- Court
- High Court of Madras
- Decided
- 22 September 2023
- Bench
- S Justice S.Srimathy
- Case no.
- WP(MD) 5638/2021
Judgment
ORDER This Writ Petition is filed for Writ of Certiorarified Mandamus, to quash the impugned order, dated 23.12.2020 passed by the third respondent and consequently directing the respondents to shift the High Tension Line from petitioner's plot into a safe distance without insisting on any payment for shifting the electrical line.
¶2Heard the learned Counsel appearing for the petitioner and the learned Standing Counsel appearing for the respondents and perused the materials available on record.
¶3The petitioner has sought to shift the electricity pole from his plot. Pending Writ Petition, the work is completed. The claim of the petitioner has already granted by the respondents. Therefore, nothing survives for adjudication.
¶4Hence, this Writ Petition is closed. There shall be no order as to costs. Consequently, connected miscellaneous petition is closed.
22.09.2023 NCC : Yes/No Index : Yes / No Internet : Yes/ No Sml
S.SRIMATHY, J.
Sml
22.09.2023
Case details
Parties and counsel
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 22.09.2023 CORAM THE HONOURABLE MRS.JUSTICE S.SRIMATHY and W.M.P.(MD).No.4474 of 2021 M.Maran ... Petitioner Vs. 1.The Superintending Engineer, Madurai Electricity Distribution Circle, Tamil Nadu Electricity Board, Madurai. 2.The Executive Engineer, Madurai Electricity Distribution Circle, Tamil Nadu Electricity Board, Madurai North, Madurai. 3.The Assistant Engineer, Rural, Tamil Nadu Electricity Board, Thiruppalai, Madurai. ... Respondents Prayer: Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Certiorarified Mandamus, to call for the records of the third respondent made in K. No. oo. me. po/ oo/ Thiru/ Madu/ Va.Aa/ Ko.pugarmanu/ A.No 570/20 dated 23.12.2020 and to quash the same in so far as it relates to directing the petitioner to pay the cost and charges for shifting of 11 KV High Tension electrical line running over the petitioner's property situated at Plot No.14A, in S.No 136/8, Tiruppalai, Madurai and consequently directing the respondents to shift the high tension line from petitioner's plot into a safety distance without insisting any payment for shifting the electrical line. For Petitioner : Mr.D.Srinivasa Ragavan For Respondents : Mr.S.Deenadhayalan, Standing Counsel
Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.