VoxJuris
Home › High Courts › Delhi High Court 2016 › High Court of Delhi

Punj Lloyd Ltd v. National Highways Authority of India & Anr

Court
High Court of Delhi
Decided
25 October 2016
Bench
S. Muralidharauthor
Case no.
O.M.P.(I) 82/2015

Follow Delhi High CourtFollow S. Muralidhar

Judgment

O R D E R %

25.10.2016

¶1This is a petition under Section 9 of the Arbitration and Conciliation Act, 1996 ('Act') seeking stay of the bank guarantee (BG) issued in favour of the Respondent No. 1.

¶2The interim order passed on 13th March 2015 inter alia directing that "subject to the Petitioner keeping the bank guarantee bearing SR No. 556880, BG No. 0007BG0016190 for an amount of Rs. 4,96,63,412 alive, the Respondents are directed to maintain status quo as on date with regard to invocation of the said bank guarantee till the next date of hearing.

¶3At the subsequent hearing on 1st July 2015 the Court directed that a joint

inspection was to be undertaken for the purpose of determining the defective work as alleged by the Respondent No. 1. It was to ascertain to what extent the defective work pointed out in the defect liability period has been rectified and what defective work remained to be identified.

¶4As noted in the subsequent order dated 22nd February 2016 a joint inspection report dated 17th October 2015 noted the financial implication in the defective period as Rs. 4,98,29,139 which was higher than the Bank Guarantee in question.

¶5Consequently, according to Respondent No. 1, even going by the decision of the Supreme Court in Fenner (India) Limited v. Punjab and Sind Bank

(1997) 7 SCC 89 since the claim of Respondent No. 1 would be higher than the Bank Guarantee there is no justification for stay of the encashment of the unconditional Bank Guarantee.

¶6The case of the Petitioner is on the other hand as noted in the order dated 22nd February 2016 that the snag list was prepared on 22nd April 2011 and therefore, the valuation of implication has to be assessed as of the year 2011 and not for the period of inspection, i.e., October 2015. It is plain, therefore, that the dispute between the parties is whether the value of the extent of the defective work is as determined in the inspection report dated 17th October 2015 or as claimed by the Petitioner.

¶7In the considered view of the Court, the above dispute cannot be examined in the present petition and therefore, will have to be examined in

the arbitral proceedings. It is to be noted that the Petitioner had till date not invoked the arbitration clause seeking reference of the disputes to arbitration.

¶8Mr. Sandeep Sethi, learned Senior counsel for the Petitioner states that the Petitioner seeks the disputes to be resolved through negotiations. However, that has not succeeded.

¶9The Court does not see that any purpose would be served in keeping the petition pending as it is plain that the parties will have go in for arbitration without any undue delay. The Court is also not satisfied that any case is made out for continuation of the interim direction as regards encashment of the BG. Consequently, the interim order passed on 13th March 2015 and continued thereafter is hereby vacated.

¶10The petition is dismissed.

¶11It is made clear that the anything stated in the present order will not influence the final decision that may be taken in the arbitral proceedings.

S.MURALIDHAR, J OCTOBER 25, 2016 Rm

Case details

Parties and counsel

* IN THE HIGH COURT OF DELHI AT NEW DELHI + PUNJ LLOYD LTD ..... Petitioner Through: Mr. Sandeep Sethi, Senior Advocate with Mr. Rajeev M. Roy, Advocate. versus NATIONAL HIGHWAYS AUTHORITY OF INDIA & ANR ..... Respondents Through: Mr. Pradeep K. Bakshi with Ms. Prachi V. Sharma and Mr. K. Pandit, Advocates. CORAM: JUSTICE S.MURALIDHAR

Source: High Court of Delhi, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.