Section 8: Hydro-electric generation

(1) Notwithstanding anything contained in section 7, any generating company intending to set up a hydro-generating station shall prepare and submit to the Authority for its concurrence, a scheme estimated to involve a capital expenditure exceeding such sum, as may be fixed by the Central Government, from time to time, by notification.

(2) The Authority shall, before concurring in any scheme submitted to it under sub-section (1) have particular regard to, whether or not in its opinion,—

(a) the proposed river-works will prejudice the prospects for the best ultimate development of the river or its tributaries for power generation, consistent with the requirements of drinking water,irrigation, navigation, flood-control, or other public purposes, and for this purpose the Authority shall satisfy itself, after consultation with the State Government, the Central Government, or such other agencies as it may deem appropriate, that an adequate study has been made of the optimum location of dams and other river-works;

(b) the proposed scheme meets the norms regarding dam design and safety.

(3) Where a multi-purpose scheme for the development of any river in any region is in operation, the State Government and the generating company shall co-ordinate their activities with the activities of the persons responsible for such scheme in so far as they are inter-related.

Source: India Code (indiacode.gov.in), the consolidated text published by the Legislative Department, Government of India. Text as updated on India Code on 14 October 2026. Words in square brackets [ ] were inserted or substituted by later amending Acts, and *** marks words omitted by an amendment. The amendment footnotes are not reproduced here. Official text on India Code.