ALLOWED
Court
High Court of Madras
Decided
23 January 2026
Bench
B.Pugalendhiauthor
Case no.
WP(MD) 1609/2026

Follow Madras High CourtFollow B.Pugalendhi

Judgment

ORDER The petitioner was appointed as a Helper in the respondent Transport Corporation on 25.07.1986 and after rendering 38 years of service, he retired from service as Special Grade Tradesman 6th Level on

31.07.2024. However, the retirement benefits due to the petitioner were settled belatedly. Seeking interest for the belated payment of retirement benefits, the petitioner gave a representation to the respondents on

25.12.2025, however, it was not considered by the respondents. Therefore, the petitioner has filed this writ petition for the above said relief.

¶2Mr.K.Ramaiah, learned Standing Counsel, who takes notice on behalf of the respondents, submits that the retirement benefits, have been settled to the petitioner, however, belatedly.

¶3By consent of both the parties, the writ petition is taken up for final hearing at the admission stage itself.

¶4This Court paid its anxious consideration to the rival submissions made and also perused the materials placed on record.

¶5The employer is liable to settle the retirement benefits to its employees without any delay and in case, if it is settled belatedly, it has to be compensated by way of interest for the belated payment. In this regard, the Hon'ble Apex Court in S.K.Dua vs. State of Haryana reported in 2008 (3) SCC 44, has held as follows: "14. In the circumstances, prima facie, we are of the view that the grievance voiced by the appellant appears to be well founded that he would be entitled to interest on such benefits. If there are statutory rules occupying the field, the appellant could claim payment of interest relying on such rules. If there are administrative instructions, guidelines or norms prescribed for the purpose, the appellant may claim benefit of interest on that basis. But even in absence of statutory rules, administrative instructions or guidelines, an employee can claim interest under Part III of the Constitution relying on Articles 14, 19 and 21 of the Constitution. The submission of the learned counsel for the appellant, that retiral benefits are not in the nature of "bounty" is, in our opinion well founded and needs no authority in support thereof. In that view of the matter, in our considered opinion, the High Court was not right in dismissing the petition in living even without issuing notice to the respondents."

¶6Following the same, in a similar issue, a Division Bench of this Court, in W.A.(MD)No.403 of 2010, etc. batch, vide common order dated 04.07.2014, has fixed the rate of interest at 6% per annum and held as under:- "5. ..... even though there is no provision in the Tamil Nadu State Transport Corporation Employees Pension Fund for payment of interest, cannot stand in the light of the law laid down by the Supreme Court in S.K.Dua v. State of Haryana and another, reported in

(2008) 3 SCC 44. As a matter of fact, the Rules do not contemplate belated payment of retirement benefits. The Rules contemplate prompt payment. When the Rules contemplate prompt payment and not bleated payment, the Rules will not contain a provision for payment of interest. The Pension Fund which was created as a Trust by the Corporation was supposed to act in trust for the employees' benefit. If the Trust could not make payments within the time stipulated, then, irrespective of whether there is any provision for payment of interest or not, the Corporation is obliged to make payment."

¶7Following the dictum laid down on this issue, the writ petition is allowed with a direction to the respondents to pay interest, for the belated payment of retirement benefits of the petitioner, at the rate of 6% p.a., within a period of six months from the date of receipt of a copy of this order. No costs.

23.01.2026 ogy Index : Yes / No. Internet : Yes / No. NCC : Yes / No.

B.PUGALENDHI, J. ogy To

¶1The Managing Director, Tamil Nadu State Transport Corporation (Thirunelveli) Limited, 23/2, Kattaboman Nagar, Thirunelveli – 627 011.

¶2The General Manager, Tamil Nadu State Transport Corporation (Thirunelveli) Limited, Thiruvanandhapuram Road, Vanarapettai, Thirunelveli – 627 003. WP(MD) No.1609 of 2026

23.01.2026

Case details

Parties and counsel

BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT Dated : 23.01.2026 CORAM THE HONOURABLE MR. JUSTICE B.PUGALENDHI WP(MD)No.1609 of 2026 P.Ramakrishnan ... Petitioner Vs 1. The Managing Director, Tamil Nadu State Transport Corporation (Thirunelveli) Limited, 23/2, Kattaboman Nagar, Thirunelveli – 627 011. 2. The General Manager, Tamil Nadu State Transport Corporation (Thirunelveli) Limited, Thiruvanandhapuram Road, Vanarapettai, Thirunelveli – 627 003. ... Respondents Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus, directing the respondent to pay interest at the rate of 6% per annum to the petitioner for the belated payment of Gratuity, Provident Fund, EL surrender and leave salary from the date of retirement to the date of actual payment within a time frame as may be fixed by this Court. For Petitioner : M/s.D.Ramya For Respondents : Mr.K.Ramaiah, Standing Counsel

Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.