ORDER

03.06.2024

¶1Mr. S.K. Chakraborty, learned counsel appears for the petitioner, while Mr. B. Gogoi, learned counsel appears for the PWD (Roads) Department.

¶2The petitioner has prayed for payment of his contractual dues amounting to Rs.59,80,540.94 in respect of the work of construction/improvement of Digboi Pengeri Bordungsa Road (1st to 5th K.m.) (Package No.J-6) under NEC's 10th fine year programme, which had commenced in the year 2007. The bill amount of Rs.59,80,540.94 is for payment of the price adjustment bills of the petitioner.

¶3The petitioner's counsel submits that the petitioner completed his contract work after clearance of the road site on 30.06.2012. He submits that the price adjustment bill relates to the price escalation, for the delay in completion of the contract work.

¶4Mr. B. Gogoi, learned counsel for the PWD (Roads) submits that the Page No.# 3/6 petitioner had completed only 49.30% of the contract work and the claim for escalation for work done could not be entertained, as the work was not completed within the stipulated time of completion.

¶5Paragraph nos.4, 5 & 7 of the affidavit-in-opposition of the respondent no.5 states as follows : "4. That with regard to the statement made in paragraph 3 of the writ petition, the deponent states that the work allotted from 1st to 5th Km. the site from 3rd to 5th Km was fee from any encumbrance.. In the 1st & 2nd Km IOCL water lines and AGC gas lines and electric posts were present on the side berms.. The main road was free but the contractor did not carry out the main road work on the pretext of presence of hindrance on the side berms..

¶5That with regard to the statement made in paragraph 4 of the writ petition, the deponent states that the contractor claims that he has completed 3 Km of Road out of 5 Km Road i.e. 60% of total work within December, 2009. But as per progress report of March, 2010 Physical progress of work is 49.30%.

¶7That with regard to the statement made in paragraph 7 of the writ petition, the deponent states that price Adjustment Bill No.1, 2 and 3 is for work done within the stipulated time of completion. Hence claim for escalation for work done within the stipulation time of completion cannot be entertained."

¶6On perusing the averments made by the respondent no.5 in his affidavit, this Writ Court is not equipped to come to any decision, as to whether the petitioner is entitled to any price adjustment, as these are disputed questions of facts. Further, paragraph-4 of the affidavit of the respondent no.5 states that in the 1st & 2nd Km IOCL water lines and AGC gas lines and electric posts were present on the side berms. The main road was free, but the contractor did not carry out the main road work, on the pretext of presence of hindrance on the Page No.# 4/6 side berms. In paragraph-5 it has been stated that physical progress of work was 49.30%, while the petitioner has taken the stand that he has completed the contract work. It is also not disputed that while the stipulated date of completion of contract work was 16.12.2008, the petitioner had completed the work on 06.06.2012 only. Paragraph-7 of the affidavit-in-opposition states that the petitioner's claim for escalation for work done within the stipulated time of completion could not be entertained.

¶7The above averments made by the State respondents, if disputed, would have to be put to challenge before an appropriate forum by recording evidence, which this Court is not equipped to do.

¶8The above being said, letter no.F-14/pt/09/187/278 dated 07.02.2014 issued by the Superintending Engineer, PWRD, Jorhat NEC Circle, Jorhat, which is at Annexure-M of the writ petition is to the following effect :- "To, The Chief Engineer, PWD, Assam, Border Roads and NEC Works, Chandmari, Guwahati-3.

Sub:- Price escalation bill for Package No. J-6 (Ch..0 to 5,000 M.) of Digboi Pangree Road.

Ref:- Executive Engineer's letter No.TSK/SRD/07/W-34/(NEC)/134; dt.29.01.2014. Sir,

I have the honour to submit herewith a price escalation bill received from the Executive Engineer, PWD, Tinsukia State Road Division for the executed Page No.# 5/6 work of Digboi-Pangeree-Bordumsa Road in respect of Package No. J-6 with all enclosures and the letter of the Executive Engineer in original. The work was started on 17/09/2007 and stipulated date of completion was 16/12/2008. But the work was completed on 6/6/2012 with time extension up to 30/06/2012 but without price adjustment. It is observed from the all correspondence made to the contractor and Inspection Report of PWD officials during execution of work, the work was delayed mainly for two reasons –

(I) Insufficient effort of the contractor in respect of machineries and labours.

(II) Non clearance of the road site in 1st. and 2nd. Km. for the existence of the belongings of Assam Gas Company. Duliajan and one private-shop M/s Poddar Store by name. The shop was not removed from the road formation up to 01/07/2010 as per Executive Engineer's letter addressed to 3.D.O. (Civil), Margherita. (Annexure-XXVI) From the above observations it may be concluded that the contractor deserves price. escalation for delay in execution only for the1st. and 2nd. Km, of road length, the remaining 3rd to 5th. Km. was clear of all incumbency. All documents are enclosed herewith for favour of your kind disposal.

¶1Executive Engineer's letter with all enclosures.

¶2Price escalation bill in triplicate. Yours faithfully, Sd/- Superintending Engineer, PWRD, Jorhat NEC Circle, Jorhat

¶9The above letter dated 07.02.2014 shows that the contractor could be given price escalation for delay in execution only for the 1st and 2nd Km of road site. However, the same has been negated by the respondent no.5 in his affidavit dated 07.09.2017. Page No.# 6/6

¶10As there are disputed questions of fact, the petitioner is given the liberty to approach the appropriate forum, including the Civil Court, for redressal of his grievance. However, the respondent nos.3, 4 & 5 may once again look into whether the petitioner deserves price escalation for the 1st and 2nd Km of the road site, in terms of the letter dated 07.02.2014 issued by the Superintending Engineer, PWRD, Jorhat NEC Circle, Jorhat. The exercise to be undertaken by the respondent nos.3, 4 & 5 should be concluded expeditiously and preferably within a period of 4 (four) months from the date of receipt of a certified copy of this order, along with the copy of the writ petition. The decision taken by the respondent nos.3, 4 & 5 should thereafter be communicated to the petitioner.

¶11The writ petition is accordingly disposed of.

JUDGE

Comparing Assistant

Case details

Parties and counsel

PageoNo.#o1/6 GAHC010196712017 ooooooo ooooooooooooooo ooooooooooooooooTHEoGAUHATIoHIGHoCOURTo (HIGHoCOURToOFoASSAM,oNAGALAND,oMIZORAMoANDoARUNACHALoPRADESH)o CaseoNo.o:oWP(C)/3149/2017o M/S.oCLASSICoINDIAo AoPARTNERSHIPoFIRMoREP.oBYoITSoPARTNERoSRIoSUSHILoDAS,oTHERMALo TINIALI,oPO-MAKUMoPATHAR,oMARGHERITA,oDIST.oTINSUKIA,oASSAM VERSUSo THEoSTATEoOFoASSAMoando4oORS.o REP.oBYoCOMMISSIONERoandoSECRETARYoTOoTHEoGOVT.oOFoASSAM,oPWDo ROADSoDEPTT. 2:THEoCHIEFoENGINEER oPWD oROADS oASSAM oCHANDMARI oGUWAHATI-781003 3:THEoCHIEFoENGINEER oPWD oNECoWORKS oCHANDMARI oGUWAHATI-781003 oASSAM 4:THEoSUPERINTENDINGoENGINEER oPWDoROAD oJORHAToNECoCIRCLE oJORHAT oASSAM 5:THEoEXECUTIVEoENGINEER Page No.# 2/6 TINSUKIA STATE ROAD DIVISION TINSUKIA ASSA Advocate for the Petitioner : MR.S K CHAKRABORTY Advocate for the Respondent : GA, ASSAM BEFORE HONOURABLE MR. JUSTICE MICHAEL ZOTHANKHUMA

Source: High Court of Gauhati, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.