- Court
- High Court of Gauhati
- Decided
- 31 August 2023
- Bench
- Devashis Baruah
- Case no.
- WP(C) 1156/2020
Judgment
O R D E R
31.08.2023
The instant writ petition has been filed seeking a writ in the nature of mandamus directing the respondents to release the security deposit in relation to the contract work with interest.
¶2The facts involved in the instant writ petition as could be seen from a perusal of the pleadings are that a work order dated 24.09.2015 was issued in favour of the petitioner for supply, fabrication, fixing and fixing of MS C-section with other allied works at 200 KW MW DRM Transmitter AIR, Pasighat. From a perusal of the said work order dated 24.09.2015, it reveals that there are various terms and conditions mentioned therein. It further reveals that value of the work order was mentioned as Rs.4,10,000/-. The period of completion of the work was 30 days from the date of issuance of the work order or LoI whichever is earlier. As per Clause 9 of the terms and conditions stipulated in the work order, 10% of the work value would be retained as security deposit for the warranty period from the date of completion of the work. In terms with Clause 13 Page No.# 3/5 of the work order, the liquidated damage for late delivery was stipulated. It was mentioned that the store/work is to be supplied/completed within the delivery period as stipulated in the work order. Otherwise, the liquidated damage for delay as per the details given shall apply. The details so given stipulated that normally the liquidated damage is payable @ 2% of the contract price per month subject to a maximum of 10% of the contract price.
¶3It reveals from the records, more particularly, from the affidavit-in-opposition filed by the respondents that though the contract value was Rs.4,10,000/- and the period of completion of the work was on or before
23.10.2015, but the work could not be completed by the petitioner. There were various extensions given without the liquidated damage and subsequently there was an extension given with liquidated damage. It further reveals that the petitioner had submitted the bill on 09.12.2015 for payment of Rs.4,10,000/-. It reveals that though the petitioner completed the works at Sl. Nos.2, 3, 4, 6, 8 & 9, but the works at Sl. Nos.1, 5 & 7 were not completed. It further reveals that the final bill was finalized by the Installation Officer of the respondents at Rs.1,77,000/- and the said amount was duly paid to the petitioner without any deductions.
¶4It further reveals from the affidavit-in-opposition that the respondent authorities claim to be entitled to Rs.41,000/-on account of liquidated damages in terms with Clause 13 of the Work Order, i.e. Rs.41,000/-. It is also the case of the respondent authorities that no amount was deducted at the time of releasing the amount of Rs.1,77,000/-. Further to that the FDR of Rs.41,000/- so submitted by the petitioner had also expired on
14.03.2017 but presently lying in the custody of the respondents. Page No.# 4/5
¶5I have heard the learned counsels for the parties and perused the materials on record. From the materials on record, it reveals that in the Agreement entered into by and between the petitioners and the respondents dated 24.09.2015, it was stipulated at Clause 2 that 10% of the order value would be retained as security deposit for one year from the date of completion of the work. It was also stipulated that successful tenderers who had deposited a Performance Guarantee equivalent to 10% cost of the total job after getting the LoI, can convert it into security deposit after completion of the work.
¶6The facts further show that the petitioner submitted the Performance Guarantee FDR on 14.02.2015 which was reviewed on 17.09.2015. Now coming to the Agreement dated 24.09.2015, and more particularly to Clause 13, it shows that the maximum liquidated damage that can be imposed is 10% of the contract value, i.e. Rs.41,000/- in the instant case.
¶7It further reveals from Annexure-8 to the affidavit-in-opposition that out of the total value of work, the petitioner completed work to the tune of Rs.1,77,000/- and work of the value of Rs.2,33.000/- was not done and as such Rs.1,77,000/- was released that too without any deduction made of 10% from the bill.
¶8Under such circumstances, the question arises as to whether the petitioner would be entitled to the return of the Performance FDR of the value of Rs.45,665.74p as could be seen from Annexure-7 of the affidavit-in-opposition. In the opinion of this Court, this aspect needs to be best left to the respondent authorities to take a call as to whether the respondent authorities would invoke Clause 13 of the Agreement for the purpose of liquidated damages in as much as the materials on record do not show Page No.# 5/5 that such action have been resorted too.
¶9Accordingly, this Court disposes of the writ petition granting liberty to the petitioner to submit a representation along with this order seeking return of the FDR of the value of Rs.45,665.74p lying with the respondents. The respondents, upon receipt of the representation, shall take a call as regards the imposition of liquidated damages if deemed fit, which under no circumstances can be more than Rs.41,000/- and do the needful. It is observed that keeping the FDR with the respondents would not serve the purpose of both the petitioner as well as the respondents as the amount lying in FDR is only stagnating. This Court further directs that the entire exercise be completed within 45 days from the date of submission of the representation along with the certified copy of this order.
JUDGE Comparing Assistant
Case details
Parties and counsel
PageoNo.#o1/5 GAHC010027052020 ooooooo ooooooooooooooo ooooooooooooooooTHEoGAUHATIoHIGHoCOURTo (HIGHoCOURToOFoASSAM,oNAGALAND,oMIZORAMoANDoARUNACHALoPRADESH)o oooooooooooooooooooooooooooooooooooooooooCaseo:oWP(C)/1156/2020 M/S.oPROTIVAoENTERPRISE AoPROPRIETORSHIPoFIRM oREP.oBY oSRIoSIDDHARTHAoCHAKRABORTY oAGEDoABOUTo47oYEARS oS/O-oLT.oBYOMKESHoCHAKRABORTY oRESIDENToOFo9/6oVIJOYGARH oJADAVPUR oKOLKATA o700032 oWESToBENGAL. oVERSUS UNIONoOFoINDIAoANDo3oORS. REP.oBYoTHEoSECY. oDEPTT.oOFoINFORMATIONoANDoBROADCASTING oGOVT.oOFoINDIA oSHASTRIoBHAWAN o039AoANDo039oWING oNEWoDELHI-o110001. 2:CHIEFoEXECUTIVEoOFFICER PRASARoBHARATIoBROADCASTINGoCORPORATIONoOFoINDIA oPARLIAMENToSTREET oNEWoDELHIo110001. o3:DIRECTORoGENERAL ALLoINDIAoRADIO oSANSADoMARG oNEWoDELHI o110001. o4:ADDL.oDIRECTORoGENERALo(NEZ) ALLoINDIAoRADIO Page No.# 2/5 DOORDARSHAN KENDRA COMPLEX R.G. BARUAH ROAD GUWAHATI- 781024 KAMRUP(METRO) ASSAM. For the petitioner (s) : Mr. S. S. Barooah, Advocate For the respondent (s) : Mr. K. K. Parasar, Advocate BEFORE HON'BLE MR. JUSTICE DEVASHIS BARUAH
Source: High Court of Gauhati, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.