Judgment

ORDER

This Petition has been filed to summon the Contemnors 1 and 2/ Respondents 2 and 3 and to punish them for their wilful and disobedience of the order of this Court made in WP(MD) No.8098 of 2018 dated 04.11.2024.

¶2While pending contempt petition, by order dated 23.01.2026, this Court recorded that a fresh proposal is prepared to lay the drainage water adjacent to the petitioner's land and also a site plan. It is also explained to the officer concerned of the Contemnors. He seeks time to consult with his super officer to complete the said project. Further, this Court also recorded that the petitioner is also ready and willing to share the expenses for the project to be completed by the respondents.

¶3In furtherance to the said order, today (ie.13.02.2026), the first respondent filed a status report. It revealed that a joint site inspection was conducted on 20.11.2025 and 13.01.2026 and an estimate has been prepared for Rs.25,00,000/- for constructing drain to prevent the flow of rainwater into the petitioner's land for the length of 90 meters. This estimate will be submitted for getting administrative approval from the Government in the upcoming Financial Year 2026-2027.

¶4In view of the above, the first respondent is directed to submit the estimate for getting administrative approval to the Government within a period of four weeks from today. The Secretary to Government, Highways Department, Government of Tamil Nadu, is directed to sanction administrative approval for the project within a period of eight weeks thereafter. It is made clear that the Secretary to Government, Highways Department, Government of Tamil Nadu, is directed to complete the project without any financial implication on the petitioner.

3.With the above directions, this Contempt Petition stands closed.

13.02.2026 NCC : Yes / No Index : Yes / No Internet : Yes / No

LS TO

¶1S.Sathyamoorthi, The Divisional Engineer, Nagercoil Division, National Highways Department, Nagercoil, Kanyakumari District.

¶2C.S.Vijaya, The Divisional Engineer, State Highways, Thuckalai, Kanyakumari District. Copy to: The Secretary to Government, Highways Department, Government of Tamil Nadu, Fort St. George, Chennai. G.K.ILANTHIRAIYAN,J LS Note: Issue order copy on 24.02.2026.

CONT P(MD) No.3022 of 2025 in WP(MD) No.8098 of 2018

13.02.2026

Case details

Parties and counsel

BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT Dated : 13.02.2026 CORAM THE HONOURABLE MR. JUSTICE G.K.ILANTHIRAIYAN CONT.P(MD). No.3022 of 2025 in WP(MD) No.8098 of 2018 M.Shahul Hameed, ... Petitioner Vs. 1. S.Sathyamoorthi, The Divisional Engineer, Nagercoil Division, National Highways Department, Nagercoil, Kanyakumari District.. 2. C.S.Vijaya, The Divisional Engineer, State Highways, Thuckalai, Kanyakumari District. ... Respondents PRAYER :- Contempt Petition filed under Section 11 of the Contempt of Courts Act, 1971, to summon the Contemnors 1 and 2/ Respondents 2 and 3 and to punish them as per law for having willfully disobeyed the order of this Court made in WP(MD) No.8098 of 2018 dated 04.11.2024. For Petitioner : Mr.T.Antony Arul Raj, Advocate. For Respondents : Mr.D.Gandhiraj Special Government Pleader

Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.