JUDGMENT & ORDER(ORAL)

Heard learned counsel for the respective parties. These appeals arise in common background. Since facts and issues are identical,

they have been heard together and would be disposed of by this common judgment. In L.A. APP. No.52 of 2021

[2]

The Government of Tripura had acquired the land measuring

0.10 acres under plot No.2755 of khatian No.5096 under Mouja-Bishalgarh, Sub-Division-Bishalgarh, Sepahijala District belonging to the claimant by a notification No.F.09(05)/REV/ACQ/XIV/11 dated 27.07. 2011 for the purpose of construction of "New Rail Line" from Agartala to Sabroom. The L.A. Collector, West Tripura awarded an amount of Rs.3,71,423/- for the acquired land including all statutory benefits. Dissatisfied with the same, the claimant filed a reference before learned L.A. Judge who after hearing both sides and appreciating evidence on record awarded an amount of Rs.17,50,000/- per kani for the acquired In L.A. APP. No.05 of 2022

[3]

The Government of Tripura had acquired the land measuring

0.06 acres under plot No.2538/13681 of khatian No.6630 of Mouja-Bishalgarh, Sub-Division-Bishalgarh, Sepahijala District belonging to the claimant by a notification No.F.09(05)/REV/ACQ/XIV/11 dated

4/5.07.2011 for the purpose of construction of "New Rail Line" from Agartala to Sabroom. The L.A. Collector, West Tripura awarded an amount of Rs.2,22,854/- for the acquired land including all statutory benefits. Dissatisfied with the same, the claimant filed a reference before learned L.A. Judge who after hearing both sides and appreciating evidence on record awarded an amount of Rs.14,00,000/- per kani for the acquired In L.A. APP. No.06 of 2022

[4]

The Government of Tripura had acquired the land measuring

0.03 acres under plot No.217/24325 of khatian No.6923 under Mouja-Bishalgarh, Sub-Division-Bishalgarh, Sepahijala District belonging to the claimant by a notification No.F.09(02)/REV/ACQ/XIV/11 dated 23.06. 2011 for the purpose of construction of "New Rail Line" from Agartala to Sabroom. The L.A. Collector, West Tripura awarded an amount of Rs.1,01,569/- for the acquired land including all statutory benefits. Dissatisfied with the same, the claimant filed a reference before learned L.A. Judge who after hearing both sides and appreciating evidence on record awarded an amount of Rs.12,00,000/- per kani for the acquired

[5]

It is represented by the learned counsel for the appellant that in the identical matter, viz. in LA APP No.53 of 2021 titled as The Deputy Chief Engineer (Construction), N.F. Railway versus Smt. Swapna Das and another vide judgment and order dated 09.01.2023 this Court had earlier taken a view in favour of the claimant and confirmed the award passed by the Court below and dismissed the appeal. The counsel for the appellant in all fairness has placed the copy of the said judgment and prayed to pass similar order. For convenience of fair adjudication of the present appeals, operative portion of the judgment and order dated

09.01.2023 passed in LA APP No.53 of 2021 is extracted hereinbelow:

"Accordingly, the present appeal filed by the appellant is dismissed and the award dated 28.02.2020 passed by the learned Land Acquisition Judge, Sepahijala District, Bishalgarh in Misc. (L.A) 24 of 2015 is affirmed. Send down the LCRs forthwith."

[6]

In view of the same, all these appeals are disposed of making the directions contained therein applicable mutatis mutandis to the present cases also. Resultantly, all the appeals stand dismissed confirming the awards passed by the learned L.A. Judge. The claimant-respondents are

entitled to compensation at such rates and on such terms as stands determined by the trial Court. Needless to add, the amount of compensation if not already released be positively released in favour of the claimant-respondents unconditionally.

[7] Stay order, if any, stands vacated.

Send down the lower court records forthwith.

Pending application(s), if any, also stands disposed of.

CHIEF JUSTICE (ACTING)

Pulak

Case details

Parties and counsel

HIGH COURT OF TRIPURA AGARTALA L.A. APP. No.52 of 2021 The Deputy Chief Engineer (Construction), N.F. Railway ----Appellant(s) Versus Sri Kanti Das and another ----Respondent(s) L.A. APP. No.05 of 2022 The Deputy Chief Engineer (Construction), N.F. Railway ----Appellant(s) Versus Sri Mihir Acharjee and another ----Respondent(s) L.A. APP. No.06 of 2022 The Deputy Chief Engineer (Construction), N.F. Railway ----Appellant(s) Versus Sri Niranjan Bir and another ----Respondent(s) For Appellant(s) : Mr. Asutosh De, Advocate. For Respondent(s) : Mr. P. Gautam, Advocate. HON'BLE THE CHIEF JUSTICE(ACTING) Date of hearing and judgment : 13th January, 2023.

Source: High Court of Tripura, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.