ORDER The learned Advocate General appearing for the respondents would submit that this Court, by its order dated 01.04.2026, had directed the respondents to deposit the admitted amount, as per the earlier order of this Court dated 24.02.2026, on or before 15.04.2026. However, the said direction has not been complied with.
¶2The learned Advocate General, on instructions, would further submit that the admitted amount is required to be paid to the petitioner either by the Water Resources Department or by the Chennai River Restoration Trust. However, a dispute has arisen as to which authority is liable to make such payment. He would further submit that the issue will now be placed before the Chief Secretary to the Government, who shall conduct an enquiry and issue appropriate directions to either the Chennai River Restoration Trust or the Page2 of 5 Water Resources Department to pay the admitted amount to the petitioner. A decision in this regard shall be taken on or before 28.04.2026.
3.In view of the submission made by the learned Advocate General, the Chief Secretary to Government, Secretariat, Fort St. George, Chennai-600 009, is suo motu impleaded as third respondent in this writ petition. The impleaded third respondent is directed to hear the respondents 1 and 2 and ensure payment of the admitted amount to the petitioner on or before 28.04.2026.
4.The appearance of the 1st and 2nd respondents is dispensed with at present.
5.Registry is directed to list the matter under the caption for reporting compliance on 28.04.2026. 16-04-2026 Uma Note: Issue order copy today i.e on 16.04.2026 Page3 of 5 To
¶1The Superintending Engineer, Water Resources Department, Public Works Department, Palar Basin Circle, WRD, Chepauk, Chennai-600 005.
¶2The Additional Chief Secretary / Member Secretary, Chennai River Restoration Trust, No.6/103, Dr.D.G.S.Dinakaran Salai, Raja Annamalaipuram, Chennai - 28.
¶3The Chief Secretary to Government Secretariat, Fort St. George, Chennai-600 009. Page4 of 5
M.DHANDAPANI, J. Uma 16-04-2026 Page5 of 5
Case details
Parties and counsel
IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 16-04-2026 CORAM THE HON'BLE MR JUSTICE M.DHANDAPANI Annai Infra Developers Limited Rep. by its Authorized Signatory M.Ambethraja, Address.1/203, Ambethkar Colony, Vadapalanji, Madurai-625 021. ..Petitioner(s) Vs 1. The Government of Tamil Nadu Water Resources Department, Rep. by its Superintending Engineer, Public Works Department, Palar Basin Circle, WRD, Chepauk, Chennai-600 005. 2. The Additional Chief Secretary / Member Secretary, Chennai River Restoration Trust, No.6/103, Dr.D.G.S.Dinakaran Salai, Raja Annamalaipuram, Chennai - 28. (R2 was suo motu impleaded vide order dated 11.07.2025 made in W.P No.20145 of 2025) 3.The Chief Secretary to Government Secretariat, Fort St. George Chennai-600 009 (R3 was suo motu impleaded vide order dated 16.04.2025) ..Respondents Page1 of 5 For Petitioner: Mr.P.J.Rishikesh For Respondents: Mr.P.S.Raman, Advocate General Assisted by Mr.S.Rajesh Government Advocate for R1 & R2 R3 suo motu impleaded