Kafila Forge Ltd v. State of Haryana and Another

DISMISSED
Court
High Court of Punjab and Haryana
Decided
18 September 2024
Bench
Arun Palli, Vikram Aggarwalauthor
Case no.
CWP 5903/2019

Judgment

VIKRAM AGGARWAL, J.

1.    The petitioner prays for the issuance of a writ of mandamus directing the  respondents  to  refund  the  10%  amount  (alongwith  interest  etc.)  which  was deducted upon surrender of plot No.45, Sector 53 Phase-V, Industrial Estate, Kundli (hereinafter referred to as the 'disputed plot') in view of the order dated 20.09.2013 (Annexure P-3) passed by respondent No.2. The petitioner further seeks the refund of the entire deposited amount as has been granted to other similarly situated allottees. The petitioner also prays for a direction to the respondents to take a decision on the various representations/legal notice dated 17.12.2018 (Annexure P-10).

2.    Pursuant  to  an  advertisement  issued  in  the  year  2008,  the  petitioner applied  for  the  allotment  of  an  industrial  plot  measuring  12000  square  meters  at Kundli  on  20.08.2008.  Upon  consideration,  a  decision  was  taken  to  allot  a  plot measuring 11250 square meters situated in Industrial Estate, Kundli at a tentative rate of Rs.55,00/- per square meters. Initially, plot No.58, Sector 53, Phase–V, Industrial Estate, Kundli was decided to be allotted to the petitioner but subsequently the plot was changed to plot No.45 and, accordingly, Regular Letter of Allotment (for short 'RLA') dated 29.01.2009 (Annexure P-1) was issued. As per the RLA, the tentative price was Rs.6,18,75,000/- @ 5500 per square meters. The schedule of payments etc. was also given in the said RLA.

3.    The  petitioner  claims  to  have  deposited  a  sum  of  Rs.3,99,97,702/- towards the cost of the plot and Rs.59,98,636/- as interest and, therefore, paid a total of Rs.4,59,96,338/-.

4.    On account of a slowdown of the economy Pan India and particularly in industrial sectors,  the  petitioner, under compelling  circumstances,  surrendered  the plot vide communication dated 12.07.2013 (Annexure P-2/A). Vide communication dated 02.09.2013 (Annexure P-2/B), the request for surrender was acceded to and a sum of Rs.3,37,97,887/- was refunded and it was mentioned that 10% cost of the plot alongwith interest etc. had been forfeited.

5.    Shortly thereafter, on 20.09.2013 (Annexure P-3), a decision was taken by  the  Haryana  State  Industrial  and  Infrastructure  Development  Corporation (respondent No.2) (for short 'HSIIDC') that where industrial plots had been allotted till 31.12.2012 and on account of the slowdown, a request for surrender was made within  a  period  of  06  months  from  the  date  of  approval  of  the  proposal  i.e

29.08.2013, the HSIIDC would consider the same without any deduction and the principal amount deposited by the allottee towards the price of the plot would be refunded. Accordingly, the petitioner submitted his requests for refund of the amount on  various  occasions  (Annexures  P-4  and  P-5)  and  in  fact  these  requests  were rejected vide communication dated 10.04.2018 (Annexure P-7).

6.    The petitioner  also places  reliance upon  the  provisions  of  the Estate Management Procedure, 2011 (for short 'EMP 2011') (Annexure P-6) to support its case for refund of the entire amount.

7.    The disputed plot was ultimately allotted to one Inox World Industry Private Limited @ Rs.10,000/- per square meters. It is the case of the petitioner that no loss was, therefore, caused to HSIIDC on surrender of the disputed plot by the

8.    The petitioner represented to the Chief Minister of Haryana and also served upon the respondents a legal notice dated 17.12.2018 (Annexures P-9 and P-10 respectively) but to no avail, leading to the filing of the instant writ petition.

9.    The writ petition has been opposed by HSIIDC. In its written statement, the  allotment  of  the  plot,  the  tentative  price,  issuance  of  the  RLA,  request  for surrender made by the petitioner, passing of the order dated 20.09.2013 and other facts  as  pleaded  in  the  petition  have  been  admitted.  The  case  set  up  by  the respondents essentially is that in terms of condition No.5(c) and 2(iv) of the RLA and further  Chapter  6  of  the  EMP  2011,  the  amount  was  to  be  refunded  only  after deduction of 10% of the tentative price alongwith interest etc. With regard to the order dated 20.09.2013, with regard to refund of the entire amount in view of the slowdown, it has been averred that there was a specific clause that refunds already made would not be affected by the said order. It has also been averred that the case of the  petitioner  is  not  covered  by  the  said  order  as  the  disputed  plot  had  been surrendered  by  the  petitioner  vide  communication  dated  12.07.2013  and  it  was accepted by HSIIDC on 06.08.2013 i.e. much before the decision of the Board of Directors of HSIIDC on 29.08.2013 communicated vide circular dated 20.09.2013. The breakup of the amount paid and deductions made have also been given in the written statement. Another stand which has been taken in the written statement is that the petitioner was not able to commence construction and various show cause notices were issued to the petitioner, the details of which have been given in the written statement and ultimately, after more than 03 years of allotment, the petitioner made a request for surrender.

10.    In the replication, averments made in the written statement have been denied and those made in the writ petition have been reiterated. In the writ petition as also in the written statement, it has been submitted that while a similar relief has been

given  to  many  other  similarly  situated  persons,  the  same  has  been  denied  to  the petitioner.

11.    Learned counsel for the parties were heard.

12.    It was submitted by learned counsel representing the petitioner that the action of the respondents in deducting a huge amount of 1 crore of rupees is illegal and  arbitrary  especially  in  view  of  the  order  dated  20.09.2013.  Learned  counsel submitted that the respondents had been over technical in rejecting the case of the petitioner  whereas  they  had  refunded  the  entire  amount  to  many  other  similarly situated  persons.  However,  no  details  of  such  similarly  situated  persons  were furnished to the Court during the course of arguments nor any specific instance has been given in the writ petition or the replication. It was submitted that the petitioner had suffered a lot on account of the economic slowdown and further on account of the illegal deduction of about Rs.1 crore by HSIIDC. Learned counsel referred to the documents annexed with the writ petition as also the stand taken by the HSIIDC in its written statement and the documents attached therewith and submitted that the action of the HSIIDC is not sustainable.

13.    Mr.  Ankur  Mittal,  learned  counsel  representing  HSIIDC,  however, submitted that the action of HSIIDC is in accordance with the order dated 20.09.2013 as also the provisions of the RLA and the EMP 2011. Reference was made to the terms  and  conditions  of  the  RLA  and  more  particularly  Clause  2(iv)  as  also  to Chapter 6 of the EMP 2011 and it was submitted that the deduction had been made in accordance  with  the  said  conditions.  It  was  also  submitted  that  the  order  dated

20.09.2013 was not applicable to the petitioner since the request of the petitioner as also the decision on the same was much prior to the decision which was conveyed vide order dated 20.09.2013. Learned counsel also submitted that no other similarly

situated persons had been granted the full refund and only people who had applied in pursuance to the order dated 20.09.2013, refunds were made in terms of the same.

14.    We have considered the submissions made by learned counsel for the parties.

15.    The RLA is on record as Annexure P-1. The disputed plot bears plot No.45 situated in Sector-53, Phase-V, Industrial Estate, Kundli, District Sonipat. It was allotted for setting up of an industrial project of manufacturing of auto parts. Offer of physical possession was given in the RLA itself. The disputed plot measured 11250 square meters and the tentative price was Rs.6,18,75,000/- @ Rs.5500/- per square meters. The schedule of payment was duly given in the RLA. Clause 2(iv) provided as under;

"Apart from fulfilling the conditions precedent as specified at 2(i) & 2(ii) above, you shall also be re?uired to execute an Agreement, in writing, with HSIIDC, at Panchkula, incorporating therein the terms & conditions,  as  contained  in  Appendix-A,  on  the  printed  agreement, attached with the RLA. This period of 60 days allowed for execution of the agreement will, however, be extendable further by HSIIDC at its sole discretion, but incase, after fulfilling any of the conditions precedent as specified at 2(i) & 2(ii) above, you fail to execute the agreement within the extended period, the allotment shall become liable to be cancelled and the principal amount received towards the tentative price shall be refundable to you without any interest; after forfeiting 10% of the total tentative price of the aforesaid plot/shed. Any amount paid to HSIIDC on account of interest and/or penal interest, as the case may be, shall be non-refundable.

16.    The terms and conditions in the format of agreement was also attached as Annexure-A alongwith the RLA. As per the agreement which is stated to have been executed between the parties, the project for which the plot had been allotted was  to  be  implemented  within  a  period  of  03  years  from  the  date  of  offer  of possession which was given alongwith the RLA but in the agreement, it was stated

that the same would be operative from the date of execution of the agreement. It was also  specified  that  implementation  of  the  project  would  mean  commencement  of commercial production after coverage of construction in accordance with the norms specified in the EMP 2011 and installation of plant and machinery. It appears that on account of the slowdown, vide communication dated 12.07.2013, a request was made by  the  petitioner  to  surrender  the  plot.  It  was  requested  that  the  allotment  be cancelled  and  the  amount  be  refunded.  Notably,  this  letter  was  submitted  on

12.07.2013 i.e. more than 04 years after the allotment of the plot. It, therefore, means that no construction was carried out within the stipulated period of 03 years. Here, it would be apposite to refer to the averments made in the written statement as regards issuance  of  show  cause  notices  to  the  petitioner  on  account  of  non-construction, which, for obvious reasons has not been disclosed in the writ petition. As per the written  statement,  the  physical  possession  was  handed  over  to  the  petitioner  on

25.11.2010 and an undertaking was given by the petitioner on 27.06.2011 (Annexure R-5) that it accepted the provisions of EMP 2011. Upon inspection of the site, a site report dated 12.10.2012 was submitted to HSIIDC in which it was stated that the disputed plot was lying vacant and that the petitioner had also failed to pay a sum of Rs.58,15,299/-  on  account  of  interest  and  delayed  interest  as  on  31.10.2012. Accordingly, show cause notice dated 22.10.2012 (Annexure R-5) was issued. The petitioner is stated to have been given an opportunity of hearing also on 29.11.2012, wherein the petitioner assured that the outstanding amount would be paid within 15 days.  However,  since  the  same  was  not  done,  further  show  cause  notices  dated

29.01.2013, 11.04.2013 and 11.07.2013 (Annexure R-6 Colly.) were issued. It is, therefore, clear that the request for surrender was not immediate but was after more than 04 years of the allotment of the disputed plot and after having received a number of show cause notices for non-construction and non-payment.

17.    Clause 6.2 of EMP 2011 deals with surrender of plots and reads as thus; "A. Surrender of Plots/ sheds:

6.2  Keeping  in  view  that  a  number  of  factors  impact  the establishment  of  a  business  in  a  dynamic  business  environment,  it  is recognized that the plans for establishment of a business may undergo a change and the allottee may review and reconsider his plans to carry on with the establishment of the intended business. In such situations, the allottees  will  have  the  option  to  surrender  the  plots/sheds  allotted  to them.  The  re?uests  for  surrender  of  plots/sheds  will  be  regulated  as under:

i)  Wherever  an  allottee  surrenders  the  plot/  shed  at  anytime within a period of two years of allotment, the Corporation will refund the full principal amount paid by the allottee in such cases, without any interest, within a period of 30 days of the receipt of surrender re?uest.

ii) Wherever an allottee surrenders the plot/shed within the third year of allotment the Corporation will refund the principal amount paid by the allottee without any interest, after deduction of 5% of the price of the  plot/shed,  within  a  period  of  30  days  of  receipt  of  the  surrender re?uest.

iii)  Any  surrender  of  plot  after  completion  of  three  years  of allotment will entail deduction of 10% of the price of plot/shed."

As per the same, any surrender of plot after completion of 03 years of allotment would entail deduction of 10% of the price of the plot. If one reads Clause 2(iv) of the RLA in conjunction with Clause 6.2 of EMP 2011, it emerges that the surrender of a plot was to entail a deduction of 10% price of the plot alongwith interest etc. In fact, Clause 2(iv) of the RLA clearly lays down that any amount paid to HSIIDC on account of interest and/or penal interest would be non-refundable in such cases.

18.    Coming to the order dated 20.09.2013, it has specifically been stated in the written statement and not controverted in the replication by any document that the case of the petitioner would not be covered by the said order as the petitioner had submitted his request for surrender on 12.07.2013 and the same was accepted by HSIIDC on 06.08.2013 which was much before the decision dated 29.08.2013 taken by  the  Board  of  Directors  and  conveyed  on  20.09.2013.  Even  the  amount  was

refunded to the petitioner on 02.09.2013 i.e. much prior to 20.09.2013. Even if the amount was refunded after the decision dated 29.08.2013, the same would not make a difference  because  firstly,  the  application,  as  already  stated  was  moved  by  the petitioner on 12.07.2013 and was accepted by HSIIDC on 06.08.2013. Still further, it has specifically been mentioned in the order dated 20.09.2013 that the cases already decided in the past where extension fee had been remitted or surrender request had been considered after deduction of 10% amount would not be reopened; "v) That the case already decided in the past where the extension fee had already been remitted by the allottee or surrender re?uest had been  considered  by  the  corporation  after  deduction  of  10%  amount, shall not be re-opened."

19.    Still  further,  the  details  of  the  amount  paid  by  the  petitioner  and deducted by HSIIDC have also been furnished in the written statement; "Total Cost of the Plot-          Rs.6,18,75,000.00 Towards 10% application money-      Rs.65,82,500.00 Towards 25% plot cost-          Rs.1,20,00,000.00 Towards balance 25% plot cost-        Rs.35,13,160.00 Towards interest due up to re-schedulement-    Rs.47,47,662.00 Amount deposited till change of plot-      Rs.2,68,43,322.00 Balance  principal  cost-Rs.6,18,75,000.00-Rs.2,68,43,322.00=Rs.3,50,31,678 Total amount deposited including installments-  Rs.4,59,78,837.00 10% of plot cost deducted-        Rs.61,87,500.00 Interest and delayed interest-        Rs.59,93,450.00 Refundable amount after deduction-      Rs.3,37,97,887.00"

As per the same, the refundable amount came to Rs.3,37,97,887/- which was duly paid to the petitioner.

20.    No doubt, the deduction of more than Rs.1.20 crores would definitely hurt and pinch the petitioner. However, the same had been done in accordance with the provisions of the RLA, the EMP 2011 and from the above discussion, the order PRINCE CHAWLAdated  20.09.2013  does  not  apply  to  the  petitioner.  In  so  far  as  the  HSIIDC  is

concerned, it is bound by the various terms and conditions of the RLA, EMP 2011 and the decision taken by its authorities. A cut-off date has to be there for everything. There will always be people on either side of the cut-off date who would feel the pinch and would contend that they were very near to the cut-off date. However, this would not entitle them to any relaxation because a cut-off date has to be fixed under all circumstances.

21.    There is another aspect of the matter. The petitioner has averred in the writ petition and it was also contended during the arguments and this was the precise contention at the time of issuance of notice of motion on 05.03.2019 that many other similarly situated persons had been granted a complete refund. However, not even a single instance has been brought on record nor has any such instance been produced before the Court which could have given strength to the case of the petitioner. Under the circumstances, the stand that such relief had been granted to many other similarly situated persons falls to the ground.

22.    No policy/instructions have also been brought to the notice of the Court vide which  the  forfeiture  amount  could have  been reduced or waived off  by  the respondents at the relevant time.

23.    From the totality of the facts and circumstances as have been discussed and noticed in the preceding paragraphs, it emerges that the claim of the petitioner is devoid of merit. In view of the same, we do not find any merit in the instant writ petition and the same is accordingly dismissed.

(ARUN PALLI)                    (VIKRAM AGGARWAL) JUDGE                                   JUDGE

Pronounced on: 18.09.2024 Prince Chawla Whether speaking/reasoned :     Yes/No. PRINCE CHAWLA Whether reportable :       Yes/No.

Case details

Parties and counsel

IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH CWP-5903-2019 Reserved on: 14.08.2024 Pronounced on: 18.09.2024 Kafila Forge Limited ….Petitioner Versus State of Haryana and Another .....Respondents CORAM: HON'BLE MR. JUSTICE ARUN PALLI HON'BLE MR. JUSTICE VIKRAM AGGARWAL Present: Mr. Vijay Pal, Advocate for the petitioner. Mr. Ankur Mittal, Addl. A.G., Haryana with Ms. Kushaldeep Kaur, Advocate and Ms. Siddhanth Arora, Advocate. ****

Source: High Court of Punjab and Haryana, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.