M/S Mayur Stone Crusher v. The State of Assam and 3 Ors

Disposed Of
Court
High Court of Gauhati
Decided
6 August 2024
Bench
Devashis Baruahauthor
Case no.
WP(C) 7717/2022

Judgment

ORDER Date : 07.08.2024

Heard Mr. S. Chamaria, the learned counsel appearing on behalf of the Petitioner and Mr. K. P. Pathak, the learned Standing counsel appearing on behalf of the Respondent Nos. 1, 3 and 4. I have also heard Ms. M. Barman, the learned Junior Government Advocate appearing on behalf of the Respondent No.2.

¶2The Petitioner herein is aggrieved by the order dated 30.04.2019 passed by the Divisional Forest Officer whereby the Petitioner's Stone Crusher Unit along with other Stone Crusher Units have been restrained from carrying out their activities in view of an order dated 12.04.2019 passed by the Supreme Court in the case of IN RE T. N. Godavarman Thirumulpad Vs. Union of India and more particularly in respect to the order in IA No.42944/2019.

¶3The learned counsel for the Petitioner submitted that the directions so issued had no relevance with carrying out of operation of the Stone Crusher Unit of the Petitioner. The Supreme Court as per the learned counsel had only directed that all kind of mining and related activities along with the Kaziranga National Park area and in the entire catchment area of rivers/streams and Page No.# 3/4 rivulets originating in Karbi Anglong Hill ranges and flowing in Kaziranga National Park including tiger reserve were restrained. The learned counsel for the Petitioner further submitted that the activity of stone crushing so carried out in the establishments of the Petitioner would not come within the meaning of mining as well as related activities and as such the impugned order dated

30.04.2019 requires to be interfered with by this Court.

¶4On the other hand, Mr. K. P. Pathak, the learned Standing counsel for the Respondent Nos. 1, 3 and 4 submitted that the order dated 30.04.2019 was passed in view of the order dated 12.04.2019 passed by the Supreme Court wherein all mining and related activities have been restrained along with the Kaziranga National Park area. He further submitted that the Stone Crusher Unit is a polluting industry and if the Petitioner's Stone Crusher Unit is permitted, it would cause pollution and it is under such circumstances, the order dated

30.04.2019 ought not to be interfered with. He further submitted that the Forest Department of the Government of Assam have issued the communication dated

30.04.2019 on the basis of an understanding that the activity of Stone Crushing would come within the ambit of related activities as mentioned in the order of the Supreme Court dated 12.04.2019 and therefore submitted that if the petitioner is aggrieved by the order dated 30.04.2019 which have been impugned in the instant proceedings, the Petitioner can very well seek a clarification from the Supreme Court taking into account that the said proceedings are still pending.

¶5This Court upon hearing the learned counsels for the parties is of the opinion that the words used in the order of the Supreme Court dated

12.04.2019 mentions about "mining" and "related activities". It is also seen that the said proceedings are presently pending before the Supreme Court and in the Page No.# 4/4 opinion of this Court, it would not be proper for giving an interpretation to a term used in the order that too when the said proceedings are presently pending before the Supreme Court.

¶6Under such circumstances, this Court while not interfering with the order dated 30.04.2019 as has been assailed in the instant proceedings observed that the Petitioner would always be at liberty to approach the Supreme Court to seek clarification as to whether the Stone Crusher Unit would come within the ambit of the word "related activities" as mentioned in the order dated 12.04.2019.

¶7Taking into account the order which has been passed hereinabove, Mr. S. Chamaria, the learned counsel submitted that the Petitioner may be permitted to take out the already finished products which are lying in the Stone Crusher Unit of the Petitioner.

¶8Mr. K. P. Pathak, the learned counsel appearing on behalf of the Forest Department submitted that for removing those materials, due permissions have to be taken from the Forest Department. Under such circumstances, this Court grants the liberty to the Petitioner to approach the concerned Divisional Forest Officer for due permission for removing the finished products. It is observed that in the circumstances, the Petitioner approaches the concerned Divisional Forest Officer, the said Authority shall do the needful in that regard by following the extant laws.

¶9With above observations and directions, the instant petition stands disposed of.

JUDGE Comparing Assistant

Case details

Parties and counsel

PageoNo.#o1/4 GAHC010243922022 ooooooo ooooooooooooooo ooooooooooooooooTHEoGAUHATIoHIGHoCOURTo (HIGHoCOURToOFoASSAM,oNAGALAND,oMIZORAMoANDoARUNACHALoPRADESH)o CaseoNo.o:oWP(C)/7717/2022o M/SoMAYURoSTONEoCRUSHERo REPRESENTEDoHEREINoBYoOWNERoNAMELYoBINODoKUMARoMORE,oAGED ABOUTo65oYEARS,oS/OoLATEoHIRAoLALoMORE,oADD-oBORBHETA,oBORJURI,o BOKAKHAT,oDIST-oGOLAGHAT,oASSAM,oPIN-785612 VERSUSo THEoSTATEoOFoASSAMoANDo3oORSo (ENVIRONMENToANDoFORESToDEPARTMENT,oGOVT.oOFoASSAM),o REPRESENTEDoHEREINoBYoTHEoADDL.oCHIEFoSECRETARYoTOoTHEoGOVTo OFoASSAM,oDISPUR,oSACHIBALAYA,oDISPUR,oGUWAHATI-06,oASSAM 2:THEoSUB-DIVISIONALoOFFICERo(CIVIL) oBOKAKHAT oOFFICEoOFoTHEoSUB-DIVISIONALoOFFICERo(CIVIL) oGOVT.oOFoASSAM oBOKAKHAT oDIST-GOLAGHAT oASSAM oPIN-785612 3:THEoDIRECTOR oKAZIRANGAoNATIONALoPARK oBOKAKHAT oDIST-oGOLAGHAT oASSAM oPIN-785612 4:THEoDIVISIONALoFORESToOFFICER oEASTERNoASSAMoWILDLIFEoDIVISION oDEPARTMENToOFoFOREST oBOKAKHAT Page No.# 2/4 DIST- GOLAGHAT ASSAM PIN-78561 For the Petitioner(s) : Mr. S. Chamaria, Advocate For the Respondent(s) : Mr. K. P. Pathak, Standing Counsel BEFORE HONOURABLE MR. JUSTICE DEVASHIS BARUAH

Source: High Court of Gauhati, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.