¶1Heard Mr. S. Hoque, learned counsel for the petitioner. Also heard Ms. S. Sarma, learned counsel for all the respondents.
¶2The petitioner's case is that the petitioner is a contractor under the PWD
(NH), Government of Assam. The petitioner was allotted construction works pertaining to Flood Damage Repairing and Ordinary Repairing of the NH-31 and NH-31(B) by the respondent no.4 in the year 2010. After completion of the contract work, the petitioner submitted his bills amounting to Rs.18,28,127/-. However, the respondent authorities have not made any payment to the petitioner, despite making payments to other contractors for works made subsequently by them. Mr. S. Haque accordingly submits that a direction may be issued to the respondents to verify the claim of the petitioner and to make payment of the admitted amount.
¶3Ms. S. Sarma, learned counsel for all the respondents submits that as she has not received any parawise comments, a direction may be passed by this Court to verify the amount claimed by the petitioner and thereafter payment will be made with regard to the admitted amount.
¶4I have heard the learned counsels for the parties. Page No.# 3/4
¶5Paragraph-2 of the writ petition shows the various Work Orders allegedly issued to the petitioner by the respondent no.4, which are as follows : "i. Work Order No. TB/FDR/2006-07/372 dated 04-06-2010 of amount of Rs.4,18,179/- ii. Work Order No. TB/FDR/2006-07/373 dated 04-06-2010 of amount of Rs.4,18,179/- iii. Work Order No. TB/FDR/2006-07/527 dated 17-06-2010 of amount of Rs.3,96,455/- iv. Work Order No. TB/FDR/2006-07/526 dated 17-06-2010 of amount of Rs.2,66,114/- v. Work Order No. TB/FDR/2006-07/667 dated 12-07-2010 of amount of Rs.2,16,804/- vi. Work Order No. TB/FDR/2006-07/704 dated 14-07-2010 of amount of Rs.1,12,346/-"
¶6Annexure-B1 to Annexure-B6 are the alleged Completion Certificates issued by the respondent no.4.
¶7The writ petition claiming payment of the contractual dues has been filed on 18.07.2016. Despite a lapse of more than 8 years, the respondent authorities have not submitted any affidavit till date and neither have they given any instructions to their counsel, with regard to the claim of the petitioner.
¶8In view of the above facts and keeping in view the judgment of the Full Bench of this Court in the case of Tamsher Ali vs. State of Assam & Others, reported in 2008 (4) GLT 1, this Court is not inclined to keep the matter Page No.# 4/4 pending any longer.
¶9In view of the reasons stated above, the respondent no.2 is directed to verify the claim of the petitioner with regard to the work orders issued and whether the petitioner had completed the same. Further, he shall also verify as to whether the amount claimed by the petitioner has been paid to the petitioner or not. If the claim of the petitioner has not been paid in full, the respondent no.2 shall clarify the admitted amount payable to the petitioner. Thereafter the respondents shall ensure that funds are made available for payment of the admitted amount to the petitioner. The entire process should be completed within a period of 3 (three) months from the date of receipt of this order.
¶10The writ petition is accordingly disposed of.
JUDGE Comparing Assistant
Case details
Parties and counsel
Page No.# 1/4 GAHC010205752016 THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) Case No. : WP(C)/4341/2016 SANOWAR HUSSAIN S/O- AHMED HUSSAIN, BARPETA ROAD, P.O.- BARPETA ROAD, DIST.- BARPETA, ASSAM. VERSUS THE STATE OF ASSAM and 3 ORS. REP. BY THE COMMISSIONER AND SECY. TO THE GOVT. OF ASSAM, PUBLIC WORKS DEPTT. BUILDIG and N.H., DISPUR, GHY- 6. 2:THE CHIEF ENGINEER PWD NH. WORKS CHANDMARI GHY- 3. 3:THE SUPERINTENDING ENGINEER PWD NH NORTHERN ASSAM CIRCLE CHANDMARI GHY- 3. 4:THE EXECUTIVE ENGINEER PWD N.H. ABHAYAPURI CONSTRUCTION DIVISION ABHAYAPURI DIST.- BONGAIGAON ASSAM- 783384 Advocate for the Petitioner : MR.S HOQUE, MR.M DEKA Advocate for the Respondent : MRS.V L SINGH, MR. D GOGOI & MR. R. DHAR, SC, PWD (NH) Page No.# 2/4 BEFORE HONOURABLE MR. JUSTICE MICHAEL ZOTHANKHUMA
Source: High Court of Gauhati, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.