- Court
- High Court of Gauhati
- Decided
- 14 September 2023
- Bench
- Devashis Baruah
- Case no.
- WP(C) 6816/2014
Judgment
JUDGMENT AND ORDER (ORAL) Date : 14-09-2023
¶1Sixty one writ petitioners have joined together and filed the instant writ petition challenging the order dated 15.09.2012 passed by the Principal Secretary, Government of Assam, P&RD Department whereby the claims of the Petitioners for payment of their outstanding dues were rejected and also seeking a direction upon the Respondent Authorities to release/pay the admitted amount of Rs.58,00,198/- to the Petitioners on account of contractual works performed and executed by them under the SGRY Scheme of Darrang Page No.# 12/19 Zilla Parishad.
¶2The facts of the instant case as could be discerned from a perusal of the writ petition is that the Petitioners claimed that they were allotted various contractual works by the Darrang Zilla Parishad under the Sampurna Gramin Rojgar Yojona (SGRY) for the financial year 2006-2007. It was alleged that the various works were carried out by the respective committees headed by the Petitioners as the President of the said committees which were supervised by the Assistant Project Officers (Technical) and the Junior Engineers working under the Darrang Zila Parishad. The Petitioners claimed that they had completed the allotted works within the stipulated time without there being any complaint as regards the nature and quality of the work but the Petitioners have not been paid their outstanding dues except making a meager part payments. The Petitioners further claimed that the total outstanding amount of which the Petitioners as a whole are entitled to is Rs.58,00,198/- against 67 numbers of Schemes. Various representations were submitted from time to time by the Petitioners but the said amounts were not paid for which the Petitioners filed separate writ petitions before this Court.
¶3This Court vide a common judgment and order dated 08.06.2011 disposed of the said writ petitions thereby directing the Principal Secretary to the Government of Assam, P&RD Department to look into the matter and after considering the communication dated 01.07.2009 to pass an order with regards to the claims of the Petitioners and also to issue appropriate directions to the Chief Executive Officer, Darrang Zila Parishad accordingly and the said exercise was directed to be completed within a period of two months. The Petitioners upon receipt of the certified copy of the said judgment, placed it before the Page No.# 13/19 Principal Secretary to the Government of Assam, P&RD Department for compliance to the directions passed. Thereupon, the impugned order dated
15.09.2012 was passed by the Respondent No.1 which have been put to challenge before this Court.
¶4From a perusal of the writ petition, it transpires that it is on account of the order dated 15.09.2012 that the Petitioners have not been paid their dues and as such it is necessary for this Court to analyse as to whether any interference can be made to the order dated 15.09.2012 as well as also take into account that as to whether a writ in the nature of certiorari can be issued for setting aside the said order.
¶5Now coming to the impugned order, it would be seen that the P&RD Department had entrusted to cause a detailed enquiry into the matter vide an order dated 26.08.2011. The Joint Secretary of the P&RD Department had submitted his enquiry report on 22.02.2012 which was found by the P&RD Department to be not in order for which a 3 (three) member committee was constituted comprising of one Joint Secretary of the P&RD Department, One Joint Director (Tech) of the Commissionerate of P&RD and the Financial Advisor, P&RD Department to re-examine the matter. The three member committee thereupon submitted their enquiry report on 26.07.2012. In the said report so submitted, the enquiry team found only 17 numbers of Schemes which tally with the list of Schemes furnished by the CEO in his letter dated
01.07.2009 and accordingly, the report was based on these 17 Schemes. It was found that out of the 17 Schemes, the enquiry team could trace out only 4 numbers of schemes from the Action Plan 2006-07 and the total estimated amount of these 4 numbers of schemes were Rs.5,00,000/-out of which an Page No.# 14/19 amount of Rs.84,920/-were received by some of the Petitioners as per their records. It is also apparent from the enquiry report that the Government of India vide a letter dated 23.03.2007 had issued certain directions which were :-
(i) No new SGRY works should be taken up w.e.f. 23.03.2007 as no further fund would be released under SGRY during 2007-08.
(ii) All works undertaken under SGRY should be completed by 31.03.2007; and
(iii) If such Schemes cannot be completed due to unavoidable circumstances during 2006-07 i.e. by 31.03.2007, the Schemes may be completed with the balance available fund on 01.04.2007 under the SGRY at the earliest.
¶6It also appears that pursuant to the Government letter dated 23.03.2007, the Government of India issued another communication dated 14.08.2007 stating that in case there are still incomplete SGRY work in NREGA Phase II Districts (where Darrang District was covered), the same has to be closed w.e.f. 31.08.2007 and no further expenditure is to be incurred on them. It was further directed vide the said letter dated 14.08.2007 that the entire balance funds of the SGRY as on 31.08.2007 must be transferred immediately to a separate account created for NREGA works, if not done so far.
¶7The impugned order dated 15.09.2012 further reveals that in terms with the enquiry report, as per Office record of the CEO, Zila Parishad Darrang, the closing balance under SGRY as on 31.03.2007 was Rs.4,27,283/- and the CEO, Zila Parishad Darrang received an amount of Rs.97,63,000/- under SGRY Programme during the period from 07.04.2007 to 06.06.2007 and out of which Page No.# 15/19 the amount received on 06.06.2007 was Rs.37,48,000/-. It was further mentioned that after discontinuance of the SGRY Scheme, the total available fund with the Zila Parishad, Darrang during 2007-08 was Rs.1,01,90,283/- of which an amount of Rs.1,01,65,834/- was spent leaving a balance of Rs.24,449/- till closure of the SGRY Scheme as on 31.08.2007. Further, it was also mentioned that the 17 numbers of Schemes which were duly taken note of by the enquiry committee were executed during the period from February, 2007 to May, 2007 and the total estimated amount of the Schemes were Rs.17,35,000/- out of which an amount of Rs.3,80,592/- were paid. The reason for non-payment of the bills out of the available funds of Rs.37,48,000/- which was received by the CEO, Zilla Parishad Darrang on 06.06.2007 could not be confirmed by the enquiry team. It was however mentioned that in the enquiry report, there was no instructions/orders from the CEO, Zilla Parishad Darrang to execute the works by the Petitioners. In the said impugned order dated
15.09.2012, the various guidelines of SGRY were taken into account and thereupon the conclusions have been recorded in the said order which are enumerated hereinunder: "(1) Total fund received by Zila Parishad, Darrang under SGRY Scheme during the year 2007-08 as on 6/6/2007 (after discontinuance of SGRY scheme i.e. afier 31/3/2007) was Rs.1,01,90,283/- and the amount received by ZP, Darrang on 6/6/2007 was Rs.37,48,000/. So the question of clearance pending bills which appears to be in between Feb 2007to May 2007 from the State share which was released by State Govt after 31/8/2007 does not arise.
(2) 17 nos. of schemes were found to be executed during Feb/2007 to May/2007. The reason for non-payment of the bills in question out of the available fund of Rs.1,01,90,283/- could not be confirmed by the enquiry team. Page No.# 16/19
(3) Schemes in question were executed in violation of clause 5.16.1, 6.1.1, 6.1.5 &
6.6.1 of SGRY guideline.
(4) The State share which was released by State Govt. after closure of SGRY account i.e. after 31/8/2007 was deposited into new NREGA Account as per GoI's instruction.
(5) Instead of engaging local rural poor wage earners, the schemes were executed by the petitioners through construction committee by constituting themselves by suo-moto will.
(6) The works undertaken by the petitioners in the field were without any instruction from CEO, ZP, Darrang as well as it appears to be executed before receipt of its due share by ZP, Darrang, which is violation of FRBM Rules."
¶8From the above conclusions so arrived at vide the impugned order dated
15.09.2012, it reveals that as the total fund received by the Zila Parishad Darrang under the SGRY Scheme during the year 2007-08 as on 06.06.2007 (after discontinuation of the SGRY Scheme i.e. after 31.03.2007) was Rs.1,01,90,283/- and the amount received by the ZP, Darrang on 06.06.2007 was Rs.37,48,000/- and as such the question of clearance of the pending bills which appears to be in between February, 2007 to May, 2007 from the State share which was released by the State Government after 31.08.2007 does not arise. It was further observed in the conclusions that 17 numbers of the Schemes were found to be executed during February, 2007 to May, 2007 and the reasons for non-payment of the bills in question out of the available funds of Rs.1,01,90,283/- could not be confirmed by the enquiry team. It is further seen from the conclusions arrived at that the State share which was released by the State Government after closure of SGRY account i.e. after 31.08.2007 was deposited in the new NREGA Account as per the Government of India's Page No.# 17/19 instructions. It was also concluded in the impugned order that the Schemes were executed by the Petitioners through construction committee by constituting themselves suo-moto instead of engaging local rural poor wage earners. Further to that, it has also been mentioned that the works undertaken by the Petitioners in the field were without any instructions from the CEO, ZP Darrang as well as it appears to be executed before the receipt of its due share by the ZP, Darrang which was in violation of the FRBM Rules. It is on the basis of the said conclusion, that the claims of the Petitioners were found to be not justified and hence were rejected.
¶9From the above, therefore it reveals that although the Petitioners claimed to have completed the works pertaining to 67 Schemes, the 3 (three) member committee only found that only 17 numbers of Schemes of the Petitioners tally with the list of schemes furnished by the CEO. On the basis of the 17 schemes, the enquiry committee could only trace out only 4 (four) numbers of schemes from the Action Plan 2006-07. It is also seen from the impugned order that there is an admission to the effect that there were 17 numbers of schemes which were executed during February 2007 to May 2007 and the total estimated amount of the Schemes were Rs.17,35,000/- out of which Rs.3,80,592/- was paid. The enquiry report so submitted however did not state as to why the said remaining amount could not be paid out of the available fund with the Zilla Parishad, Darrang. It further appears from the enquiry report that there was no instructions/orders from the CEO, Zilla Parishad, Darrang to execute the works by the Petitioners. It further shows that there has been certain allegations that there are violations to the SGRY Guidelines more particularly to Clause 5.16.1, 6.1.1, 6.1.5 and 6.6.1. It also transpires that there are admissions to the effect in the impugned order itself that the 17 Page No.# 18/19 numbers of schemes were executed by the Petitioners though construction committee constituted by themselves. Therefore, the fact as to whether the Petitioners are entitled to any amount remains inconclusive in view of the report on which the impugned order was passed, more so in respect to the 17 numbers of schemes which was duly taken note of by the enquiry committee.
¶10It is also relevant to take note of that as to whether the Petitioners were allotted the works in terms with the SGRY Guidelines; as to whether the Petitioners completed the works as per the allotment of the works made to the Petitioners and as to how much amount the Petitioners would be entitled to are factual determination which cannot be made by this Court under article 226 of the Constitution. Be that as it may, the order which was passed on 15.09.2012 in the opinion of this Court is also an inconclusive determination so made and on the basis of the said order, the Petitioners cannot be denied their entitlement if the Petitioners prove in a competent Court of jurisdiction that they have been allotted the work as per the guidelines and they have duly completed the work and accordingly are entitled to the claimed amount.
¶11This Court also cannot be unmindful of the fact that the claims as regards the entitlement of the amounts have been pursued by the Petitioners since 2009 itself when the Petitioners filed their first set of writ petitions and thereupon the Petitioners diligently have been pursuing the instant writ petition for claiming the amount to which the Petitioners are entitled to. This Court while exercising the jurisdiction under Article 226 of the Constitution cannot adjudicate these factual aspects for the reasons above mentioned and as such the reliefs so sought for as regards the direction for payment of an amount of Rs.58,00,198/- to the Petitioners cannot be issued by this Court. Page No.# 19/19
¶12Under such circumstances, the instant writ petition stands disposed of thereby granting liberty to the Petitioners to avail remedies before the competent Civil Court against the Respondents claiming the amount due to them on the basis of their contracts and the order dated 15.09.2012 shall not act as a bar in granting the Petitioners their reliefs if the Petitioners prove their entitlement before the competent Civil Court.
¶13This Court further observes and clarifies that taking into account that the Petitioners have been pursuing their remedies diligently before this Court since 2009, the Petitioners would be entitled to the benefit of Section 14 of the Limitation Act, 1963, if any suit is being filed.
¶14With the above observations and directions, the instant writ petition stands disposed of.
JUDGE Comparing Assistant
Case details
Parties and counsel
PageoNo.#o1/19 GAHC010020042014 ooooooo ooooooooooooooo ooooooooooooooooTHEoGAUHATIoHIGHoCOURTo (HIGHoCOURToOFoASSAM,oNAGALAND,oMIZORAMoANDoARUNACHALoPRADESH)o CaseoNo.o:oWP(C)/6816/2014ooooooooo RANJUMONIoSARMAHoando60oORSo S/OoSRIoJITENoSARMAH,oR/OoSANKARoNAGAR,oBHEBARGHAT,oP.O.oandoP.S.o MANGALDOI,oDIST.oDARRANG,oASSAM,oPINo784125 2:oMD.oHABIBURoRAHMAN oSONoOFoLATEoJONABoALI oRESIDENToOFoVILLAGEoHIRAPARA oP.O.oDHULA oDISTRICT-DARRANG oASSAMoPINo784146 3:oMD.oMOZAMILoHOQUE oSONoOFoMD.oRAHIMUDDINoAHMED oRESIDENToOFoVILLAGEoADHIKARI oP.O.oRAJGHAToDISTRICT-DARRANG oASSAM.oPINo784125 4:oMD.oABDULoHAMID oSONoOFoABDULoLATIF oRESIDENToOFoVILLAGEoDUMINICHOWKI oP.O.oMARWACHOWKI oDISTRICT-DARRANG oASSAMoPINo784145 5:oMD.oAZIZULoMAZID oSONoOFoENAMULoMAZID oRESIDENToOFoVILLAGEoandoP.OoBYASPARA oDISTRICT-DARRANG oASSAMoPINo784125 6:oSRIoBICHITRAoNATH Page No.# 2/19 SON OF SRI PHULESWAR NATH RESIDENT OF VILLAGE KABIKARA P.O. JANARAM CHOWKA DISTRICT-DARRANG ASSAM. PIN 784529 7: MD. SAMSUL HOQUE SON OF ABDUL BAREK RESIDENT OF VILLAGE KANAICHUBA P.O. HOWLY MOHANPUR DISTRICT-DARRANG ASSAM PIN 784529 8: ABU BAKKAR SIDDIQUE SON OF LATE AHMED ALI RESIDENT OF VILLAGE DUMUNI CHOWKI P.O. MARUAWA CHOWKI DISTRICT-DARRANG ASSAM PIN 784145 9: KHABIRUDDIN AHMED SON OF LATE KASEM ALI RESIDENT OF VILLAGE and P.O. SANOWA DISTRICT-DARRANG ASSAM. PIN 784145 10: MD AHSAN ALI SON OF LATE JAMATULLA ALI RESIDENT OF VILLAGE and P.O. SANOWA DISTRICT-DARRANG ASSAM PIN 784145 11: SRI HEMANTA DEKA SON OF MINARAM DEKA RESIDENT OF VILLAGE and P.O. MENAPARA DISTRICT-DARRANG ASSAM. PIN 784125 12: MD MAJAR ALI SON OF LATE ARAJ ALI RESIDENT OF VILLAGE BANDIA GOAN P.O. MANGALDAI DISTRICT-DARRANG ASSAN. PIN 784125 PageoNo.#o3/19 13:oSRIoKANESWARoDEKA oSONoOFoLATEoBENUoDEKA oRESIDENToOFoVILLAGEoSENGAPATHAR oP.O.oSENGAPATHARoKALAIGAONoDISTRICT-DARRANG oASSAM.oPINo784525 14:oMD.oATIKURoHUSSAIN oSONoOFoLIYAKAToALI oRESIDENToOFoVILLAGEoNIRANoCHUBA oP.O.oPATHARIGHAT oDISTRICT-DARRANG oASSAM.oPINo784145 15:oMD.oRAJIBoAHMED oSONoOFoLATEoMATLIBoALI oRESIDENToOFoVILLAGEoGHORASHAL oP.O.oPATHARIGHAT oDISTRICT-DARRANG oASSAM.oPINo784145 16:oSARIFULoHOQUE oSONoOFoLATEoDALISHAoSHEIKH oRESIDENToOFoVILLAGEoNO.2oBEZPARA oP.O.oHOWLYoMOHANPUR oDISTRICT-DARRANG oASSAM.oPINo784529 17:oMD.oHASIBUDDINoAHMED oSONoOFoLATEoHABIBARoRAHMAN oRESIDENToOFoVILLAGEoSANOWAoTARI oP.O.oSANOWA oDISTRICT-DARRANG oASSAM.oPINo784145 18:oSRIoHIRENoSARMAH oSONoOFoLATEoJOGENDRAoSARMAH oRESIDENToOFoVILLAGEoBAMUNPARA oP.O.oMANGALDAI oDISTRICT-DARRANG oASSAM.oPINo784125 19:oMD.oSAHARoALI oSONoOFoLATEoSAYEDoALI PageoNo.#o4/19 oRESIDENToOFoVILLAGEoGHILAKURI oP.O.oBARAMPUR oDISTRICT-DARRANG oASSAM.oPINo784144 20:oMD.oZIAULoHASSAN oSONoOFoLATEoSADULLAoAHMED oRESIDENToOFoMANGALDAIoTOWN oWARDoNO.2 oP.O.oMANGALDAI oDISTRICT-DARRANG oASSAM.oPINo784125 21:oMD.oJAINURoALI oSONoOFoLATEoBASHIRoALI oRESIDENToOFoVILLAGEoHETAMTOLA oP.O.oSIPAJHAR oDISTRICT-DARRANG oASSAM.oPINo784145 22:oMD.oMATLEBoALI oSONoOFoLATEoRAMJANoALI oRESIDENToOFoVILLAGEoBOTABARI oP.O.oDHULAoDISTRICT-DARRANG oASSAM.oPINo784146 23:oSRIoSANJIBoKUMARoKALITA oSONoOFoSRIoCHANDAMALoKALITA oRESIDENToOFoVILLAGEoBORKOLAoBAGICHA oP.O.oBORKOLAoCHOWKA oDISTRICT-DARRANG oASSAM.oPINo784525 24:oMD.oHABIBARoRAHMAN oSONoOFoMD.oANOWARoHUSSAIN oRESIDENToOFoVILLAGEoKHATOWALPARA oP.O.oHOWLYoMOHANPUR oDISTRICT-DARRANG oASSAM.oPINo784529 25:oABDULoHANNAN oSONoOFoMD.oHAKIMoALI oRESIDENToOFoVILLAGEoMUSLIMoGHOPA PageoNo.#o5/19 oP.O.oSIPAJHAR oDISTRICTo-DARRANG oASSAM.oPINo784145 26:oMD.oILIASoALI oSONoOFoLATEoIDRISHoALI oRESIDENToOFoVILLAGEoMOLLAPARA oP.O.oHOWLYoMOHANPUR oDISTRICT-DARRANG oASSAM.oPINo784529 27:oMD.oKHAIRULoISLAM oSONoOFoMD.oKHASNURoALI oRESIDENToOFoVILLAGEoKANAICHUBA oP.O.oHOWLYoMOHANPUR oDISTRICT-DARRANG oASSAM.oPINo784529 28:oMD.oRAFIKULoISLAM oSONoOFoABDULoJABBAR oRESIDENToOFoVILLAGEoBOTABARI oP.O.oDHULAoDISTRICTo-DARRANG oASSAM.oPINo784146 29:oMD.oFAIZUDDINoAHMED oSONoOFoDIDARUDDINoAHMED oRESIDENToOFoVILLAGEoKANAICHUBA oP.O.oHOWLYoMOHANPUR oDISTRICT-DARRANG oASSAM.oP
Source: High Court of Gauhati, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.