Jegaselvi v. The Executive Engineer

DISPOSED OF ACCORDINGLY
Court
High Court of Madras
Decided
25 August 2023
Bench
B.Pugalendhiauthor
Case no.
WP(MD) 20677/2023

Judgment

O R D E R The petitioner has approached the second respondent seeking for domestic electricity service connection for her house. With a grievance that the same has not been effected based on the objections of the third respondent, the petitioner has filed this writ petition.

2.Mr.S.Deenadayalan, learned Standing Counsel, who takes notice for the respondents 1 & 2 submits that the third respondent has raised certain objections for providing electricity service connection to this petitioner, that if any poles are erected, it would affect his ingress and egress to his property. According to the learned Standing Counsel, they are intending to take poles through a common pathway. However, the third respondent without any valid reasons has raised objections preventing the authorities from effecting the service connection.

3.Considering the rival submissions made, this writ petition is disposed of with a direction to the second respondent to ascertain from the revenue officials as to whether the place to be used for erecting poles is a pathway or not, provide an opportunity to the third respondent and shall proceed further for effecting electricity service connection to the petitioner by taking police protection, if necessary. No costs.

25.08.2023 NCC : Yes / No. Index : Yes / No. Internet : Yes / No. vrn To

1.The Executive Engineer, Operation & Maintenance, Tamil Nadu Electricity Generation and Distribution Corporation (TANGEDCO), Pudukkottai, Pudukkottai District.

2.The Assistant Engineer, Operation & Maintenance, Tamil Nadu Electricity Generation and Distribution Corporation (TANGEDCO), Melapatti, Ennai Post, Iluppur Taluk, Pudukkottai District.

B.PUGALENDHI, J. vrn

25.08.2023

Case details

Parties and counsel

BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 25.08.2023 CORAM: THE HONOURABLE MR.JUSTICE B.PUGALENDHI Jegaselvi ... Petitioner Vs 1.The Executive Engineer, Operation & Maintenance, Tamil Nadu Electricity Generation and Distribution Corporation (TANGEDCO), Pudukkottai, Pudukkottai District. 2.The Assistant Engineer, Operation & Maintenance, Tamil Nadu Electricity Generation and Distribution Corporation (TANGEDCO), Melapatti, Ennai Post, Iluppur Taluk, Pudukkottai District. 3.Ayilusamy ... Respondents PRAYER: Writ Petition filed under Article 226 of the Constitution of India, seeking for the issuance of Writ of Mandamus, directing the respondents 1 & 2 to grant Domestic Electricity Service Connection to the petitioner's house in Door No.460a, at Vettukadu Village, Illupur Taluk, Pudukkottai District on the basis of the petitioner's online application dated 31.07.2023. For Petitioner : Mr.D.Ramesh Kumar For R1 & R2 : Mr.S.Deenadayalan Standing Counsel

Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.