Judgment
ORDER (Order of the Court was made by the Hon'ble Chief Justice) This petition, styled as public interest litigation, has been filed by a practising advocate seeking issuance of a writ of mandamus directing respondents 1 to 3 herein to take action against the fourth respondent hotel/restaurant on the basis of the communication sent by the first respondent dated
02.09.2025 at the earliest point of time as may be fixed by this court.
¶2It is the case of the petitioner that the fourth respondent/restaurant is functioning illegally in a residential area without obtaining any license and without proper parking area for the visitors. In this regard, the petitioner has sent a representation to the first respondent and the first respondent, by proceedings dated 2.9.2025, addressed to respondent Nos.2 and 3, directed the said authorities to examine the veracity of the complaint and take necessary enforcement action. It is alleged that till date no action has been taken against the fourth respondent/restaurant till date. Hence, the present writ petition.
¶3It is admitted that seeking identical relief the petitioner herein had earlier filed W.P.No.45310 of 2025. This Court, by order dated 25.11.2025, disposed of the writ petition by directing the local authority to take those measures as may be necessary to manage and regulate traffic movement, parking, etc.
¶4On a perusal of the prayers made in W.P.No.45310 of 2025 and the present writ petition, we are of the view that both are identical in nature. The present writ petition is, therefore, hit by the principle of res judicata. It is well settled proposition in law that principle of res judicata applies to writ proceedings, as has been held by the Supreme Court in Daryao v. State of Uttar Pradesh1; Virudhuttagar Steel Rolling Mills Limited v. Government of Madras2, and Shankara Co-operative Housing Society Limited v. M. Prabhakar3. Therefore, we are not inclined to entertain the present writ petition and the same is liable to be dismissed.
¶5If the court's earlier order has not been acted upon, the petitioner's recourse lies elsewhere. Filing a new petition for the same relief is not the correct procedure. 1 AIR 1961 SC 1457 2 AIR 1968 SC 1196 3 (2011) 5 SCC 607
¶6The writ petition is, therefore, dismissed. There shall be no order as to costs. Consequently, interim application stands closed. We make it clear that this order shall not come in the way of the respondent authorities considering the complaint of the petitioner in accordance with law. (SUSHRUT ARVIND DHARMADHIKARI,CJ) (G.ARUL MURUGAN,J)
16.04.2026 Index : : sasi To:
¶1The Member Secretary Chennai Metropolitan Development Authority, No.1, Gandhi Irwin Road, Egmore, Chennai – 600 008.
¶2The Commissioner Greater Chennai Corporation, Chennai – 600 003.
¶3The Zonal Executive Engineer Zone IX, 4th Cross street, Lake View road, Chennai – 600 034. THE HON'BLE CHIEF JUSTICE AND G.ARUL MURUGAN,J.
(sasi) WP No.14275 of 2026
16.04.2026
Case details
Parties and counsel
IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 16.04.2026 CORAM : THE HONOURABLE MR. SUSHRUT ARVIND DHARMADHIKARI, CHIEF JUSTICE AND THE HONOURABLE MR.JUSTICE G.ARUL MURUGAN WP No.14275 of 2026 and WMP N o .15516 of 2026 M.Babu Advocate, Room B, Door No. 348/160 Hussain Plaza, Thambu Chetty Street, Parrys Corner, Chennai – 600 001. Petitioner(s) Vs 1. The Member Secretary Chennai Metropolitan Development Authority, No.1, Gandhi Irwin Road, Egmore, Chennai – 600 008. 2. The Commissioner Greater Chennai Corporation, Chennai – 600 003. 3. The Zonal Executive Engineer Zone IX, 4th Cross street, Lake View road, Chennai – 600 034. 4. The Proprietor Hotel Manjal, Door No.6/9 Kasthuri Estate, 3rd Street, Poes Garden, Mylapore, Chennai. Respondent(s) PRAYER : Petition filed under Article 226 of the Constitution of India seeking issuance of a writ of mandamus directing respondents 1 to 3 herein to take action against the 4th respondent hotel/restaurant on the basis of the communication sent by the 1st respondent dated 2.09.2025 at the earliest point of time as may be fixed by this court. For Petitioner(s): Mr. J.Pothiraj For Respondent(s):Mrs.P.Veena Suresh Standing Counsel for R1 Mr.D.B.R.Prabhu Standing Counsel for R2 and R3
Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.