O R D E R

31.08.2023

The instant writ petition has been filed seeking a writ in the nature of mandamus directing the respondents to release the security deposit in relation to the contract work with interest.

¶2The facts involved in the instant writ petition as could be seen from a perusal of the pleadings are that a work order dated 19.02.2015 was issued in favour of the petitioner for supply, fabrication, fixing and installation of 120 ohm 16 wire feeder line works at 100 kw MW DRM Transmitter at All India Radio, Pasighat. From a perusal of the said work order dated 19.02.2015, it reveals that there are various terms and conditions mentioned therein. It further reveals that value of the work order was mentioned as Rs.15,72,687/-. The period of completion of the work was 90 days from the date of issuance of the work order or LoI whichever is earlier. As per Clause 9 of the terms and conditions stipulated in the work order, 10% of the work value would be retained as security deposit for the warranty period from the date of completion of the work. In terms with Clause 13 of the work order, the liquidated damage for late delivery was stipulated. It was mentioned that the store/work is to be Page No.# 3/4 supplied/completed within the delivery period as stipulated in the work order. Otherwise, the liquidated damage for delay as per the details given shall apply. The details so given stipulated that normally the liquidated damage is payable @ 2% of the contract price per month subject to a maximum of 10% of the contract price.

¶3It reveals from the records, more particularly, from the affidavit-in-opposition filed by the respondents that though the contract value was Rs.15,72,690/- and the period of completion of the work was 20.05.2015, but the work could not be completed by the petitioner. There were various extensions given without the liquidated damage and subsequently there was an extension given with liquidated damage.

¶4It further reveals that the petitioner had submitted the bill on

29.03.2016 for payment of Rs.10,83,669/- and the said amount was paid after making deduction of 10% of the bill amount. It further reveals that the final bill was finalized by the Installation Officer of the respondents at Rs.13,18,783/- and by deducting the earlier part payment of Rs.10,83,669/-, the differential amount was Rs.2,35,114/-. Upon deduction of another 10% from the said amount, the petitioner was paid an amount of Rs.2,11,603/-. Therefore, 10% of the final bill of Rs.13,18,783/-, i.e. Rs.1,31,878/- was retained by the authority due to non-completion of the work by the petitioner.

¶5It is relevant further to take note of that the imposition of 10% as liquidated damage on the value of the work done by the petitioner has not been put to challenge. Therefore, the deduction and retainment of the amount of Rs.1,31,878/- by the respondent authorities cannot be called in question. Page No.# 4/4

¶6Be that as it may, the petitioner at the time of submission of the bill submitted an FDR of an amount of Rs.1,57,269/- which was 10% of the value of the contractual work. However, while the disputes were going on as to whether the security deposit should be paid to the petitioner or not, the said FDR was encashed by the petitioner.

¶7Under such circumstances, it is the opinion of this Court that the question of issuance of a direction in the instant proceedings for payment of security deposit of Rs.1,31,878/- to the petitioner does not arise as the same forms the liquidated damage which the respondents have levied upon the petitioner for non-completion of the work in terms with Clause

13.

¶8In that view of the matter, the writ which have been sought for in the instant writ petition cannot be issued, and accordingly, the instant writ petition stands dismissed.

JUDGE Comparing Assistant

Case details

Parties and counsel

PageoNo.#o1/4 GAHC010027052020 ooooooo ooooooooooooooo ooooooooooooooooTHEoGAUHATIoHIGHoCOURTo (HIGHoCOURToOFoASSAM,oNAGALAND,oMIZORAMoANDoARUNACHALoPRADESH)o CaseoNo.o:oWP(C)/816/2020o M/S.oPROTIVAoENTERPRISEo AoPROPRIETORSHIPoFIRM,oREP.oBYoSRIoSIDDHARTHAoCHAKRABORTY,oS/O. LT.oBYOMKESHoCHAKRABORTY,oR/O.o9/6oVIJOYGARH,oJADAVPUR,o KOLKATA,o700032,oWESToBENGAL. VERSUSo UNIONoOFoINDIAoANDo3oORS.o REP.oBYoTHEoSECRETARY,oDEPTT.oOFoINFORMATIONoANDo BROADCASTING,oGOVT.oOFoINDIA,oSHASTRIoBHAWAN,o039AoANDo039o WING,oNEWoDELHI-110001. 2:CHIEFoEXECUTIVEoOFFICER oPRASARoBHARATIoBROADCASTINGoCORPORATIONoOFoINDIA oPARLIAMENToSTREET oNEWoDELHI-110001. 3:DIRECTORoGENERAL oALLoINDIAoRADIO oSANSADoMARG oNEWoDELHI o110001. 4:ADDL.oDIRECTORoGENERALo(NEZ) oALLoINDIAoRADIO oDOORDARSHANoKENDRAoCOMPLEX oR.oG.oBARUAHoROAD oGUWAHATI-781024 oKAMRUPo(M) oASSAMo Page No.# 2/4 For the petitioner (s) : Mr. S. S. Barooah, Advocate For the respondent (s) : Mr. K. K. Parasar, Advocate BEFORE HON'BLE MR. JUSTICE DEVASHIS BARUAH

Source: High Court of Gauhati, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.