BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 07.09.2023 CORAM THE HONOURABLE MRS.JUSTICE S.SRIMATHY W.P.(MD)Nos.21661 to 21663 of 2023 K.Nagarajan ... Petitioner in W.P(MD)No.21661 of 2023 S.V.Construction, Prop. N.Chitra ... Petitioner in W.P(MD)No.21662 of 2023 Arumugam ... Petitioner in W.P(MD)No.21663 of 2023 Vs.

¶1The Government of Tamil Nadu, Represented by its Principal Secretary, Public Works Department, Fort St. George, Secretariate, Chennai - 600009.

¶2The Chief Engineer, Public Works Department, Building (Construction and Maintenance) Division, Chennai.

¶3The Chief Engineer, Public Works Department, Building (Construction and Maintenance) Division, Madurai.

¶4The Superintending Engineer, Public Works Department, Building (Construction and Maintenance) Division, Madurai Circle, Madurai.

¶5The Executive Engineer, Public Works Department, Building (Construction and Maintenance) Division, Dindigul.

¶6The Assistant Commissioner of Central GST and Central Excise, Nethaji Nagar, R.M.Colony Road, Dindigul. ... Respondents in All the Writ Petitions Prayer in W.P(MD)No. 21661 of 2023 : Writ Petition filed under Article 226 of the Constitution of India for issuance of Writ of Mandamus, directing the Respondents No.1 to 5 to disburse the Service Tax, Interest and penalty amount to the Petitioner for the service rendered by the Petitioner for a period from 2014 to 2018 based on his Representation, dated 03.07.2023 and vide Letter, dated

11.07.2023 sent by the 5th Respondent in Letter No.Tha5/40/2023 within the stipulated time as fixed by this Court. COMMON PRAYER in W.P(MD)Nos. 21662 & 21663 of 2023 : Writ Petition filed under Article 226 of the Constitution of India for issuance of Writ of Mandamus, directing the Respondents No.1 to 5 to disburse the Service Tax, Interest and penalty amount to the Petitioner for the service rendered by the Petitioner for a period from 2015 to 2018 based on the Petitioner's Representation, dated 03.07.2023 and vide Letter, dated 11.07.2023 sent by the 5th Respondent in Letter No.Tha5/40/2023 within the stipulated time as fixed by this Court. In All the Writ Petitions For Petitioners : M/s.C.Mayilvahana Rajendran For Respondents : Mr.B.Saravanan Additional Government Pleader for R-1 to R-5 Mr.N.Dilip Kumar,

Senior Standing Counsel, for R-6

COMMON ORDER Since the issue involved in these Writ Petitions are similar in nature both the writ petitions are taken up together and disposed of by a Common order.

¶2This writ petitions are filed for issuance of a Writ of Mandamus, to direct the respondents to disburse the service tax, interest and penalty Waiver to the petitioner for the service rendered by him for the period from 2014-2018 and 2015 to 2018 respectively; based on their representations.

¶3The petitioners are Registered Class I Contractor in Public Works Department and he has carried out the works contract service to the Public Works Department during the period 2014-2018 and 2015-2018 respectively. The issue of paying service tax was considered by the Hon'ble Division Bench of this Court and has held that the petitioner is liable to pay tax. However, liberty was granted to the petitioners that they can collect the tax from the Government and pay it to the Department. Now, the petitioners have come out with a case that the Government is not considering the claim of the petitioners and pay the tax, inspite of several representations.

¶4Therefore, the 1st respondent ought to consider the case of the petitioners. The Learned Additional Government Pleader submitted that the claim of the petitioners is under consideration. Therefore, this Court is of the considered opinion that appropriate authority ought to consider and pass orders.

¶5Hence, the 1st respondent is directed to consider the case of the petitioners therein and pass orders within a period of twelve weeks from the date of receipt of a copy of this order.

¶6With the above said observation, the writ petitions are allowed. No Costs. Index : Yes / No

07.09.2023 Internet : Yes

ksa To

¶1The Government of Tamil Nadu, Represented by its Principal Secretary, Public Works Department, Fort St. George, Secretariate, Chennai - 600009.

¶2The Chief Engineer, Public Works Department, Building (Construction and Maintenance) Division, Chennai.

¶3The Chief Engineer, Public Works Department, Building (Construction and Maintenance) Division, Madurai.

¶4The Superintending Engineer, Public Works Department, Building (Construction and Maintenance) Division, Madurai Circle, Madurai.

¶5The Executive Engineer, Public Works Department, Building (Construction and Maintenance) Division, Dindigul.

¶6The Assistant Commissioner of Central GST and Central Excise, Nethaji Nagar, R.M.Colony Road, Dindigul. S.SRIMATHY, J ksa Common Order made in W.P.(MD)Nos.21661 to 21663 of 2023

07.09.2023

Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.