VoxJuris
Home › High Courts › Sikkim High Court 2026 › High Court of Sikkim

Union of India v. M/S Mahabir Prasad Agarwal

Dismissed
Court
High Court of Sikkim
Decided
12 May 2026
Bench
The Chief Justice Mr. A. Muhamed Mustaque, Bhaskar Raj Pradhan
Case no.
Arb.A. 11/2025

Judgment

J U D G M E N T

A. Muhamed Mustaque, C.J.

This is an appeal filed by the Union of India challenging judgment dated 09.07.2025 passed by the learned Commercial Court, Gangtok in an application filed under Section 34 of the

Arbitration and Conciliation Act, 1996 (hereinafter referred to as the Act), refusing to set aside the award of the Arbitral Tribunal.

¶2In a matter arising out of a contract between the Appellant and the Respondent, a dispute arose as to the entitlement of payment claimed by the Respondent for the disposal of surplus material beyond 1000 meters lead.

¶3Consequent upon appointment of an Arbitrator by this Court, the dispute was adjudicated by Justice Pranab Kumar Chattopadhyay, retired Judge of Calcutta High Court as a Sole Arbitrator. The arbitral award is a sum of ₹7,48,74,932.80 payable with interest @9% per annum from the date of filing the statement of claims till the date of the award.

¶4Aggrieved by the award, the Appellant filed an application to set aside the award invoking Section 34 of the Act before the learned Commercial Court, Gangtok but the learned Commercial Court declined to interfere.

¶5Learned Deputy Solicitor General of India, Ms. Sangita Pradhan, assailing the Judgment of the learned Commercial Court, Gangtok, argued that the Sole Arbitrator committed manifest error in allowing the claim of muck disposal without cogent evidence and overlooking conditions of contract. Elaborating the argument, the learned Deputy Solicitor General of India submits that the site for disposals was identified by the State Government of Sikkim and further pointed out that by Annexure A3, contractor therein was intimated that no extra payment shall be made for disposal of muck other than the specified site identified by the State Government of Sikkim.

¶6On the other hand, learned Senior Counsel Mr. Jorgay Namka appearing for the Respondent, submits that the Arbitrator awarded and allowed the claim stating reasons and Annexure A3 was never produced before the Arbitrator. It is submitted that there was no dispute about the disposal of muck beyond the last point of the road beyond 19.35 kilometers and it was measured by the Officers of the Appellant. It is submitted that the amount was also calculated in accordance with the Military Engineering Services Standard (Schedule of Rates), 2010. It is argued that the Appellant failed to provide a muck dumping yard within the 1000 meters as agreed in the contract.

¶7The question is whether the Arbitral Tribunal passed the award confining the dispute arose out of contract or not.

¶8On going through the award, it can be seen that the contractor executed the work based on the terms and conditions of contract. The learned Sole Arbitrator appreciated the evidence based on the contract entered between the parties. Though, there was an alleged delay on the part of the Respondent in execution of the work, the Arbitral Tribunal appreciated the evidence and found that there was no fault on the part of the Respondent.

¶9Though the Respondent raised several claims, the Arbitral Tribunal allowed claim no.3, which was the claim for additional cost incurred on muck dumping lead and financial charges. As per the terms of the contract, the lead for disposal or dumping such soil and rocks is supposed to be within 1000 meters. The Tribunal relied on Clause 4.3.8 of the particular specifications of Statement of Claims and Clause 301.3.11 of MORT&H specifications of road and bridge

works. MORT&H provides for measurement and method of computing claim of disposal of muck beyond 1000 meters lead. It is not a dispute that these specifications do not apply. Anyway, as agreed by the parties, the dumping act shall be within 1000 meters. If the dumping is beyond 1000 meters, as agreed in the contract, questions then arise whether specifications prescribed by the MORT&H as such for dumping beyond 1000 meters would apply or not.

¶10It has come out through the evidence that muck dumping areas were beyond 19.8 KM, at 20.60 KM, KM 23.50 and KM 23.70, calculated at average areas of 21.9 KM.

¶11We may not have a doubt that even in the absence of MORT&H specifications, principles of Quantum Meruit would apply unless specifically excluded by the contract. MORT&H specifications in fact have to be read along with the other specifications of the contract unless specifically excluded.

¶12An attempt was made by the learned Deputy Solicitor General of India to rely upon Annexure A3. We find no justification to consider the same, as it has been produced for the first time through an application under Section 34 of the Act. Even assuming that Annexure A3 merely reiterates the contractual terms, it does not advance the case of the Appellant. The clause of the contract referred to in the said Annexure stipulates that the contractor shall utilize materials obtained from excavation for purposes such as filling road embankments, existing pits, landscaping, etc., for which no extra payment shall be made. However, the present dispute does not fall within the ambit of that clause. The issue in question

pertains to the transportation of such materials beyond a lead of 1000 meters, as agreed, for dumping purposes.

¶13The scope of dispute before the Arbitral Tribunal cannot be enlarged by producing certain documents along with the application under Section 34 of the Act.

¶14The Arbitral Tribunal confined the scope of inquiry within the subject of contract.

¶15The learned Commercial Court found in the application under Section 34 that there was no scope for interference.

¶16In an Appeal, our scope of inquiry is limited and we cannot enter into an exercise for re-appropriation of evidence like a normal Appellate Court. The question is only that the matter is confined to the parameters under Section 34.

¶17The learned Commercial Court, rightly looking into the Arbitral Tribunal award found that no case is made out for interference invoking under Section 34.

¶18We affirm the order and dismiss the Appeal.

¶19Trial Court records shall be remitted back to the learned Commercial Court, Gangtok.

(Bhaskar Raj Pradhan) (A. Muhamed Mustaque) Judge

Chief Justice

Approved for Reporting:

ami

Case details

Parties and counsel

THE HIGH COURT OF SIKKIM: GANGTOK (Civil Appellate Jurisdiction) ---------------------------------------------------------------------------------- DIVISION BENCH: THE HON'BLE MR. JUSTICE A. MUHAMED MUSTAQUE, CHIEF JUSTICE THE HON'BLE MR. JUSTICE BHASKAR RAJ PRADHAN, JUDGE --------------------------------------------------------------------------------- ARB. A. No. 11 of 2025 Union of India, Represented by the Chief Engineer (P) Swastik C/O. 99 APO Pin: 931717 Email: bro-swtk@nic.in .... Appellant versus M/s Mahabir Prasad Agarwal 1 AA, Government Contractor Namchi Bazar, South Sikkim, Sikkim, Pin: 737126 Email: vikashalto@yahoo.in ..... Respondent --------------------------------------------------------------------------- Appearance: Ms. Sangita Pradhan, Deputy Solicitor General of India (through V.C.) with Mr. Amit Kumar Sharma, Advocate, for the Appellant. Mr. Jorgay Namka, Senior Advocate with Mr. Lahang Limboo, Advocate for the Respondent. ------------------------------------------------------------------------------- Date of Hearing : 24.04.2026 Date of Judgment : 12.05.2026 Date on which uploaded : 12.05.2026 ----------------------------------------------------------------------------

Source: High Court of Sikkim, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.