VoxJuris
Home › High Courts › Madras High Court 2026 › High Court of Madras

Kaliammal v. The District Collector

DISPOSED OF
Court
High Court of Madras
Decided
11 March 2026
Bench
Krishnan Ramasamyauthor
Case no.
WP 12233/2024

Judgment

ORDER This Writ Petition has been filed to direct the respondents to consider the petitioner's representation dated 08.03.2024.

2.The learned counsel for the petitioner would submit that in this case, the petitioner has given a representation dated 08.03.2024 to provide service road facility abutting retaining walls for its entire stretch on the either side of the 'Road under Bridge' to be constructed in Neikaranpatti – Parali road crossing the Salem-Karur Broad Guage Railways line level crossing Gate No.12, by acquiring land, enabling the petitioner for her ingress and egress from Neikaranpatti – Parali Road to her properties.

¶3In reply, the learned Additional Government Pleader appearing for the respondents 1 & 2 would submit that the petitioner's representation dated

08.03.2024 will be disposed of by the 2nd respondent within a period of four weeks. Page3 of 4

¶4Heard the learned counsel for the petitioner and the learned Additional Government Pleader for the respondents and also perused the materials available on record.

¶5In view of the above, this Court directs the 2nd respondent to consider the petitioner's representation dated 08.03.2024 on its own merits and dispose of the same in accordance with law within a period of four weeks from the date of receipt of copy of this order, after issuing notice to the petitioner.

¶6With the above directions, this writ petition is disposed of. No costs. 11-03-2026 Index: Yes/No Speaking/Non-speaking order KKN Page4 of 4

KRISHNAN RAMASAMY, J. KKN To

¶1The District Collector, District Collectorate, Namakkal.

¶2The Special Tahsildar (Land Acquisition) Salem-Karur Broad Gauge Railway Project, Collectorate Complex, Namakkal 637003.

¶3The Deputy Chief Engineer, Southern Railways (Construction) Southern Railway Office Complex, Salem 5. 11-03-2026

Case details

Parties and counsel

Page1 of 4 IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 11-03-2026 CORAM THE HON'BLE MR JUSTICE KRISHNAN RAMASAMY Kaliammal ..Petitioner(s) Vs 1. The District Collector, District Collectorate, Namakkal. 2. The Special Tahsildar (Land Acquisition) Salem-Karur Broad Gauge Railway Project, Collectorate Complex, Namakkal 637003. 3. The Deputy Chief Engineer, Southern Railways (Construction) Southern Railway Office Complex, Salem 5. ..Respondent(s) Prayer: Writ Petition filed under Article 226 of the Constitution of India, seeking issuance of writ of mandamus, directing the respondents to provide service road facility abutting retaining walls for its entire stretch on the either side of the Road Under Bridge to be constructed in Neikaranpatti - Parali Road crossing the Salem-Karur Broad Gauge Railways line level crossing gate No.12 by acquiring land, enabling the petitioner for his ingress and egress from Neikaranpatti - Parali Road to his properties situate in S.Nos. 464/5A in Ariyur Village, Mohanur Taluk, Namakkal District by considering the petitioner's representation dated 08.03.2024 within the time frame. Page2 of 4 For Petitioner(s): Mr.K.M.Arun For Respondent(s): Mr.T.K.Saravanan Additional Government Pleader for R1 & R2 Mr.K.S.Jeyaganeshan Senior Panel Counsel for R3

Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.