ORDER

03.06.2024

¶1Heard Mrs. D. Jain, learned counsel for the petitioner. Also heard Ms. A. Gayan, learned CGC appearing for the respondent No.1 and Ms. A. Lodha, learned counsel for the respondent Nos. 2-7.

¶2The petitioner's case is that the petitioner is a registered contractor with the Water Resources Department, Morigaon. The petitioner was given work contracts under the Scheme of "R/S to T/dyke Along Both Banks of Kopilli River From Charaihagi to Tuklaitup (L/B), Basundhari to Killing Kopilli Junction (L/B) and Chaparmukh Ahatguri Amsoi P.W.D. Road (R/B) Including Ante-Erosion Measures at Different Reaches." Page No.# 3/4

¶3Though the petitioner had completed the work contracts and was paid a certain sum of money, the balance amount of Rs.2,28,287/- has not been paid to the petitioner.

¶4The petitioner's counsel submits that the Executive Engineer, Morigaon WR Division, vide letter No. MGWRD/W-205/PT.VI/2022/344 dated 27.01.2023, has furnished the liability statement issuing the outstanding amount liability towards the petitioner, i.e., Rs.2,28,287/-. The petitioner's counsel submits that that the present case is covered by the order dated 27.09.2022 passed by this Court in WP(C) No. 4734/2021 (Nazim Hussain Vs. The State of Assam and 8 Ors.). She accordingly submits that a similar direction, as given in the above case, be issued in this case.

¶5Ms. A. Gayan, learned CGC appearing for the respondent No.1 and Ms. A. Lodha, learned counsel for the respondent Nos. 2-7 submit that they have got no objection to the prayer made by the petitioner's counsel.

¶6I have heard the learned counsels for the parties.

¶7This Court, in a series of cases, leading case being WP(C) 4734/2021 (Nazim Hussain -vs-The State of Assam and 8 others), while disposing of the similar matters, had passed the following direction, which are as follows:- "(1) Within 15 (fifteen) days from today, the concerned official of the State Government of Assam will communicate the supplementary budget passed in the last Assembly Session pertaining to the scheme to the competent authority of the Ministry of Jal Shakti, Government of India.

(2) Within 60 (sixty) days from the date of receipt of such communication, the Ministry of Jal Shakti to release the amount due under the schemes to Page No.# 4/4 the concerned Department of the Government of Assam.

(3) Upon receipt of the amount, bills of the writ petitioners shall be processed and cleared within a further period of 45 days"

¶8In view of the consent of the parties and in view of the liability statement attached to the letter No. MGWRD/W-205/PT.VI/2022/344 dated 27.01.2023, issued by the Executive Engineer, Morigaon W.R. Division, this Court is of the view that this writ petition can be disposed of at the motion stage itself.

¶9In view of there being an admission made by the respondent No. 5, the respondent No. 3 is directed to re-verify and thereafter take a decision with regard to whether the amount claimed by the petitioner is as per records. In the event, the respondent No. 3 comes to a decision that the amount claimed is an admitted amount, the direction passed in WP(C)4734/2021, which has been enumerated above, shall be complied with. The respondents shall thereafter complete the entire process, within a period of 5 (five) months from the date of receipt of a copy of this order.

¶10This writ petition is accordingly disposed of

JUDGE

Comparing Assistant

Case details

Parties and counsel

PageoNo.#o1/4 GAHC010109372024 ooooooo ooooooooooooooo ooooooooooooooooTHEoGAUHATIoHIGHoCOURTo (HIGHoCOURToOFoASSAM,oNAGALAND,oMIZORAMoANDoARUNACHALoPRADESH)o CaseoNo.o:oWP(C)/2871/2024o HANNANoUDDINoAHMEDo S/O-oIMANoUDDINoAHMED,o R/O-oBARKANDAJoPATH,oFAUJDARIPATTY,o DIST-oNAGAON,oASSAM,oPIN-782001 VERSUSo THEoUNIONoOFoINDIAoANDo6oORSo REPRESENTEDoBYoTHEoMINISTRYoOFoJALoSHAKTIo,o DEPARTMENToOFoWATERoRESOURCEoANDoRIVERoDEVELOPMENToANDo GANGAoREJUVENATION,o NEWoDELHI-110001 2:THEoSTATEoOFoASSAM oREP.oBYoTHEoSECRETARY.oTOoTHEoGOVT.oOFoASSAM oWATERoRESOURCEoDEPTT. oDISPUR oGHY-06 3:THEoCHIEFoENGINEER oWATERoRESOURCEoDEPTT. oGOVT.oOFoASSAM oBASISTHA oGUWAHATI-29 4:THEoSUPERINTENDINGoENGINEER oWATERoRESOURCEoDEPARTMENT o oNAGAONoWATERoRESOURCEoCIRCLE oNAGAON oASSAM. Page No.# 2/4 5:THE EXECUTIVE ENGINEER NAGAON WATER RESOURCE DIVISION NAGAON ASSAM. 6:THE EXECUTIVE ENGINEER MORIGAON WATER RESOURCE DIVISION MORIGAON ASSAM. 7:THE ASSISTANT EXECUTIVE ENGINEER JAGIROAD WATER RESOURCE SUB-DIVISION JAGIROAD ASSAM Advocate for the Petitioner : MR. C SHARMA Advocate for the Respondent : DY.S.G.I. BEFORE HONOURABLE MR. JUSTICE MICHAEL ZOTHANKHUMA

Source: High Court of Gauhati, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.