VoxJuris
Home › High Courts › Madras High Court 2026 › High Court of Madras

S.Selvam v. The Divisional Engineer

DISPOSED OF WITH DIRECTION
Court
High Court of Madras
Decided
23 March 2026
Bench
M.Dhandapaniauthor
Case no.
WP 11429/2024

Judgment

ORDER This Writ Petition is filed for a direction to the first respondent to consider the representations, dated 23.01.2024 and 14.02.2024 and to return back the amount of Rs.17,39,22,088/- deposited by the petitioner as a security to the first respondent.

¶2It is the contention of the petitioner that he was appointed as Sub-Contractor for laying of Optical Fiber Cable works for the project given to the M/s.Larsen & Toubro Limited. The petitioner approached the Assistant Divisional Engineer for permission for right of way. The Highway Department directed the petitioner to deposit the refundable security money for restoration of cable laying works and also to execute a performance bank guarantee. Accordingly, he remitted the amount by way of Demand Draft in favour of the first respondent. After completion of the work, the National Highway authorities inspected the work and issued a completion certificate. Even though the prime contractor, M/s.Larsen & Toubro Limited received the entire amount, the petitioner was not given the refundable security amount. Inspite of several representations, the security deposit amount was not refunded to the petitioner. Hence, this Writ Petition is filed.

¶3Learned Counsel for the petitioner submitted that this Court may direct the first respondent to consider and pass orders on the petitioner's representations within the stipulated time as fixed by this Court.

¶4Learned Senior Panel Counsel appearing for the respondents submitted that the representations will be considered and orders will be passed within the stipulated time as fixed by this Court.

¶5Heard the learned Counsel for both side and perused the materials available on record.

¶6Considering the facts and circumstances of the case and in view of the limited request sought for by the petitioner, this court directs the first respondent to consider and pass orders on the petitioner's representations dated 23.01.2024 and 14.02.2024 within a period of four weeks from the date of receipt of a copy of this order.

¶7With the above directions, the Writ Petition is disposed of. There shall be no order as to costs.

23.03.2026 Index : yes/no Speaking order/Non-speaking order : yes/no grs To

¶1The Divisional Engineer, National Highway, Coimbatore – 18.

¶2The Regional Officer, Ministry of Road Transport & Highways, C-1-A, Rajaji Bhavan, Besant Nagar, Chennai – 600 090.

¶3Bharat Sanchar Nigam Limited, No.78, Purasawalkam High Road, Chennai – 600 010.

M.DHANDAPANI, J. grs

23.03.2026

Case details

Parties and counsel

IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED : 23.03.2026 CORAM : THE HON'BLE MR.JUSTICE M.DHANDAPANI S.Selvam .. Petitioner Versus 1. The Divisional Engineer, National Highway, Coimbatore – 18. 2. The Regional Officer, Ministry of Road Transport & Highways, C-1-A, Rajaji Bhavan, Besant Nagar, Chennai – 600 090. 3. Bharat Sanchar Nigam Limited, No.78, Purasawalkam High Road, Chennai – 600 010. .. Respondents Prayer : Writ Petition filed under Article 226 of the Constitution of India seeking a Writ of Mandamus, directing the 1st respondent to consider the representations, dated 23.01.2024 and 14.02.2024 and to return back the amount of Rs.17,39,22,088/- deposited by the petitioner as a security to the 1st respondent. For Petitioner : Mr.B.K.Girish Neelakantan For Respondents : Ms.P.J.Anitha, Senior Panel Counsel, for RR-1 and 2

Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.