- Court
- High Court of Madras
- Decided
- 8 June 2023
- Bench
- C.V. Karthikeyan
- Case no.
- WP(MD) 13259/2023
Judgment
ORDER
The Writ Petition has been filed in the nature of a Mandamus seeking a direction to the respondents to permit the petitioner to pay additional security deposit of Rs.37,45,580.00 /- (Rupees Thirty Seven Lakhs Fourty Five Thousand Five Hundred and Eighty only) in 10 equal installments.
¶2In the affidavit filed in support of the writ petition, it had been stated that owing to demand recession in marketing the products, the usage of electricity had come down drastically. It is also stated that even the petitioner was also affected owing to various conditions consequent to the Covid-19 pandemic.
¶3In view of all these facts, a request is placed before this Court that the additional security deposit demanded by the respondents may be permitted to be paid in equal monthly installments.
¶4Heard Mr.R.S.Pandiyaraj, learned Counsel for the petitioner and Mr.S.Deenadhayalan, learned Standing Counsel for the respondents.
¶5There had been earlier directions issued by Courts permitting such request, and accordingly, the petitioner is permitted to pay the additional security deposit in 6 equal monthly installments to the second respondent. The first monthly installment should be paid on or before 03.07.2023. The remaining five instalments should be paid within the next five succeeding months.
¶6Granting such permission, the Writ Petition stands disposed of. No costs.
08.06.2023 NCC : Yes / No Index : Yes / No Internet : Yes / No pnn
C.V.KARTHIKEYAN, J. pnn TO
1.The Chairman and Managing Director, Tamil Nadu Generation and Distribution Corporation Limited, 144, Anna Salai, Chennai 600 002.
2.The Superintending Engineer, TANGEDCO, Virudhunagar Electricity Distribution Circle, Virudhunagar. ORDER IN WP(MD) No.13259 of 2023 Date : 08/06/2023
Case details
Parties and counsel
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT Date : 08/06/2023 CORAM The Hon`ble Mr.Justice C.V.KARTHIKEYAN W.P(MD). No.13259 of 2023 Divyalakshmi Textiles (P) Limited, Kulasekaranallur Village, Thiruchuli Road, Ramasamy Nagar Post, Aruppukottai - 626 105, Virudhunagar District. represented by its General Manager Admin. R.Ganganna ... Petitioner Vs 1.The Chairman and Managing Director, Tamil Nadu Generation and Distribution Corporation Limited, 144, Anna Salai, Chennai 600 002. 2.The Superintending Engineer, TANGEDCO, Virudhunagar Electricity Distribution Circle, Virudhunagar. ... Respondents PRAYER :- Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus, directing the 1st and 2nd respondents to permit the petitioner to pay the Additional Security Deposit of Rs.37,45,580.00 alone in 10 equal monthly installments, along with the regular current consumption charges. For Petitioner : M/s.R.S.Pandiyaraj, Advocate. For Respondents : Mr.S.Deenadhayalan, Standing Counsel
Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.