- Court
- High Court of Gauhati
- Decided
- 6 August 2024
- Bench
- Michael Zothankhuma
- Case no.
- WP(C) 3274/2024
Judgment
ORDER Date : 07.08.2024
Heard Mr. R. Mazumdar, learned counsel for the petitioner. Also heard Mr. B. Choudhury, learned counsel for the APDCL.
¶2The petitioner's grievance is with regard to the APDCL not having processed the petitioner's application for being given an additional electricity load to run his Stone Crusher Unit, namely, M/s Bholanath Stone Crusher Unit.
¶3The petitioner's counsel submits that the petitioner has submitted all the required documents to the APDCL. However, the respondents APDCL have not taken a final decision till date.
¶4Mr. B. Choudhury, learned counsel for the APDCL submits that the APDCL Page No.# 3/3 has received all the required documents from the petitioner and the process for giving an additional electricity load to the petitioner, for running Stone Crusher Unit, will be completed within six weeks. He however submits that the completion of the formalities would require the petitioner to pay some extra charges, as per the guidelines and Rules of the APDCL.
¶5Mr. R. Mazumdar, learned counsel for the petitioner submits that all the required fees/charges would be paid by the petitioner whenever the petitioner is informed about the same.
¶6I have heard the learned counsels for the parties.
¶7On considering the submission made by Mr. B. Choudhury, learned counsel for the APDCL that all the formalities for giving an additional electricity load to the petitioner would be completed within a period of six weeks from today, the respondents are directed to complete all the formalities required, within six weeks from today. The above is subject to the condition that the petitioner submits a certified copy of this order to the respondent No. 6 within one week and after making all necessary payment/fees for the additional electricity load to be given.
¶8This writ petition is accordingly disposed of. JUDGE Comparing Assistant
Case details
Parties and counsel
PageoNo.#o1/3 GAHC010127472024 ooooooo ooooooooooooooo ooooooooooooooooTHEoGAUHATIoHIGHoCOURTo (HIGHoCOURToOFoASSAM,oNAGALAND,oMIZORAMoANDoARUNACHALoPRADESH)o CaseoNo.o:oWP(C)/3274/2024o BOLAIoROYo S/O-oLATEoRANENDRAoKUMARoROY,o R/O-oVILLAGE-oSHIBERBOND,o P.O.-oTHALIGRAM,o DISTRICT-oCACHAR,oASSAM.o PROPRIETORoOFo-o M/SoBHOLANATHoSTONEoCRUSHER,o SHIBERBOND,oUDHARBOND,o DISTRICT-oCACHAR,oASSAM. VERSUSo THEoASSAMoPOWERoDISTRIBUTIONoCOMPANYoLIMITEDo(APDCL)oANDo6o ORSo REPRESENTEDoBYoITSoMANAGINGoDIRECTOR,o H.O.-oBIJULIoBHAWAN,o PALTANoBAZAR,oGUWAHATI-o781001. 2:THEoCHIEFoGENERALoMANAGERo(D) oAPDCLoCARoBIJULIoBHAWAN oPALTANoBAZARoGUWAHATI-o781001. 3:THEoGENERALoMANAGER oSOUTHoZONEoAPDCLoSILCHAR-o788005 oDISTRICT-oCACHARoASSAM. 4:THEoASSISTANToGENERALoMANAGER oToANDoCoDIVISIONoAPDCLoSILCHAR-o788005 oDISTRICT-oCACHARoASSAM. 5:THEoCHIEFoEXECUTIVEoOFFICER oCACHARoELECTRICALoCIRCLE oAPDCLoCAR oSILCHAR-o788015. Page No.# 2/3 6:SUB-DIVISIONAL ENGINEER UDHARBOND ELECTRICAL SUB-DIVISION APDCL CAR UDHARBOND DISTRICT- CACHAR ASSAM. 7:THE BLOCK DEVELOPMENT OFFICER UDHARBOND DEVELOPMENT BLOCK UDHARBOND PIN- 788030 DISTRICT- CACHAR ASSAM Advocate for the Petitioner : MR. R MAJUMDAR, MR. JUNM LASKAR,MS. J GHOSH Advocate for the Respondent : SC, APDCL, GA, ASSAM BEFORE HONOURABLE MR. JUSTICE MICHAEL ZOTHANKHUMA
Source: High Court of Gauhati, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.