ORDER By consent of both the parties, this Writ Petition is taken up for final disposal.
¶2Originally, the fishery rights lease was granted to the petitioner for a period of four months commencing from 23.02.2021. According to the respondents, the lease was not thereafter extended. The learned counsel for the petitioner herein would submit that the petitioner had made some investments on the presumption that his lease would be extended. In this connection, he has also made a representation to the respondents on 06.09.2022 seeking for extension of lease.
¶3This Court is of the view that since the lease had already expired after four months from 23.02.2021, the present prayer may not require consideration. Rather the ends of justice could be secured, if the respondents are directed to consider the petitioner's representation. Accordingly, there shall be a direction to the respondents herein to consider the petitioner's representation dated
06.09.2022 on its own merits and pass appropriate orders in accordance with law within a period of four (4) weeks from the date of receipt of a copy of this order.
¶4With the above direction, this Writ Petition stands disposed of. There shall be no order as to costs. Consequently, connected miscellaneous petitions are closed.
25.05.2023 NCC : Yes / No Index : Yes / No Internet : Yes/ No Lm To
1.The Executive Engineer, Water Resource Organization/ Public Works Department, Mel Vaippar Basin Division, Rajapalayam Post - 626 117, Virudhunagar District.
2.The Assistant Engineer, Water Resource Organization/ Public Works Department, Mel Vaippar Basin Sub-Division, Krishnankovil Section, Srivilliputhur - 626 125, Virudhunagar District. M.S.RAMESH
, J.
Lm
25.05.2023
Case details
Parties and counsel
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 25.05.2023 CORAM THE HONOURABLE MR.JUSTICE M.S.RAMESH and W.M.P.(MD).Nos.10529 and 10530 of 2023 S.Mariappan ... Petitioner Vs. 1.The Executive Engineer, Water Resource Organization/ Public Works Department, Mel Vaippar Basin Division, Rajapalayam Post - 626 117, Virudhunagar District. 2.The Assistant Engineer, Water Resource Organization/ Public Works Department, Mel Vaippar Basin Sub-Division, Krishnankovil Section, Srivilliputhur- 626 125, Virudhunagar District. ...Respondents Prayer : Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus, to direct the respondents to extend the fishery rights lease for further period of two years as per G.O.(Ms) No.332 Animal Husbandry and Fisheries (FS-IV) Department dated 17.11.1993 and to receive the enhanced 10% lease amount from the past year lease amount from the petitioner, for renewal of fishery rights for the pasali year 2023-2024 and 2024-2025 in respect of Ilanthaikulam Tank, Ilanthaikulam Village, Watrap Taluk, Virudhunagar District is concerned. For Petitioner : Mr.M.Saravanakumar For Respondents : Mr.M.Siddharthan Additional Government Pleader
Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.