- Court
- High Court of Madras
- Decided
- 6 April 2026
- Bench
- M.Dhandapani
- Case no.
- WP 12763/2026
Judgment
ORDER By consent of both parties, this writ petition is taken up for final disposal at the admission stage itself. Since no adverse order is passed against the private respondent, notice to the private respondent is dispensed with.
¶2This petition has been filed for a direction, directing the respondents 1 to 3 to restore the electricity connection of petitioner pertaining to 3rd respondent service connection in S.C.NO.041270141500 by considering the petitioners representation dated 25.10.2025.
¶3It is the case of the petitioner that the petitioner has got title of the subject lands through his father by virtue of sale deed dated 10.05.2025 on the file of SRO, Omalur, however, the electricity connection was not transferred to his name and the same stands in his father name. The fourth respondent with an ulterior motive removed the fuse carrier disconnected the electricity connection on 16.09.2025, in this regard, the petitioner made a complaint before the Inspector of Police, Thivattipatti Police Station and the same is pending. The petitioner has also sent representation to the official respondents on 25.10.2025, however, the same is pending without consideration. Hence, this writ petition.
¶4Heard the learned counsel for the petitioner and the learned counsel for the official respondents and perused the materials placed on record.
¶5Considering the limited relief sought for in this writ petition, this Court without going into the merits of the case directs the respondents 1 to 3 to consider the representation of the petitioner dated 25.10.2025 and pass appropriate order on merits and in accordance with law after giving opportunity to the fourth respondent by conducting enquiry between the petitioner and the fourth respondent and if it is found that the fourth respondent has illegally disturbed the petitioner's connection, the same may be restored. Such exercise shall be completed within a period of four weeks from the date of receipt of a copy of this Order.
¶6Accordingly, this writ petition stands disposed of. No costs. 06-04-2026 dhk Index:Yes/No Speaking/Non-speaking order Internet:Yes To
1.The Executive Engineer, Tamilnadu Electricity Board, Omalur Taluk, Salem District.
2.The Assistant Executive Engineer, Tamilnadu Electricity Board, Signampatti Post (Thumbipadi) pannapatti, Salem District.
3.The Assistant Engineer, Tamilnadu Electricity Board, Chinna Tirupathi, Kadayampatti Taluk, Salem District. M.DHANDAPANI J. dhk
06-04-2026
Case details
Parties and counsel
IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 06-04-2026 CORAM THE HONOURABLE MR JUSTICE M.DHANDAPANI S.Sathishkumar Petitioner(s) Vs 1. The Executive Engineer, Tamilnadu Electricity Board, Omalur Taluk, Salem District. 2.The Assistant Executive Engineer, Tamilnadu Electricity Board, Signampatti Post (Thumbipadi) pannapatti, Salem District. 3.The Assistant Engineer, Tamilnadu Electricity Board, Chinna Tirupathi, Kadayampatti Taluk, Salem District. 4.S.Ganesan Respondent(s) PRAYER: Petition filed under Article 226 of Constitution of India, directing the respondents 1 to 3 to restore the electricity connection of petitioner pertaining to 3rd respondent service connection in S.C.NO.041270141500 by considering the petitioners representation dated 25.10.2025. For Petitioner(s): Mr.B.Ramprabu For Respondent: Mr.I.Syed Sibghatulla for R1 to R3
Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.