VoxJuris
Home › High Courts › Madras High Court 2026 › High Court of Madras

A. Radhakrishanan v. The Secretary to Government

DISPOSED OF
Court
High Court of Madras
Decided
17 February 2026
Bench
D.Bharatha Chakravarthyauthor
Case no.
WP 6524/2026

Judgment

ORDER This writ petition is filed for a Mandamus directing the respondents to take adequate and appropriate safety and regulatory measures in connection with the construction and Kumbabishekam, which is scheduled to be held on

22.02.2026 in the 9th respondent temple, by considering the petitioner's representations.

2.Upon perusing the petitioner's representation, it can be seen that the petitioner has flagged issues, such as, non-completion of construction and not taking enough safety measures and non-regulation of shops in and around the temple.

¶3In reply thereto, the learned counsel appearing on behalf of the respondents would submit that as far as the construction is concerned, the same is complete with reference to the sannadhi and all the sanctums. As per the traditions, that is followed in the said temple, some works have to be kept pending and are to be completed only after the kudamuzhukku. Therefore, the outer prakaram laying etc. are kept pending and it will be completed after the kudamuzhukku. All arrangements including safety and cleaning are going on and the kudamuzhukku will be conducted by duly following the procedure and all the arrangements for the safety of the devotees will be made.

¶4The said undertaking is recorded. It is made clear that after the kudamuzhukku is over, the work should not be left in lurch. The pending outer praharam work should be completed with due quality. The Heritage Committee shall constitute a sub-committee to inspect the temple two months after the kudamuzhukku ensuring by duly auditing as to whether the amount spent has been properly utilized and whether all the constructions have been properly made and submit a report before the Commissioner (HR and CE). The Commissioner (HR and CE) shall ensure the completion of all the works as originally planned. A copy of the said report shall also be furnished to the petitioner.

¶5Accordingly, this Writ Petition is disposed of. No costs. 17-02-2026 ari To

1.The Secretary to Government, Tourism Culture and Endowments Department, Secretariat, Chennai 600 009.

2.The Commissioner, 119, Nungambakkam High Road, Chennai 600 034.

3.The Chief Engineer, 119, Nungambakkam High Road, Chennai 600 034.

4.The Chief Sthapathi, 119, Nungambakkam High Road, Chennai 600 034.

5.The District Executive Magistrate/District Collector, Salem Town 636 001.

6.The Commissioner of Police, Line Medu, Salem 636 006.

7.The Joint Commissioner, Nethimedu, Salem 636 002.

8.The Fit Person/Chairman Board of Trustee/Administrator, Arulmigu Mariamman Temple, Shevapettai, Selam 636 002.

9.The Executive Officer, Arulmigu Mariamman Temple, Shevapettai, Salem 636 002.

D.BHARATHA CHAKRAVARTHY, J. ari

17-02-2026

Case details

Parties and counsel

IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 17-02-2026 CORAM THE HONOURABLE MR.JUSTICE D.BHARATHA CHAKRAVARTHY Writ Petition No.6524 of 2026 A.Radhakrishnan, S/o T.Arumuga Gounder, 38, Mettur Agraharam, Salem 636 001. .. Petitioner /versus/ 1.The Secretary to Government, Tourism Culture and Endowments Department, Secretariat, Chennai 600 009. 2.The Commissioner, 119, Nungambakkam High Road, Chennai 600 034. 3.The Chief Engineer, 119, Nungambakkam High Road, Chennai 600 034. 4.The Chief Sthapathi, 119, Nungambakkam High Road, Chennai 600 034. 5.The District Executive Magistrate/District Collector, Salem Town 636 001. 6.The Commissioner of Police, Line Medu, Salem 636 006. 7.The Joint Commissioner, Nethimedu, Salem 636 002. 8.The Fit Person/Chairman Board of Trustee/Administrator, Arulmigu Mariamman Temple, Shevapettai, Selam 636 002. 9.The Executive Officer, Arulmigu Mariamman Temple, Shevapettai, Salem 636 002. Writ Petition has been filed under Article 226 of Constitution of India praying to issue a Writ of Mandamus directing the respondents to take adequate and appropriate safety and regulatory measures in connection with the construction and Kumbabishekam, which is schedule to be held on 22.02.2026 in the 9th respondent temple by considering the petitioner representations dated 12.01.2026, 07.02.2026 and 15.02.2026. For Petitioner :Mr.R.Marudhachalamurthy For Respondents :Mr.K.Karthikeyan, GA (Hr & CE) for R1 to R4, R7 to R9 Mr.J.Subbiah, GA(Crl.Side) for R6 Mr.S.Senthilmurugan, Spl.GP for R5 --------

Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.