ORDER This Writ Petition has been filed for the following reliefs:- "Directing the respondents to pay interest for the belated payment of Death cum Retirement Gratuity and Encashment of Earned Leave, at the rate of 18 percent per annum form the date of retirement of the petitioner ie.30.09.2022 till the date of payment of benefits within the time frame fixed by this Honble Court."
¶2The case of the petitioners is that he was appointed in the respondent-Corporation on 27.03.1992 and retired from service on 30.09.2022. However, the terminal benefits have been settled to the petitioner on 07.05.2026 but no interest has been paid for the delayed period. Therefore, the petitioner had submitted a representation to the respondent dated 28.05.2026, requesting to pay interest for the delayed period. Since the same was not considered, the present writ petition has been filed.
¶3The learned Government Advocate appearing on behalf of the respondents would fairly submit that they are willing to pay the interest at the Page3 of 4 rate of 6% per annum for the belated payment of the eligible and admissible amount.
¶4Heard the learned counsel for both sides and perused the materials available on record.
¶5In view of the above submission of the learned Government Advocate, this Court deems it appropriate to direct the respondents to pay interest at the rate of 6% per annum for the belated payment of eligible and admissible terminal benefits from the date of retirement till the date of actual disbursal of the terminal benefits of the petitioner within a period of six weeks from the date of receipt of a copy of this order.
¶6In the result, the Writ Petition is disposed of. No costs. 22-06-2026 Index: Yes/No Speaking/Non-speaking order SHR Page4 of 4 P.T.ASHA J. SHR To
¶1The Principal Secretary to Government Environment, Climate Change and Forest Department, Ex -offiicio Chairman for Tamilnadu for Tamil nadu Tea Plantation corporation, Fort St. George, Chenani 600 009
¶2Tamil nadu Tea Plantation Corporation Ltd., Rep by its Managing Director, Orange Grove Road, Coonoor 643 101
¶3The Divisional Manager Tamil nadu Tea Plantation Corporation Ltd, Nelliyalam Tea Division, Kolapalli Post, Pandalur Taluk, The Nilgiris District 22-06-2026
Case details
Parties and counsel
Page1 of 4 IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 22-06-2026 CORAM THE HON'BLE MS. JUSTICE P.T. ASHA K.A.Iyyappan ..Petitioner(s) Vs 1. The Principal Secretary to Government Environment, Climate Change and Forest Department, Ex -offiicio Chairman for Tamilnadu for Tamil nadu Tea Plantation corporation, Fort St. George, Chenani 600 009 2. Tamil nadu Tea Plantation Corporation Ltd., Rep by its Managing Director, OrangeGrove Road, Coonoor 643 101 3. The Divisional Manager Tamil nadu Tea Plantation Corporation Ltd, Nelliyalam Tea Division, Kolapalli Post, Pandalur Taluk, The Nilgiris District ..Respondent(s) Prayer:- Writ petition filed under Article 226 of the Constitution of India praying for issuance of a writ of Mandamus Directing the respondents to pay interest for the belated payment of Death cum Retirement Gratuity and Encashment of Earned Leave, at the rate of 18 percent per annum form the date of retirement of the petitioner ie.30.09.2022 till the date of payment of benefits within the time frame fixed by this Honble Court. Page2 of 4 For Petitioner(s): Mr.N.K.Ponraj For Respondent(s): Mr.L.Gokulraj, GA for R1 to R3.
Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.