Judgment
Order This writ petition has been filed seeking the issuance of a writ of mandamus directing the respondents 1 to 3 to pass orders on the representations for Re-Enquiry dated 20.11.2025, 03.01.2026, and 23.02.2026 submitted by the petitioner against the report of the enquiry officer pursuant to the memo in Ku. Aa. No 3112-2/Me.Po / Ka. Mi. Pa. Va / Kallai / Ni. A / Ni. Pi. II / Assistant 3 / Ko. O.Na/ 2025 dated 06.11.2025 on the file of the 3rd respondent. Page3 of 6
¶2The case of the petitioner is that he was appointed as an Assistant in the respondent Board through direct recruitment on 01.03.2014. Thereafter, he was promoted as a Wireman in the year 2018 and subsequently promoted as Line Inspector and posted at Puthupattu Sub-Station on 30.11.2024.
¶3While so, the 3rd respondent had issued a charge memo dated
25.02.2025 alleging that, during the restoration of a damaged 11 KV High Tension electricity line across the Thenpennai River following the Fengal Cyclone, the petitioner had engaged four persons who were not employees of the respondent Board and that one among them, namely Dilipkumar, was swept away by the river and remained untraceable. The petitioner submitted his explanation on 07.03.2025. Thereafter, an enquiry was conducted by the 4th respondent, who submitted a report confirming the charges. Based on the said report, the 3rd respondent had issued a further memo dated 06.11.2025 calling upon the petitioner to submit his explanation. The petitioner submitted his explanation on 20.11.2025 before the 3rd respondent, followed by a reminder on
03.01.2026. Even thereafter, no order was passed by the 3rd respondent. Hence, he made a representation to the respondents 1 to 3 on 23.02.2026 requesting them to take action on his explanation. However, no action has been taken to date. Hence, the petitioner has filed the present writ petition. Page4 of 6
¶3The learned counsel for the petitioner would submit that it would suffice if a direction is issued to the respondents 1 to 3 to pass orders on the explanation submitted by the petitioner on 20.11.2025.
¶4Heard the learned counsel for the petitioner and the learned Standing Counsel appearing for respondents.
¶5Considering the facts and circumstances of the case, respondents 1 to 3 are directed to consider the petitioner's explanation dated 20.11.2025 and pass appropriate orders on merits and in accordance with law, as expeditiously as possible.
¶6With the above direction, this writ petition is disposed of. No costs. 02-06-2026 Index: Yes/No Speaking/Non-speaking order SRN Page5 of 6 To
¶1The Chairman cum Managing Director Tamil Nadu Power Distribution Corporation Ltd., Chennai 600 002
¶2The Chief Engineer Distribution, Thiruvannamalai Region, Tamil Nadu Power Distribution Corporation Ltd., Thiruvannamlai
¶3The Superintending Engineer Tamil Nadu Power Distribution Corporation Ltd., Kallakurichi Electricity Distribution Circle, Kallakurichi
¶4The Assistant Engineer (O and M) Town Chinna Salem Sub Division, Kallakurichi Division, Kallakurichi Electricity Distribution Circle, Kallakurichi Page6 of 6 P.T.ASHA J. SRN 02-06-2026
Case details
Parties and counsel
Page1 of 6 IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 02-06-2026 CORAM THE HON'BLE MS. JUSTICE P.T. ASHA R.Kannan Line Inspector, O/o AE / 110 / 22 KV SS / Puthupattu, Sankarapuram West Sub Division, Sankarapuram Division, Kallakurichi Electricity Distribution Circle, Kallakurichi District, ..Petitioner(s) Vs 1. The Chairman cum Managing Director Tamil Nadu Power Distribution Corporation Ltd., Chennai 600 002 2. The Chief Engineer Distribution, Thiruvannamalai Region, Tamil Nadu Power Distribution Corporation Ltd.,Thiruvannamlai 3. The Superintending Engineer Tamil Nadu Power Distribution Corporation Ltd.,Kallakurichi Electricity Distribution Circle, Kallakurichi 4. The Assistant Engineer (O and M) Town Chinna Salem Sub Division, Kallakurichi Division, Kallakurichi Electricity Distribution Circle, Kallakurichi ..Respondent(s) Page2 of 6 Prayer:- Writ petition filed under Article 226 of the Constitution of India praying for issuance of a Writ of Mandamus directing the respondents 1 to 3 to pass orders on the representation for Re-Enquiry dated 20.11.2025, 03.01.2026, and 23.02.2026 given by the petitioner against the report of the enquiry officer in pursuant to the memo in Ku. Aa. No 3112- 2/Me.Po / Ka. Mi. Pa. Va / Kallai / Ni. A / Ni. Pi. II / Assistant 3 / Ko. O.Na/ 2025 dated 06.11.2025 on the file of the 3rd respondent and reject the report of the enquiry office on the basis that it was not supported by the Statements of the witnesses, as well as the documentary evidences and substantiate the charge on the basis of materials on record or should establish that there was probability that the charges are made out. For Petitioner(s): Mr.S.Doraiswamy For Respondent(s): Mr.C.Manoharan Standing Counsel
Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.