ORDER Date : 02.08.2023

¶1The instant writ petition is filed by the Petitioner challenging the inaction on the part of the Respondent Authorities in releasing the dues to which the Petitioner is entitled to upon completion of the work allotted to him by the Superintendent Engineer, PWD, Guwahati.

¶2The case of the petitioner herein is that the Petitioner was allotted the work for construction and repairing of sub-centre building namely Dhuparguri Sub-Centre and Kaibartapara Sub-Centre in Kamrup District (R) under Annual Plan (SCCP) for the year 2008-2009 through tender process. The total value of the tender was Rs.13,03,854/-. After the completion of the work, the Petitioner has submitted the completion report to the Respondent authorities. Out of Rs. Page No.# 3/4 13,03,854/-, the Petitioner received a total amount of Rs.8,13,124/- in two different installments. The first installment of Rs.3,25,000/- was received against the ceiling allotment dated 31.03.2011 and the second installment of Rs.4,88,124/- was received against the ceiling allotment dated 16.03.2013 and an amount of Rs.4,90,730/- still remains pending to be paid by the Respondent Authorities.

¶3It has been alleged that the Respondent Authorities have been denying the payment of outstanding balance amount of Rs.4,90,730/- due to non-completion of electrical work by some other contractor in Ganeshtola sub-centre.

¶4Mr. D. Upamanyu, the learned counsel appearing on behalf of the Respondents submits that there is no denial to the fact that the work in question was allotted to the Petitioner. The learned counsel for the Respondents however submits that the entitlement of the Petitioner would be dependent upon further verification to be carried out by the Respondent Authorities.

¶5Upon perusal of the materials on record, this Court is of the opinion that if the Petitioner had completed the work in question, the Petitioner would be entitled to the amount as claimed. However, for the same, verification on the part of the Respondent Authorities would be required.

¶6This Court, therefore, disposes of the instant writ petition with a direction to the Respondent Authorities to verify as to whether the Petitioner had completed the work in question as per the allotment of the work and also as to whether the Petitioner had submitted requisite documents which are required for the purpose of releasing the amount claimed by the Petitioner.

¶7This Court further directs that upon verification, if it is found that the Page No.# 4/4 Petitioner is entitled to, the Respondent Authorities shall pay to the Petitioner the entitlement to the extent of the work done by the Petitioner.

¶8The said exercise be completed with a period of 6 (six) months from the date a certified copy of the instant order is served upon Respondent No.2.

JUDGE Comparing Assistant

Case details

Parties and counsel

PageoNo.#o1/4 GAHC010083842018 ooooooo ooooooooooooooo ooooooooooooooooTHEoGAUHATIoHIGHoCOURTo (HIGHoCOURToOFoASSAM,oNAGALAND,oMIZORAMoANDoARUNACHALoPRADESH)o CaseoNo.o:oWP(C)/2646/2018o SHAHoSULTANoGIASUDDINoAHMEDo C/O-oLATEoAMIRoALI,oVILL-oLARMAoGAURHATI,oP.O-oDHUBRI,oP.S-oKAYAN,o DIST-oKAMRUP(R),oASSAM,oPIN-o781350 VERSUSo THEoSTATEoOFoASSAMoANDo7oORS.o REP.oBYoTHEoCOMMISSIONERoANDoSECRETARYoTOoTHEoGOVToOFoASSAM,o PWDoDEPTT,oDISPUR,oGUWAHATI-o6 2:THEoHEALTHoANDoFAMILYoWELFARE(A)oDEPTT oREP.oBYoCOMMISSIONERoANDoSECRETARYoTOoTHEoGOVToOFoASSAM oDISPUR oGUWAHATI-o6 3:THEoFINANCEoDEPTT oREP.oBYoCOMMISSIONERoANDoSECRETARYoTOoTHEoGOVToOFoASSAM oDISPUR oGUWAHATI-o6 4:THEoCHIEFoENGINEER oPWDoBUILDING oASSAM oCHANDMARI oGUWAHATI-3 5:SUPERINTENDENToENGINEER oPWD oGUWAHATIoBUILDINGoCIRCLE-II oCHANDMARI oGUWAHATI-3 Page No.# 2/4 6:THE DEPUTY COMMISSIONER KAMRUP GUWAHATI 7:EXECUTIVE ENGINEER PWD GUWAHATI BUILDING DIVISION-II DISPUR GUWAHATI-6 8:THE SUB DIVISIONAL MEDICAL AND HEALTH OFFICER HAJO DIST- KAMRU For the Petitioner(s) : Mr. A. Islam, Advocate For the Respondent(s) : Mr. D. Upamanyu, Advocate for Health Department : Ms. S. Chutia, Advocate for Finance Department BEFORE HONOURABLE MR. JUSTICE DEVASHIS BARUAH

Source: High Court of Gauhati, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.