Ratul Sarmah v. The State of Assam and 6 Ors

Disposed Of
Court
High Court of Gauhati
Decided
30 August 2023
Bench
Devashis Baruahauthor
Case no.
WP(C) 851/2021

Judgment

ORDER Date : 30.08.2023

¶1The case of the Petitioner herein is that the Petitioner is aggrieved by the inaction on the part of the Respondent Authorities in making payment of the bills of the Petitioner. The case of the Petitioner herein is that the Petitioner has participated in the tender process for special repair and annual repair works of roads, Dibrugarh Road Division under Tengakhat Road Sub-Division. Being successful bidder, the Petitioner was issued 6 (six) formal work orders which are

(I) CE/DEV/TB/326/02/12 dated 28.02.2002 (II) CE/ DEV/TB/326/02/13 dated

28.02.2002, (III) CE /DEV/TB/326/02/2001-02 dated 18.01.2002, (IV) CE /DEV/TB/326/02/14 dated 28.02.2002, (V) CE/DEV/TB /326/25/2001-02 dated

18.01.2002, and (VI) CE /DEV/TB/326/25/2001-02 dated 18.01.2002. It was further mentioned in the formal work orders that the work be completed within Page No.# 3/4 a period of 3 (three) months from the date of issue of formal work order.

¶2It is the case of the Petitioner that the Petitioner successfully executed the works and to that effect completion certificates were also issued and accordingly submitted the bills for the said works. As per the Petitioner, the Petitioner is entitled to amount of Rs.1,52,89,990/-. It is the further case of the Petitioner that the Petitioner had submitted various representations to the Respondent Authorities time and again for release of the amount however the said amount of Rs.1,52,89,990/- is still pending, for which the Petitioner has approached this Court under Article 226 of the Constitution.

¶3Mr. R. Dhar, the learned Standing counsel appearing on behalf of the Public Works (Roads) Department submitted that as to whether the Petitioner has completed the work in terms with the work orders in question is a subject matter of verification which needs to be carried out by the Respondent Authorities and it is only on the basis of such verification, the actual entitlement of the Petitioner could be ascertained.

¶4Upon hearing the learned counsels for the parties, this Court is of the opinion that the interest of justice would be met if a direction is given to the Respondent Authorities to verify as to whether the Petitioner has completed the work in accordance with the formal work orders mentioned hereinabove and thereupon to ascertain the exact amount to which the Petitioner is entitled to, if any.

¶5It is under such circumstances, this Court therefore disposes of the instant writ petition thereby directing the Respondent Authorities more particularly the Respondent Nos. 2, 5 and 6 to verify the entitlement of the Petitioner on the basis of the tender conditions as well as the formal work orders which were Page No.# 4/4 issued in favour of the Petitioner and as to whether the Petitioner has completed the work in question and thereupon, after verification if it is found that the Petitioner is entitled to any amount, the same should be paid to the Petitioner in terms with the judgment of the Full Bench of this Court in the case of Tamsher Ali and Others Vs. State of Assam and others reported in 2008 (4) GLT 1. The said verification be completed within a period of 2 (two) months from the date a certified copy of the instant order is served upon the Respondent No.2.

¶6With above observations and directions, the instant writ petition stands disposed of.

JUDGE Comparing Assistant

Case details

Parties and counsel

PageoNo.#o1/4 GAHC010022042021 ooooooo ooooooooooooooo ooooooooooooooooTHEoGAUHATIoHIGHoCOURTo (HIGHoCOURToOFoASSAM,oNAGALAND,oMIZORAMoANDoARUNACHALoPRADESH)o CaseoNo.o:oWP(C)/851/2021o RATULoSARMAHo S/OoLATEoGANESHoSARMAH,oR/OoKUMARANICHIGAoGAON,oP.O.oRAJAo BHETA,oP.S.oDIBRUGARH,oDIST.oDIBRUGARH,oASSAM,oPINo786008 VERSUSo THEoSTATEoOFoASSAMoANDo6oORSo REPRESENTEDoBYoTHEoCOMMISSIONERoANDoSPECIALoSECY.oTOoTHEo GOVT.oOFoASSAM,oPUBLICoWORKSo(ROADS)oDEPTT.,oDISPUR,oASSAMo 781006 2:THEoCOMM.oANDoSECY. oFINANCEoDEPTT. oGOVT.oOFoASSAM oDISPUR oASSAM oGHY-6 3:THEoCHIEFoENGINEER oPWRD oASSAM oCHANDMARI oASSAMoAToGHY-3 4:THEoADDL.oCHIEFoENGINEER oPWRD oEASTERNoZONE oDIBRUGARH 5:THEoSUPERINTENDINGoENGINEER oPWRD oDIBRUGARHoROADoCIRCLE Page No.# 2/4 DIBRUGARH 6:THE EXECUTIVE ENGINEER PWRD DIBRUGARH RURAL ROADS DIVISION DIBRUGARH 7:EXECUTIVE ENGINEER P.W.D. DIBRUGARH LAHOWAL TINGKHONG TERRITORIAL ROAD DIVISION DIBRUGAR For the Petitioner(s) : Mr. D. Gogoi, Advocate For the Respondent(s) : Mr. R. Dhar, Standing Counsel, PWD BEFORE HONOURABLE MR. JUSTICE DEVASHIS BARUAH

Source: High Court of Gauhati, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.