- Court
- High Court of Gauhati
- Decided
- 26 March 2024
- Bench
- Michael Zothankhuma
- Case no.
- WP(C) 1699/2024
Judgment
ORDER Date : 27.03.2024
Mr. A. D. Choudhury, learned counsel for the petitioner submits that he may be allowed to withdraw this writ petition, with liberty to avail of Clause 24 & 25 of the Contract Agreement for constitution of a Dispute Review Board, to settle the dispute between the parties.
¶2Mr. B. Gogoi, learned counsel for the PWD submits that he has got no objection to the prayer of the petitioner.
¶3The petitioner's case is that despite the petitioner having been awarded a contract, which was to be completed within two years, the same has been terminated prior to expiry of two years. The petitioner claims Rs. 43,66,676/- for the work done by the petitioner.
¶4On the other hand, as per the statement of final account (revised) made by the Executive Engineer, PWD, Hailakandi District Territorial Building Division, the debt payable by the petitioner to the employer (respondents) amounts to Rs. 28,88,684/-.
¶5In view of the above disputed questions of facts, the prayer of the petitioner's counsel is allowed.
¶6The writ petition is dismissed as withdrawn, with liberty being given to the petitioner to avail of Clause 24 & 25 of the Contract Agreement, which states as follows:- "24. Disputes
24.1. If the Contractor believes that a decision taken by the Page No.# 3/4 Engineer was either outside the authority given to the Engineer by the Contract or that the decision was wrongly taken, the decision shall be referred to the Dispute Review Board within 14 days of the notification of the Engineer's decision.
¶25Procedure for Disputes
25.1. The Dispute Review Board shall be constituted with three members, one from Employer, One from Contractor and the other to be nominated jointly by the above two members to give a decision in writing within 28 days of receipt of a notification of a dispute.
25.2. The Dispute Review Board shall be paid daily at the rate specified in the Contract Data together with reimbursable expenses of types specified in the Contract Data and the cost shall be divided equally between the Chief Engineer, PWD(Building), Chandmari, Guwahati-3,Assam, and the Contractor, whatever decision is reached by the Dispute Review Board. Either party may give notice to the other to refer a decision of the Dispute Review Board to an Arbitrator within 28 days of the Dispute Review Board's written decision. If neither party refers the dispute to arbitration within the next 28 days, the Dispute Review Board's decision will be final and binding.
25.3. The arbitration shall be conducted in accordance with the arbitration procedure stated in the Special Conditions of Contract
(SCC)."
¶7The delay on the part of the petitioner in availing Clause 24 & 25 of the Contract Agreement should be condoned by the concerned authorities, provided Page No.# 4/4 the petitioner's representation on the same is submitted to the respondent authorities, within a week from today.
JUDGE Comparing Assistant
Case details
Parties and counsel
PageoNo.#o1/4 GAHC010059992024 ooooooo ooooooooooooooo ooooooooooooooooTHEoGAUHATIoHIGHoCOURTo (HIGHoCOURToOFoASSAM,oNAGALAND,oMIZORAMoANDoARUNACHALoPRADESH)o CaseoNo.o:oWP(C)/1699/2024o MRIGENoSUTRADHARo S/O-oLATEoPRAFULLAoKUMARoSUTRADHAR,o R/O-oDISPUR,oSUPERoMARKET,oGUWAHATI,o P.O-oDISPUR,oPIN-781006,o DIST-oKAMRUPo(M),oASSAM VERSUSo THEoSTATEoOFoASSAMoANDo3oORSo REP.oBYoTHEoCOMMISSIONERoANDoSECRETARY,oTOoTHEoGOVERNMENTo OFoASSAM,oPWDo(ROADS)oDEPARTMENTo,o oDISPUR,oGUWAHATIo-6 2:THEoCHIEFoENGINEER oPWDo(ROADS) o oASSAMoCHANDMARIoGUWAHATIo781003oASSAM 3:THEoSUPERINTENDINGoENGINEER oPWDoSILCHARoBUILDINGoCIRCLEo oSILCHARo oASSAM 4:THEoEXECUTIVEoENGINEERoPWD oHAILAKANDIoDISTRICToTERRITORIALoBUILDINGoDIVISION oHAILAKANDI o-78815o AdvocateoforotheoPetitionerooooo:oMR.oAoDoCHOUDHURYo AdvocateoforotheoRespondento:oSC,oPoWoDoo oooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooo Page No.# 2/4 BEFORE HONOURABLE MR. JUSTICE MICHAEL ZOTHANKHUMA