmac, the licensee will collect/carry the same in covered trolleys instead of open passenger baggage trolleys. n

¶19The licensee is expected to remove and dispose approximately06 to 10 tonnes of Garbage, which are generated from different sources at IGI Airport as per the above procedure. However,the quantumof Garbage is not guaranteedby AAI and the licensee is expectedto remove and dispose all the Garbage from the designated points. No claim on any accounts for reduction in license fee payable due to non-availabilityof saleable garbage shall be entertained by AAI."

¶9On 28^** June 1999 itself, Hans wrote a letter to the Flight Kitchen Units

(FKUs), i.e., M/s. Taj Air Caterers ('Taj'), M/s. Oberoi Flight Services ('OFS') and M/s. Ambassador Flight Kitchen Operator ('Ambassador'), OMPNos.295of2008,370of2008,34Sof2009&364of2009 P°9e5of15 q/0 requesting them to issue instructions to their employees to handover the garbage to Hans on a daily basis. On 29^*" June 1999, Hans wrote to AAI complaining that the Flight Kitchen Operators (FKOs) were not allowing Hans to remove garbage. AAI then wrote a letter on 2"^ July 1999 to the ^ FKOs, asking them to allow Hans to collectwet garbagewhich had arrived from the aircraft and deposited at flight kitchen. After Hans again complained by lettersdated 7^*^ July 1999and 15^^ July 1999,AAI summonedameetingof Hans and the representatives of FKOs and directed them to handover the wet O garbage to Hans. On 15^^ July 1999, Hans requestedAAI to introducethe token system at Steel Gate No.1 and on 9*'* August 1999, it wrote a letterto AAI requesting that till such time the matter is resolved, it should be permitted to pay the Reserved Price of Rs. 1,90,000, instead of Rs.5,35,000. The problem did not end with Hans repeatedly protesting to AAI by letters dated27'^July 1999 and 29'^July 1999. O

¶10Hans then filed a petition under Section 11 of the Act in this Court for the appointmentof an Arbitrator.By an order dated 14^*^ October 1999, while directing AAI to appoint an Arbitrator, the Court referred the following disputes to arbitration: "(a) Airports Authority of India has failed to ensure supply of wet garbage from the flight kitchen units of Taj Air Caterer, Oberoi Flight Services, Ambassador Flight Kitchen and Chef-Air Flight Kitchen - Effect thereof

(b) Effect of no introducingtokensystemat SteelGate,Terminal-I.

(c) Heavy lossessufferedby the petitionerbecauseof the breachof the terms and conditions committed by the respondents.

(d) In the circumstancesof the case, are the respondentsentitledto claim a sum of Rs. 5-,35,000per month from the claimants? OMPNos.295of2008,370of2008,345of2009&364of2009 Poge6ofIS

(e) That since the respondents are not able to enforce the tenns and conditions of the licence agreement particularly to arrange providing wet garbage from the flight kitchen units of the four caterers and also failure to introduce token system at Steel Gate, Terminal-I, is the petitioner entitled to pay only a sum of Rs. 1,90,000/- per month during the period of contract?

(f) Other disputes related to the matter connected with the licence."

¶11Hans filed its Statementof Claims on 12^ November 1999, inter alia, claiming the following reliefs;

(i) Hans should be permitted to pay AAI Rs.1,90,000 per month till such time AAI ensures supply of wet garbage from the FKUs of Taj, OFS, Ambassador and Chefair Flight Kitchen ('Chefair').

(ii) AAI should be held to have failed to introduce the token system at Steel Gate No.l resulting in loss to Hans of Rs.1,50,000 per month from 25"* June 1999 till the filing of the claim "and further till such time the token system is introduced at Steel Gate No.l."

(iii) Hans also prayed for awarding of damages calculated on the above amount.

(iv) That because of the breaches committed by AAI, Hans was liable only to pay Rs. 1,90,000 per month and AAI had no right to invoke the BG which had been wrongly encashed by it and it should be asked to reimburse the said amount to Hans with interest @ 24% per annum.

¶12It appears that on the failure of OFS to hand over the wet garbage to Flans,it filed a complaintagainstOFS at theMahipalpurPoliceStation(P.S.). OMPNos.295of2008,370of2008,345of2009&364of2009 PoQe7of15 cyi/ The vehicle of OFS, which was removing the wet garbage, was detained by the police. On 11^'^ October2000, AAI wrote to the StationHouse Officer (*SHO'), Mahipalpur P.S. that the matter had been discussed with the Manager of OFS to ensure the delivery of wet garbage to Hans.

¶13AAI filed its reply to the statement of claims, denying that it had committed any breach of the agreement. No evidence was led by the parties. By an Award dated 5^"^ December2001 (hereinafter'the first Award'), the learned Arbitrator rejected the claims of Hans, holding that Clause 16 of the OTCs did not make it obligatory on AAI to ensure the availability of garbage from the flight kitchens. The flight kitchens were not mentioned in the designated points in the schedule to the agreement and, therefore, the plea of Hans that AAI failed to ensure the supply of weight garbage from the flight kitchens was not tenable and there was no occasion for Hans being granted any concession in the licence fee on account of non-availability of garbage in general and from any specific source in particular. Likewise, any claim on the basis of failure to pay AAI to introducethe token system was also not tenable. Hans had failed to substantiate any losses suffered by it and at no time had it invoked Clause 21. At no point of time, AAI bound itself to supply certain qualityand quantityof garbageto beprovidedto Hans. Therewere,therefore, no breach of the terms and conditions of the agreement by AAI.

¶14Aggrievedby the above Award, Hans filed OMP No.l of 2002 under Section34 ofthe Act. The said petitionwas allowedby ajudgmentdated 6^*^ May 2003 by the learnedSingleJudge.It was held that the learnedArbitrator had totally misconstruedthe clausesof the contractin holdingthat AAI was not required to ensure that wet garbage from the flight kitchens was also OMPNOS.295of2008,370of2008,345of2009&364of2009 Sof15 q/j7 handed over to Hans. It was held that the various clauses of the contract, read with the con*espondencebetween the parties, "clearly envisage the removal of wet garbage from flight kitchens." The operative part of the said judgment in para 15 read as under: "15. In view of the foregoing, this Court is of the opinion that the Award of the sole arbitrator, to the above effect was not based on true construction of the terms and conditions of the contract between the parties and correct appreciation of the material inasmuch as he has ignored the certain important clauses of the agreement while arriving at the said findings. In turn it would mean that the award rendered by the arbitrator is clearly in conflict with the public policy of India and therefore, is liable to be set aside. As the claim of the petitioner for damages has been declined and a nil award given on the basis of incorrect construction of the contract between the parties, this Court is of the opinion that it is necessary in ends of justice if the Award is remitted back to the Arbitrator with the direction that the Arbitrator will read the contract between the parties as inclusive of a contract for removal of wet garbage from the four flight kitchens namely Air Taj Air Caterer, Oberoi Flight Service, Ambassador Flight Kitchen and Shefair Flight Kitchen, besides from the designated points as appearing in Annexure "A" of the Licence Agreement dated 8.7.99. In the light of this, the Arbitrator will proceed further to enter the reference as directed by this Court vide order dated 14.10.99."

¶15The above judgment led to the second round of arbitration. The same learned Arbitrator, on remand, passed an Award dated 5^^ July 2005 (hereinafter 'the second Award'), again rejecting the claims of Hans. It was held in the second Award that Hans had not filed any document regarding the non-supply of garbage after 1999-2000. From the documents on record as well as the conduct of the Claimant, it was cleai-that Hans was receiving wet garbage and paying the monthly licence fee. Accordingly, it was held that Hans had failed to prove that the wet garbage was not handed over to it and, therefore, was not entitled to the sums claimed. Hans had also not led OMP Nos.295of2008,370of2008,345of2009&364of2009 Page9of15 Vj evidence to prove that it was entitled to damages for the specific period of the contract. It failed to quantify the garbage or the damage or loss suffered. Hans had the option of not paying the licence fee or terminating the agreement if the wet garbage was not being handed over to it. It was strange that far from raising any such dispute, Hans continued to pay the monthly licence fee of Rs. 5,35,000 along with 10% escalation for the later years. It was, therefore, held that Hans was not entitled to the sums claimed.

¶16The second Award of the learned Arbitrator was challenged by Hans in this Court by filing OMP No.285 of 2005 under Section 34 of the Act. By an order dated 16^^ July 2007, the second Award was set aside by a learned Single Judge of this Court. It was held that despite the learnedSingle Judge havingfound in the order dated 6^^ May 2003 thatthe learnedArbitratorhad overlooked the aspect of removal of wet garbage and remanded the matter to the learned Arbitrator with the direction that the learned Arbitrator would "read the contract between the parties as inclusive of the contract for removal of wet garbage from the four flight kitchens", the second Award ignored the said aspect. The matter was again remanded but this time to a sole Arbitrator appointedby the Courtby its orderdated20"^ July2007.

¶17The learnedArbitrator,who was so appointedby the orderdated 20^'' July 2007, has passed the impugned Award dated 18"^ March 2008 (hereinafter 'the third Award'), in which AAI has been asked to pay Hans a sum of Rs. 1,62,63,984along with interest at 7% per annum "on Rs. 26,64,000/-from the expiry of first year of the licence till payment. Interest @ 7% per annum on Rs. 29,30,400/-from the expiryof the secondyear till payment. Interest @ 7% per annum on Rs. 32,13,440/- from the expiry of the third year till OMP Nos.295of2008,370of2008,345of2009&364of2009 Po9e10of15 o payment. Interest @ 7% per annum on Rs. 35,45,784/- from the expiry of fourth year till payment and interest @ 7% per annum on Rs. 39,00,360/- per annum from the expiry of five years of the licence till payment." Further, AAI has been asked to pay the Respondent Rs. 1,00,000 as costs.

¶18Aggrieved by the third Award, AAI has filed OMP No.295 of 2008. Aggrieved to the extent that interest has been awarded only @ 7% per annum and not 18%per annum, Hans has filed OMPNo.370 of 2008.

¶19During the pendency of the third Award,.the issue arose as regards the entitlement of Hans to further benefits for the period of nine months beyond 25^"^ June 2004. The issuewent beforethe yet anotherlearnedArbitratorwho gave the fourth Award on 2"^ April 2009. By the fourth Award, it was directed that Hans would be entitled to damages at the same rate granted to it in the third Award for the fiirther period of nine months. Both the parties were aggrieved by the said fourth Award. Mr. Sunil Kumar Yadav, the sole proprietor of Hans, has filed OMP No.345 of 2009 on the ground that the 10% increase in the licence fee should have been accounted for a further period of nine months and the interest should have been @ 18% per annum. AAI has filed OMP No.364 of 2009 against the fourth Award to the extent that no amount, at all, should have been awarded to Hans.

¶20This Court has heard the submissions of Mr. Abhinav Vashisht, learned Senior counsel for AAI and of Mr. Sandeep Sethi, learned Senior counsel for Hans. OMPNos.295of2008,370of2008,345of2009&364of2009 Page11 of15

¶21The first issue relates to the scope of the proceedings before the learned Arbitrator who passed the impugned third Award. It was sought to be urged by Mr. Vashisht that the issue decided in the first and the second Award filed pertained to entitlement of Hans to collect the wet garbage, andt what was remitted to the learned Arbitrator to decide was whether at all Hans was entitled to any loss or damages and to what extent. In other words, it was sought to be urged that the learned Arbitrator erred in holding that Hans was to be compensated by AAI for the loss suffered by it on account of it being denied wet garbage from the FKU and that this was in the teeth of Clause 19 of the licence agreement as well as Clause 19 of the OTC. Secondly, it was submitted that the annual licence fee agreed was Rs. 5,35,000 and there was no scope for the reduction of the licence fee at all on any account whatsoever. Thirdly, it was sought to be urged that the evidence on record showed that, in fact, Hans was actually offered wet garbage by the FKUs but did not collect it.

¶22Mr. Sethi referred to the first and the second Award which were comprehensively set aside by the learned Single Judges of this Court. According to him, there was no scope left for AAI to argue that Hans was not entitled to be compensatedfor being deprived of the wet garbage from the FKUs. In other words, only the quantum of damages to which Hans was entitledhad to be decided.It is pointedout that the third Award, in fact, only determinesthe reasonable sum of compensation.Two alternativefigureswere suggestedby Hans beforethe learnedArbitrator.The highersum was based on the licence fee chargedby the FKUs from the Contractorswho collected the wet garbage.The learnedArbitratorawardedthe lesserfigure.It is further submitted that inasmuch as the licence agreement required Hans to pay AAI OMPNos.295of2008,370of2008,345of2009&364of2009 12 of15 penal interest at 18% per annum on delayed payment of licence fee, the same yardstick would apply as regards interest payable by AAI to Hans on the quantified amount of damages. He submitted that as regards the fourth Award, there was no justification for the learned Arbitrator to overlook the clause of the licence deed which required the licence fee to be enhanced by 10% every year. In other words, there damages for the nine months should have been at a rate 10% higher than what was granted by the third Award. O

¶23The judgmentdated 6'*^ May 2003 ofthe learned Single Judge set aside the first Award in its entirety. In other words, the finding of the learned Arbitrator in the first Award that Hans was not entitled to any claim, based on / deprivation of wet garbage from the FKUs was set aside by this Court. Para 15 ofthe judgmentdated 6^'' May 2003 makes is clearthat on the questionof damages to which Hans would be entitled,the matter had to be remittedto the learned Arbitrator. In fact, in the second Award, the learned Arbitrator again went into the questionwhetherHans was entitledat all to collectwetgarbage from the FKUs. This Court, while setting aside the second Award, took umbrage and held that the learnedArbitrator while passing the second Award th ignored the specific directions in the judgment dated 6 May 2003. j

¶24Consequently, at the present stage of challenge to the third Award, AAI ought not to be permittedto again urge that on the basis of Clause 19 of the licenceagreementand the OTCs, Hans is not entitledto be compensatedfor beingdeprivedofthewetgarbage.The only issuethatremainedto bedecided in the third round of arbitration was the quantum of damages to which Hans was entitled. OMPNOS.Z95of2008,370of2008,345of2009&364of2009 PoQe13 of15 f;

¶25AAI is not right in its submission that Hans was claiming reduction in the licence fee. What Hans was asking for was to be compensated for the loss it incurred on account of being deprived of the wet garbage for the five years and then again for a period of nine months when the licence was renewed. Therefore the question of applicability of Cause 19 of the agreement or the OTC did not arise. Two different bases were put forward by Hans for the claim for compensation - one was the differential between the rates offered by it for the dry garbage, i.e., Rs.1,13,000 per annum and Rs.5,35,000 along with an enhancement of 10% every year if it was given the entire wet garbage. The alternative that Hans proposed for quantifying its loss was to go by the licence fee offered by the parties to the FKUs for lifting their wet garbage. No doubt, this would give a reasonable estimate of the value of the wet garbage, which Hans was otherwise entitled to.

¶26This Court is unable to agree with the submissions on behalf of AAI that Hans had failed to quantify the loss suffered by it. The fact that Hans suffered loss was not in doubt. To that extent the third Award is right. As far as the yardstick for determining the loss is concerned, the differential between the two rates offered by Hans, even at the stage of execution of the licence agreement, was a reasonable basis. In the third Award, the learned Arbitrator had adopted that as the basis for determiningthe loss. This was a plausible view for the learned Arbitrator to take and cannot be said to be suffering from any patent illegality.

¶27As regards the awarding of interest at 7%, again this Court is not impressed with the submissionsmade on behalf of Hans that the interest chargedby AAI for the late paymentof licencefee shouldform the basis for OMPNos.295of2008,370of2008,345of2009&364of2009 Page14ofIS c C.) awarding interest on the compensation payable to Hans by AAI for the loss sufferedby Hans. The reasonsfor chargingof penal interestfor late payment obviously cannot be the basis for awarding interest on money dues by AAI to Hans. The award of interest was within the discretion of the learned Arbitrator and it cannot be said that he has exercised it erroneously.

¶28Therefore, as far as the third Award is concerned, this Court fmds no ground having been made out for interference under Section 34 of the Act.

¶29As far as the fourth Award is concerned, the differential licence fee offered by Hans was only a yardstick for determining the loss suffered by it. Once it is clear that what was being awarded to Hans was not the refund of any excess licence fee but only the compensation for the loss suffered by it, then the quantification of the loss for the nine months' period on the same basis as determined in the third Award could not be said to be erroneous or suffering from any patent illegality. This Court therefore does not fmd any reason to interfere with the fourth Award of the learned Arbiti-ator.

¶30Resultantly, all the four petitions are dismissed, but in the circumstances, with no order as to costs. November 20, 2012 tp S. MURALIDHAR, J. OMPNos.295of2008,370of2008,345of2009&364of2009 Poge15of15

Case details

Parties and counsel

o * IN THE HIGH COURT OF DELHI AT NEW DELHI #45,46, 47&48 + OMP 295 of 2008 AIRPORTS AUTHORITY OF INDIA Petitioner Through: Mr. Abhinav Vashisht, Senior Advocate with Mr. Digvijay Rai, Mr. B,K. Goel, Ms. Amrita Jayan and Mr. Raman Kumar, Advocates versus M/S. HANS ENTERPRISES & ANR Respondents Through: Mr. Sandeep Sethi, Senior Advocate with Mr. P.S. Bindra & Ms. Preeti Gupta, Advocates AND OMP 370 of 2008 M/S. SI-D^ HANS ENTERPRISES Petitioner Through: Mr. Sandeep Sethi, Senior Advocate with Mr. P.S. Bindra & Ms. Preeti Gupta, Advocates versus AIRPORTS AUTHORITY OF INDIA Respondent •Through: Mr. Abhinav Vashisht, Senior Advocate with Mr. Digvijay Rai, Mr. B.K. Goel, Ms. Amrita Jayan & Mr. Raman Kumar, Advocates and of 2009 SUNIL KUMAR Petitioner Through: Mr. Sandeep Sethi, Senior Advocatewith OMP Nos.295of2008,370of2008,345of2009&364of2009 Page1of15 & Mr. P.S. Bindra & Ms. Preeti Gupta, Advocates versus AIRPORTSAUTHORITYOFINDIA Respondent Through: Mr. Abhinav Vashisht, Senior Advocate with Mr. Digvijay Rai, Mr. B.K. Goel, Ms. Amrita Jayan & Mr. Raman Kumar, Advocates and O ' OMP 364 of2009 AIRPORTS AUTHORITY OF INDIA Petitioner Through: Mr. Abhinav Vashisht, Senior Advocate with Mr. Digvijay Rai, Mr. B.K. Goel, Ms. Amrita Jayan & Mr. Raman Kumar, Advocates versus M/S. SHRI HANS ENTERPRISES & ANR Respondents Through: Mr. Sandeep Sethi, Senior Advocate with Mr. P.S. Bindra & Ms. Preeti Gupta, Advocates CORAM: JUSTICE S. MURALIDHAR

Source: High Court of Delhi, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.