- Court
- High Court of Delhi
- Decided
- 7 May 2019
- Bench
- Rajiv Sahai Endlaw
- Case no.
- CS(COMM) 271/2016
Judgment
RAJIV SAHAI ENDLAW, J. MAY 07, 2019 "gsr" (Corrected & released on 6th June, 2019)
Case details
Parties and counsel
* IN THE HIGH COURT OF DELHI AT NEW DELHI % Date of decision: 7th May, 2019 + CS(COMM) NO. 271/2016 & IA No. 12596/2016 (u/O VII R-11 CPC) SOFTWARE ONE INDIA PVT. LTD. ..... PLsAINTIFF Through: Mr. Manoj Kumar Sahu, Adv. Versus C&S ELECTRIC LTD. ...DEFENDANT Through: Mr. Chander M. Lall, Sr. Adv. with Ms. Nancy Roy & Mr. Rupin Bahl, Advs. CORAM: HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW 1. The plaintiff has sued the defendant for recovery of Rs.1,18,55,172/- pleading that: (i) the plaintiff is a software licensing company; (ii) the defendant placed a purchase order dated 27th June, 2011 on the plaintiff seeking delivery of various software licenses of Microsoft from the plaintiff, for a period of three years, on year 1, year 2 and year 3 basis; (iii) under the said purchase order, the defendant was liable to pay license fee of Rs.52,75,531/- for each of the three years and the plaintiff was to deliver to the defendant software licenses of Microsoft on yearly basis for a consecutive period of three years; (iv) an Enterprise Enrollment Agreement dated 28th June, 2011 was entered between the plaintiff, Microsoft and the defendant, for a term of 36 months, on year 1, year 2 and year 3 basis; as per the said agreement all the products were to be imported directly from the principal publisher Microsoft to the defendant and the plaintiff was appointed as the re-seller to meet the terms of pricing and delivery of licenses and payment of billing etc. to the defendant; (v) the aforesaid Enterprise Enrollment Agreement could only be terminated or renewed as per the termination clause thereof; in view of the termination clause, it was clear that the defendant had no right to terminate the already existing enrollment under the agreement and the defendant had a right only to terminate the ability to enter into new enrollments under the agreement, by giving 60 days notice; (vi) in compliance with the agreed terms of the purchase order, the software licenses were duly delivered to the defendant for year 1 and the defendant in turn had also paid outstanding dues for the year 1 invoice as raised by the plaintiff on the defendant; Microsoft in turn raised an invoice on the plaintiff for year 1 and the plaintiff duly made payment against the said invoice as raised by Microsoft; (vii) the plaintiff, for due compliance of year 2 of the purchase order had delivered the software licenses to the defendant and raised an invoice dated 7th July, 2012 on the defendant and the defendant was liable to pay Rs.59,27,586/- including taxes to the plaintiff within a month of the date of the invoice; Microsoft raised a corresponding invoice dated 28th June, 2012 for year 2 for a sum of Rs.52,72,532.79 on the plaintiff and the plaintiff made payment thereof to Microsoft; (viii) however, the defendant failed and refused to make the payment against the invoice dated 7th July, 2012 in spite of repeated requests and reminders of the plaintiff; the plaintiff got served a legal notice dated 8th April, 2013 on the defendant; (ix) the defendant, in response dated 22nd April, 2013 to the legal notice of the plaintiff, took a stand that the defendant had consulted and communicated to Microsoft vide letter dated 27th April, 2012 that the defendant did not wish to renew the Enterprise Agreement; however the said stand of the defendant was incorrect as the Enterprise Agreement was perpetual in nature for an agreed term of 36 months and could not be terminated mid-term; (x) the plaintiff also received a letter dated 30th May, 2013 from Microsoft informing the plaintiff that Microsoft had communicated to the defendant that the Enterprise Agreement was perpetual and could not be terminated mid-term; and, (xi) Microsoft raised an invoice dated 28th June, 2013 for year 3 on the plaintiff and the plaintiff has made payment thereof as well. The plaintiff raised a corresponding invoice dated 15th July, 2013 on the defendant for a sum of Rs.59,27,586/- but which also has not been paid by
Source: High Court of Delhi, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.